Home / Browse projects / Palghar, Maharashtra / SHUBHAPRADA

Registration lapsed No litigation declared Residential / Group Housing project

SHUBHAPRADA

By OJAS REALTORS

RG-MH-53450 · RERA P99000033216 · Last updated on MahaRERA portal: 3 May 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 18 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Apr 2025Possession promised18 months past this date
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 60%
0Complaints at MahaRERAon this registration
Jump to the 30 documents Report an error

SHUBHAPRADA is a Residential / Group Housing project by OJAS REALTORS in Palghar, Maharashtra, registered with MahaRERA as P99000033216 on 9 Feb 2022. Possession was promised by 15 Apr 2025 and is now 18 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSHUBHAPRADA
  • TypeResidential / Group Housing
  • Location
    • SHANI MANDIR ROAD
    • SHANI MANDIR
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401201
  • Pincode401201
  • RERA no.P99000033216
  • ReraGenie IDRG-MH-53450

Builder

  • NameOJAS REALTORS
  • Entity typePartnership
  • PartnersVIVEK VASANT KANE, AMIT VASANT KANE, CHIRAG PUSHPASEN KHOKHANI, NEENA AJAY KHOKHANI, HITUL MAHENDRA PATEL, PANKAJ SUBHASH MHATRE
  • Declared earlier projects3 →

Key dates

18 months past promisethis monthRegisteredFeb 2022First promiseApr 2024Revised toApr 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Feb 2022
  • Promised completion15 Apr 2025
  • Revised completionRevised to 15 Apr 2025 (originally 15 Apr 2024)
  • Buildings1 building record
  • Documents filed30 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHUBHAPRADANA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 60%.

SHUBHAPRADA: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area517 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1363.26
Proposed, not sanctioned1,363 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPAN KELA MARKET, HOLI, VASAI W 401201

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUM ARCHITECTS
EngineerPARESH UNNARKAR
Chartered AccountantVISHAL SANE
PartnerRole in project
OJAS REALTORS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000019595Apr 2024 → Apr 2025

Reason as filed by the promoterTHE WORK HAS BEEN SUSPENDED IN LIEU OF AN ORDER BY THE COMPETENT AUTHORITY RESPONDING TO A COMPLAINT. PROPER INVESTIGATION IN THIS MATTER IS BEING CARRIED OUT AND THE WORK SHALL RESUME IN ANOTHER COUPLE OF DAYS.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed30

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: FORM B RERA.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECTS CERTIFICATE 23- 24.PDF3 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - FOR 2023 - 24.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 2023 -24.pdf3 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ojas realtors Rera form 3 23 -24.pdf3 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ojas realtors Rera form 5 23 -24.pdf3 May 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY.pdf8 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A 2023 - Other Real Estate Project (2) - HItul Patel.pdf8 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A 2023 - Other Real Estate Project (2) Amit Kane.pdf8 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: OTHER REAL ESTATE - CHIRAG KHOKHANI.pdf8 May 2023
Proforma of Agreement for saleFile: AGREEMENT FORMAT SHUBHAPRADA.pdf8 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPERATE BANK AC.pdf8 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2021 - 22.pdf24 Jan 2023
Layout approvalFile: PLAN JUMBO.pdf20 Jan 2022
Building plan approvalFile: N A ORADER.pdf20 Jan 2022
PAN CardFile: PAN.pdf20 Jan 2022
Copy of the legal title reportFile: TITLE SEARCH - RERA FORMAT_compressed.pdf20 Jan 2022
Details of encumbrancesFile: LETTER OF ENCUMBRANCES.pdf20 Jan 2022
Copy of Layout Approval (in case of layout)File: PLAN JUMBO.pdf20 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: N A ORADER.pdf20 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: CC_compressed.pdf20 Jan 2022
Declaration about Commencement CertificateFile: DECLARATION - COMMENCEMENT CERT.pdf20 Jan 2022
Declaration in FORM BFile: FORM B.pdf20 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed.pdf20 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGINEER CERT.pdf20 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200229416239_For_Asset_Based_Search_03_02_2022_11_49_11_914.pdf20 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA CERT_compressed.pdf20 Jan 2022
Proforma of Allotment letterFile: LETTER OF ALLOTMENT.pdf20 Jan 2022
Proforma of Allotment letterFile: AGREEMENT FORMAT SHUBHAPRADA.pdf20 Jan 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
VAIJAYANTP99000027287SAGARSHET, Palghar-Dec 2020CompletedNov 2022Late, Dec 2023
SHIVARCHANOPP POLICE STATION34-CompletedOct 2019Late, Dec 2020
SHIVALIK A - B WINGOPP SBI36-CompletedJan 2017Late, Apr 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 12 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHUBHAPRADA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHANI MANDIR3,200+ in Palghar

Builder: OJAS REALTORS

OJAS REALTORS has 1 registration on MahaRERA, including SHUBHAPRADA. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that SHUBHAPRADA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHUBHAPRADA is delayed beyond 15 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHUBHAPRADA?

The registered promoter entity is OJAS REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHUBHAPRADA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHUBHAPRADA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHUBHAPRADA?

The professionals named in the filing: Architect: SUM ARCHITECTS; Engineer: PARESH UNNARKAR; Chartered Accountant: VISHAL SANE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHUBHAPRADA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHUBHAPRADA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHUBHAPRADA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.