Home / Browse projects / Nashik, Maharashtra / SIGNIFICANT
SIGNIFICANT
RG-MH-13726 · RERA P51600027892 · Last updated on MahaRERA portal: 8 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 17 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SIGNIFICANT is a Residential / Group Housing project by IND DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600027892 on 14 Jan 2021. Possession is promised by 19 Nov 2026. The completion date has moved by 17 months from the original filing. 150 of the 266 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameSIGNIFICANT
- TypeResidential / Group Housing
- Location
- WADALA ROAD
- WADALA
- Nashik (M Corp.)
- Nashik
- 422006
- Pincode422006
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600027892
- ReraGenie IDRG-MH-13726
Builder
- NameIND DEVELOPERS
- Entity typePartnership
- GSTIN27AAHFI9469C1Z2
- PartnersShahid Gulam Mustufa Jin, Naz Dastagir Jin, Zarina Shahid Jin, Abdul Qadir Shahid Jin, Nizamuddin Gulam Mohiuddin Jin, Fariduddin Gulam Mohiuddin Jin, Mainuddin Mohyuddin Jin, Gulamdastagir Mustufa Jin, Imran Gulam Dastagir Jin
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Jan 2021
- Promised completion19 Nov 2026
- Revised completionRevised to 19 Nov 2026 (originally 30 Jun 2025)
- Buildings1 building record
- Documents filed110 files
Current status
Figures as on 8 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SIGNIFICANT | NA | 9 | 7 | 266 | 0 | 266 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SIGNIFICANT: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 8 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 100% |
Parking filed100
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SIGNIFICANT | NA | Rs 24.63 cr | Rs 22.46 cr |
| - | NA | Rs 1.82 cr | Rs 54.73 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRASHANT THEMASKAR |
| Engineer | CHETAN SONAWANE |
| Engineer | Muazzam Nazir Shaikh |
| Chartered Accountant | GIRISH LASI |
| Chartered Accountant | MS V R Mintri & Associates |
| Partner | Role in project |
|---|---|
| IND DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project has been completed, and the extension is being sought to facilitate necessary corrections and updates in the application. Upon completion of the required corrections, the application will be updated accordingly, following which the completion update will be submitted
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Dec 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 19 Nov 2026
Documents filed110
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate.pdf | 8 Sep 2026 |
| Withdrawal Update Form 3File: CA Certificate.pdf | 8 Sep 2026 |
| Form 5 (FY 2023-2024)File: RA-2022-23.pdf | 8 Sep 2026 |
| Form 5 (FY 2024-2025)File: RA-2022-23.pdf | 8 Sep 2026 |
| Form 5 (FY 2025-2026)File: RA-2022-23.pdf | 8 Sep 2026 |
| Form 2A (FY 2020-2021)File: Form 2A - March 21.pdf | 20 Aug 2026 |
| Form 2A (FY 2021-2022)File: Form 2A - March 22.pdf | 20 Aug 2026 |
| Form 2A (FY 2022-2023)File: Form 2A - March 23.pdf | 20 Aug 2026 |
| Form 2A (FY 2023-2024)File: Form 2A - March 24.pdf | 20 Aug 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - March 25.pdf | 20 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A - March 226.pdf | 20 Aug 2026 |
| Form 5 (FY 2021-2022)File: RA-2021-22.pdf | 20 Aug 2026 |
| Form 5 (FY 2020-2021)File: RA-2020-21.pdf | 20 Aug 2026 |
| Form 5 (FY 2022-2023)File: RA-2022-23.pdf | 20 Aug 2026 |
| Form 1File: AR June 24.pdf | 6 Jul 2026 |
| Form 2File: ER Certificate June 24.pdf | 6 Jul 2026 |
| Form 3File: CA - June.pdf | 6 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE - JUNE 24.pdf | 6 Jul 2026 |
| Form 2File: ER sep 24 significant.pdf | 6 Jul 2026 |
| Form 3File: CA- SEP 24.pdf | 6 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE - SEP 24.pdf | 6 Jul 2026 |
| Form 1File: AR - Sept 2024.pdf | 6 Jul 2026 |
| Form 1File: AR Dec 24.pdf | 6 Jul 2026 |
| Form 2File: ER dec 24.pdf | 6 Jul 2026 |
| Form 3File: significant CA dec 24.pdf | 6 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE - DEC 24.pdf | 6 Jul 2026 |
| Form 1File: AR june 25.pdf | 1 Oct 2025 |
| Form 2File: ER june 25.pdf | 1 Oct 2025 |
| Form 3File: CA june 25.pdf | 1 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - June 25.pdf | 1 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR.pdf | 1 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf | 1 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER.pdf | 1 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - March 25.pdf | 1 Jul 2025 |
| Form 1File: AR.pdf | 27 Jun 2025 |
| Form 2File: ER.pdf | 27 Jun 2025 |
| Form 3File: CA.pdf | 27 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 25.pdf | 27 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR June 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Sep 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Dec 24.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA - June.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA - June.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA- SEP 24.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: significant CA dec 24.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Certificate June 24.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER sep 24 significant.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER dec 24.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Significant -June 24.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE - SEP 24.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE - DEC 24.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_ Dec 23.pdf | 7 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_March 24.pdf | 7 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Dec 23.pdf | 7 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Mar 24.pdf | 7 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure - DEC 23.pdf | 7 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Q4.pdf | 7 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Q4.pdf | 7 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA AUDIT - 20-21.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA AUDIT - 21-22.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA AUDIT - 22-23.pdf | 8 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure - DEC 23.pdf | 27 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 30-11-23.pdf | 24 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Dec 23.pdf | 30 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - March 24.pdf | 30 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 18 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE (1).pdf | 3 Nov 2023 |
| Declaration in FORM BFile: FORM B.pdf | 11 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SIGNIFICANT 31-12-2022 updated.pdf | 11 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 22.pdf | 11 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 110 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SIGNIFICANT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WADALA4,100+ in Nashik
Filed coordinates, straight-line distance. 168 registered projects within 2 km.
Shree Parshwanath
Darshan Anil Lodha
Anandsagar Annex Phase 1 ( L and M Wing )
Ravi Mahajan Builders & Developers Pvt. Lt
SHREEJI INSPERIA
Shreeji Landmarks LLP
Pawa Blossom
Pawa Construction
Bait E Muhammad Phase 1
Onyx Constructions
SILVER PARK
MR SACHIN R BHATTAD AND HEMANT ARJUN HIRAN
See every Nashik project, with the district possession charts
Builder: IND DEVELOPERS
IND DEVELOPERS has 2 registrations on MahaRERA, including SIGNIFICANT and Solitaire. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if SIGNIFICANT is delayed beyond 19 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SIGNIFICANT?
The registered promoter entity is IND DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAHFI9469C1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SIGNIFICANT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SIGNIFICANT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SIGNIFICANT?
The professionals named in the filing: Architect: PRASHANT THEMASKAR; Engineer: CHETAN SONAWANE; Engineer: Muazzam Nazir Shaikh; Chartered Accountant: GIRISH LASI; Chartered Accountant: MS V R Mintri & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SIGNIFICANT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback