Registered No litigation declared Residential / Group Housing project

Siddharth Enclave

By Siddharth Developers

RG-MH-55992 · RERA P51900001979 · Last updated on MahaRERA portal: 30 Aug 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 84 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2026Possession promisedmoved 84 months from the original
9 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 98%
4 of 68Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

Siddharth Enclave is a Residential / Group Housing project by Siddharth Developers in Lower Parel, 400013, registered with MahaRERA as P51900001979 on 31 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 84 months from the original filing. 64 of the 68 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSiddharth Enclave
  • TypeResidential / Group Housing
  • Location
    • Sitaram Jadhav Marg
    • Lower Parel
    • 400013
  • Pincode400013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900001979
  • ReraGenie IDRG-MH-55992

Builder

  • NameSiddharth Developers
  • Entity typePartnership
  • PartnersBharat Shah, Kishor Rathod, Raju Rathod, Jignesh Kothari
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Jul 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed69 files

Current status

94%64 of 68 units booked
102.4%Work done, per cost certificate

Figures as on 30 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WingNA161258058
C WingNA10610010

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 98%.

B Wing87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor97%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
C Wing89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor97%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 30 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes98%
Storm Water DrainsYes98%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes97%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed38

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots38
Closed/Covered32
Open Space6
BuildingClosed/CoveredOpen SpaceTotal
B Wing25328
C Wing7310

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,322 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Aug 2025

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI7356.96
Proposed, not sanctioned7,132 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNanik Motwani Marg Fort Mumbai
Estimated costRs 42.55 cr
Cost incurredRs 43.57 cr
Work done102.4%
BuildingWingEstimatedIncurred
B WingNARs 22.48 crRs 22.48 cr
C WingNARs 17.94 crRs 18.91 cr
-NARs 2.13 crRs 2.18 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMS Wairkar and Associates
EngineerMS Consultants & Engineers
Chartered AccountantB B Jain & Associates
Chartered AccountantVINOD PATIL & ASSOCIATES
PartnerRole in project
Siddharth Developers-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900016976Dec 2019 → Jun 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 72.13% allottees for purpose of extension of RERA registration period of the said project

EXT51900003858Dec 2019 → Dec 2020

Reason as filed by the promoterThe promoter states that Phase I of the Building i.e. Siddharth Enclave is almost completed as per current approved plan. Phase II consist of additional 2 floors on sale building and the same will be sanctioned by the MCGM upon available of 9 mtrs. access road. The Promoter has already obtained requisite consent from the prospective purchasers. The Promoter further states that One of the I.O.D. condition is that 9.00 mtr. wide access road is required and the same is the condition for issuance of CFO NOC. Once the CFO NOC is issued then only we can apply for Occupation Certificate. In view ther

EXT51900010458Dec 2019 → Dec 2022

Reason as filed by the promoterDue to failure of handing over the road set back area by adjoining property having C.S. No. 211 and 212, the C.F.O. NOC is not being issued in terms of compulsory 9 meter R.L. Road which is at present 6 meter. we have sold 57 flats out of 68 flats and taken consent of 38 flats i.e. 67%. kindly issue the extension certificate.

EA30082502478Dec 2019 → Dec 2026

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000198958Kamlakar N ShanbhagSiddharth Developers09/11/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Sep 2022

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 as on 30062025.pdf30 Aug 2025
Withdrawal Update Form 2File: Form 2 as on 2022.pdf30 Aug 2025
Withdrawal Update Form 3File: Form 3 as on 30062025.pdf30 Aug 2025
Certificates of CA (Form 3)File: CA Certificate siddharth enclave sept 2024.pdf10 Jan 2025
Certificates of CA (Form 3)File: CA Certificate.pdf10 Oct 2024
Certificates of CA (Form 3)File: CA Certificate.pdf10 Oct 2024
Certificates of CA (Form 3)File: CA Certificate March2024.pdf20 Jun 2024
Certificates of CA (Form 3)File: Form 3 Sep 2023.pdf20 Dec 2023
Certificates of CA (Form 3)File: CA certificate June 2023.pdf22 Sep 2023
Certificates of CA (Form 3)File: CA Certificate march 23 enclave.pdf13 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate December 2022.pdf26 Apr 2023
Certificates of CA (Form 3)File: CA Certificate.pdf3 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Siddharth Enclave - 2021 - 2022.pdf16 Feb 2023
Certificates of CA (Form 5)File: Form 5 - Siddharth Enclave - 2021 - 2022.pdf1 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 SD Sept 21.pdf1 Feb 2023
Certificates of CA (Form 3)File: CA Certificate siddharth enclave sept 2022.pdf7 Jan 2023
Certificates of CA (Form 3)File: march.pdf7 Sep 2022
Certificates of CA (Form 3)File: june 22.pdf7 Sep 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC.pdf7 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Dec 2021.pdf23 Mar 2022
Certificates of CA (Form 3)File: CA Certificate DEC 2021.pdf14 Mar 2022
PAN CardFile: SIDDHARTH DEVELOPERS-pan card.pdf31 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf31 Dec 2021
Certificates of CA (Form 3)File: CA Certificate sept 2021.pdf31 Dec 2021
Certificates of CA (Form 5)File: Form 5 SD Sept 21.pdf31 Dec 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architact certificate.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate March 2021.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate June 2021.pdf14 Aug 2021
Certificates of CA (Form 3)File: C A Certificate March 2021.pdf14 Aug 2021
Certificates of CA (Form 3)File: C A Certificate June 21.pdf14 Aug 2021
Declaration about Commencement CertificateFile: Form D.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assuarnce Certificate Siddharth Enclave.pdf28 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf28 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Certificates of CA (Form 5) (2).pdf28 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Siddharth Form 5.pdf28 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf12 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf12 Apr 2021
Certificates of CA (Form 3)File: CA Certificate.pdf12 Apr 2021
Certificates of CA (Form 3)File: CA Certificate.pdf12 Apr 2021
Certificates of CA (Form 3)File: CA Certificate June 2020.pdf2 Oct 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate March-2020.pdf30 Sep 2020
Certificates of CA (Form 3)File: CA Certificate March 2020.pdf30 Sep 2020
Certificates of CA (Form 3)File: CA Certificatre.pdf23 Dec 2019
Certificates of CA (Form 5)File: Form -5.pdf13 Dec 2019
OtherFile: Form -5.pdf13 Dec 2019
Certificates of CA (Form 3)File: Siddharth Developers C A Certificate June 2019.pdf7 Aug 2019
Certificates of CA (Form 3)File: C A Certificate March 19.pdf6 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate March 2019.pdf4 Jun 2019
Certificates of CA (Form 5)File: siddharth enclave form 5.pdf30 Sep 2018
Declaration in FORM BFile: Form B Siddharth Enclave.pdf30 Mar 2018
Details of encumbrancesFile: indiabulls mortgage deed (1).pdf28 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf28 Mar 2018
Proforma of Allotment letterFile: Siddharth Enclave RERA Agreement.pdf28 Mar 2018
Building plan approvalFile: 9 10th floor.pdf29 Jul 2017
Building plan approvalFile: 11th 12th floor.pdf29 Jul 2017
Building plan approvalFile: typical plan.pdf29 Jul 2017
Layout approvalFile: Layout plan.pdf29 Jul 2017
Copy of the legal title reportFile: Title certificates.pdf29 Jul 2017
Details of encumbrancesFile: Mortgage deed.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout plan.pdf29 Jul 2017
Building Plan Approval (IOD)File: 9 10th floor.pdf29 Jul 2017
Building Plan Approval (IOD)File: 11th 12th floor.pdf29 Jul 2017
Building Plan Approval (IOD)File: typical plan.pdf29 Jul 2017
Declaration in FORM BFile: FORM B Siddharth Enclave Declaration.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - SD.pdf29 Jul 2017
Certificates of CA (Form 3)File: FORM 3 CA Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: Decleration of Agreement.pdf29 Jul 2017
OtherFile: Decleration letter.pdf29 Jul 2017

Keep Siddharth Enclave on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lower Parel

2 kmSiddharth EnclaveCompleted 22Lapsed / revoked 12Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 45 registered projects within 2 km.

Builder: Siddharth Developers

SIDDHARTH DEVELOPERS has 4 registrations on MahaRERA, including SPRING DIVISHA and SPRING PARSHWA. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record.

Frequently asked questions

What are my rights if Siddharth Enclave is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Siddharth Enclave?

The registered promoter entity is Siddharth Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Siddharth Enclave?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Siddharth Enclave?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Siddharth Enclave?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Siddharth Enclave?

The professionals named in the filing: Architect: MS Wairkar and Associates; Engineer: MS Consultants & Engineers; Chartered Accountant: B B Jain & Associates; Chartered Accountant: VINOD PATIL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Siddharth Enclave?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Siddharth Enclave. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Siddharth Enclave to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.