ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / SHYAM ICONIC

Registration lapsed No litigation declared Others project

SHYAM ICONIC

By NEETA MEHULKUMAR VAGHELA

RG-MH-55520 · RERA P51600050372 · Last updated on MahaRERA portal: 27 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
8 of 11Construction stages donefurthest along: Internal walls, 86%
22 of 32Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

SHYAM ICONIC is a Others project by NEETA MEHULKUMAR VAGHELA in Nashik, Maharashtra, registered with MahaRERA as P51600050372 on 5 Apr 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 10 of the 32 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHYAM ICONIC
  • TypeOthers
  • Location
    • PUJYA SRI SRI RAVISHANKAR MARG
    • WADALA SHIVAR
    • Nashik (M Corp.)
    • Nashik
    • 422006
  • Pincode422006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600050372
  • ReraGenie IDRG-MH-55520

Builder

  • NameNEETA MEHULKUMAR VAGHELA
  • Entity typeIndividual
  • Declared earlier projects2 →

Key dates

10 months past promisethis monthRegisteredApr 2023PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Apr 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed60 files

Current status

31%10 of 32 units booked
86.1%Work done, per cost certificate

Figures as on 27 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHYAM ICONICNA8826632

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 86%.

SHYAM ICONIC: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed123

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots123
Open Space123

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,020 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
Declared on9 Jun 2025
LandownerVillageDistrict
RAHUL TUKARAM BORADENashik (M Corp.)Nashik

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI3857.64
Proposed, not sanctioned3,858 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPANCHAVATI NASIK
Estimated costRs 7.50 cr
Cost incurredRs 6.46 cr
Work done86.08%
BuildingWingEstimatedIncurred
SHYAM ICONICNARs 7.50 crRs 6.46 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANISH JADHAV P JADHAV
EngineerMILIND RATHI R RATHI
EngineerATUL SADASHIV KATARE
Chartered AccountantSONALI R GUJARATHI RANDHIR GUJARATHI
Chartered AccountantRANDHIR DWARKADAS GUJARATHI
PartnerRole in project
NEETA MEHULKUMAR VAGHELA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1.pdf27 Jan 2026
Withdrawal Update Form 2File: form 2.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3_compressed.pdf27 Jan 2026
Withdrawal Update Form 1File: form -1.pdf19 Nov 2025
Withdrawal Update Form 2File: form -2.pdf19 Nov 2025
Withdrawal Update Form 3File: form -3.pdf19 Nov 2025
Form 5 (FY 2024-2025)File: form -5 24-25.pdf13 Nov 2025
Withdrawal Update Form 1File: form -1 iconic 30-6-25.pdf28 Jul 2025
Withdrawal Update Form 2File: form-2 iconic 30-6-25.pdf28 Jul 2025
Withdrawal Update Form 3File: form -3 30-6-25.pdf28 Jul 2025
Form 1File: form 1.pdf28 May 2025
Form 2File: form 2.pdf28 May 2025
Form 3File: Form-3.pdf28 May 2025
Form 1File: form 1.pdf28 May 2025
Form 2File: form 2.pdf28 May 2025
Form 3File: Form-3.pdf28 May 2025
Form 1File: form 1.pdf28 May 2025
Form 2File: form 2.pdf28 May 2025
Form 3File: Form-3.pdf28 May 2025
Form 1File: form 1.pdf28 May 2025
Form 2File: form 2.pdf28 May 2025
Form 3File: Form 3.pdf28 May 2025
OthersFile: Form-5 23-24.pdf28 May 2025
Form 1File: form 1.pdf28 May 2025
Form 2File: form 2.pdf28 May 2025
Form 3File: Form 3.pdf28 May 2025
Form 2File: form 2.pdf28 May 2025
Form 1File: form 1.pdf28 May 2025
Form 3File: Form 3.pdf28 May 2025
Form 1File: Form 1 31102023.pdf28 May 2025
Form 2File: Form 2 31102023.pdf28 May 2025
Form 3File: Form 3 08122023.pdf28 May 2025
Self-declaration of Quarterly ProgressFile: Self Declaration.pdf28 May 2025
Form 5 (FY 2023-2024)File: Form-5 23-24.pdf28 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31102023.pdf8 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31102023.pdf8 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 08122023.pdf8 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf28 Mar 2023
Copy of the legal title reportFile: Title Report-Com.pdf4 Mar 2023
Proforma of Agreement for saleFile: Shyam Iconic AFS.pdf4 Mar 2023
Declaration in FORM BFile: Form B_NV.pdf22 Feb 2023
CERSAI detailsFile: CERSAI_Search_Report_200260900543_For_Asset_Based_Search_21_02_2023_13_38_10_727.pdf21 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Disclosure of Interest.pdf21 Feb 2023
Layout approvalFile: Layout Plan.pdf20 Feb 2023
Building plan approvalFile: BuildingPlan1.pdf20 Feb 2023
Building plan approvalFile: BuildingPlan2.pdf20 Feb 2023
PAN CardFile: pancard_1.pdf20 Feb 2023
Details of encumbrances concerned to FinanceFile: Encumbrances.pdf20 Feb 2023
Details of encumbrances concerned to LegalFile: Encumbrances.pdf20 Feb 2023
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf20 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: BuildingPlan1.pdf20 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: BuildingPlan2.pdf20 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate_compressed (1).pdf20 Feb 2023
Declaration about Commencement CertificateFile: Format-D.pdf20 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Feb 2023
Proforma of Allotment letterFile: Allotment Letter.pdf20 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format-A.pdf20 Feb 2023
Deviation Report with respect to Allotment letterFile: Deviation of AL.pdf20 Feb 2023
Deviation Report with respect to model copy of AgreementFile: Deviation of AFS.pdf20 Feb 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHYAM ORCHIDWADALA SHIVAR8CompletedDec 2019Sep 2019

How this compares with Nashik

31%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHYAM ICONIC on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WADALA SHIVAR4,100+ in Nashik

2 kmSHYAM ICONICCompleted 77Lapsed / revoked 18Other 71Dot size: filed unitsN

Filed coordinates, straight-line distance. 166 registered projects within 2 km.

Builder: NEETA MEHULKUMAR VAGHELA

NEETA MEHULKUMAR VAGHELA has 1 registration on MahaRERA, including SHYAM ICONIC. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that SHYAM ICONIC shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHYAM ICONIC is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHYAM ICONIC?

The registered promoter entity is NEETA MEHULKUMAR VAGHELA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHYAM ICONIC?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHYAM ICONIC?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHYAM ICONIC?

The professionals named in the filing: Architect: MANISH JADHAV P JADHAV; Engineer: MILIND RATHI R RATHI; Engineer: ATUL SADASHIV KATARE; Chartered Accountant: SONALI R GUJARATHI RANDHIR GUJARATHI; Chartered Accountant: RANDHIR DWARKADAS GUJARATHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHYAM ICONIC?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHYAM ICONIC. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHYAM ICONIC to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.