ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Shubh Mangal

Registration lapsed No litigation declared Residential / Group Housing project

Shubh Mangal

By Rajpurohit Builders LLP

RG-MH-25590 · RERA P51800002774 · Last updated on MahaRERA portal: 19 Aug 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 80%
1Complaints at MahaRERAon this registration
Jump to the 32 documents Report an error

Shubh Mangal is a Residential / Group Housing project by Rajpurohit Builders LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002774 on 4 Aug 2017. Possession was promised by 29 Jun 2023 and is now 40 months past that date. The completion date has moved by 48 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameShubh Mangal
  • TypeResidential / Group Housing
  • Location
    • C.S.T. Road
    • Kalina
    • Santacruz East
    • Andheri
    • Mumbai Suburban
    • 400098
  • Pincode400098
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002774
  • ReraGenie IDRG-MH-25590

Builder

  • NameRajpurohit Builders LLP
  • Entity typeOthers
  • GSTIN27AATFR6167N1Z5
  • PartnersPradeep Ramkripal Mishra, Saurabh Kundan Borida Bordia
  • Designated PartnersShrem Karmvir Construction LLP NA, Ashtavinayak Highrise LLP NA

Key dates

40 months past promisethis monthRegisteredAug 2017First promiseJun 2019Revised toJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Aug 2017
  • Promised completion29 Jun 2023
  • Revised completionRevised to 29 Jun 2023 (originally 30 Jun 2019)
  • Buildings1 building record
  • Documents filed32 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shubh MangalNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 80%.

Shubh Mangal: 25% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor10%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered1
Open Space17

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area978 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityShri. Shivanand S Mendigeri -Asst.Eng.(B.P.) H Ward Assistant Engineer
Permissible FSI2577.18
Proposed, not sanctioned979 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch27th Cross Road, Baba House, Off Linking Road, Bandra West, Mumbai 400050

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtul Situt and Assocates
EngineerN. S.Lele & Associates
PartnerRole in project
Rajpurohit Builders LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800002198Jun 2019 → Jun 2020

Reason as filed by the promoter1. The development control and promotions regulations 2034 for Greater Mumbai was sanctioned on 8th May, 2018. However, a major part of the same was under Excluded Part. Hence, the implementation of the same was not possible. 2. The earlier DCR 1991, stopped being in existence from 31st August, 2018. 3. The Government sanctioned the Excluded Part on 21st September, 2018 and stated that implementation of DCPR 2034 would commence form 24th October, 2018. 4. However, the Government notified on 23rd October, 2018 that there were lots of typographical errors in the notification dated 21st September

EXT51800009966Jun 2019 → Dec 2022

Reason as filed by the promoterDelay caused by supply of materials, services of contractors, market conditions of the Real Estate Sector, followed by COVID-19 Pandemic and Prolonged delay in obtaining necessary approvals from the Authority

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000196324Mr. Issac John D'souza and Mrs. Cynthia Issac D'souzaRajpurohit Builders LLP19/03/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed32

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineers Certificate on Quality Assurance (Form 2A)_Shubh Mangal-FY 19-20.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers Certificate on Quality Assurance (Form 2A)_Shubh Mangal-FY 20-21.pdf19 Aug 2021
Disclosure of sold/ booked inventoryFile: Shubh Mangal-Disclsoure of Sold Inventory details Circular No 29.pdf19 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Certificate of CA (Form 5) _ Annual Report_RBLLP-18-19.pdf19 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificate of CA (Form 5) _ Annual Report_RBLLP-19-20.pdf19 Aug 2021
Certificates of CA (Form 5)File: Certificate of CA (Form 5) _ Annual Report_RBLLP-19-20.pdf19 Apr 2021
Certificates of CA (Form 3)File: 8-Certificate of CA (Form 3)_Shubh Mangal_RBLLP-3Qtr-2019.pdf23 Nov 2020
Certificates of CA (Form 3)File: 9-Certificate of CA (Form 3)_Shubh Mangal_RBLLP-4Qtr-2019.pdf23 Nov 2020
Certificates of CA (Form 3)File: 10-Certificate of CA (Form 3)_Shubh Mangal_RBLLP-1Qtr-2020.pdf23 Nov 2020
Certificates of CA (Form 3)File: 11-Certificate of CA (Form 3)_Shubh Mangal_RBLLP-2Qtr-2020.pdf23 Nov 2020
Certificates of CA (Form 3)File: Form 3_RBLLP_Q1_18-19.pdf23 May 2020
Certificates of CA (Form 3)File: Form 3_RBLLP_Q2_18-19.pdf23 May 2020
Certificates of CA (Form 3)File: Form 3_RBLLP_Q3_18-19.pdf23 May 2020
Certificates of CA (Form 3)File: Form 3_RBLLP_Q4_18-19.pdf23 May 2020
Certificates of CA (Form 5)File: D:\SAMEER PANCHAL - CS\Company Secretary\03_MahaRERA\00_PROJECTS\00_ PROJECTS\03_Shubh Man3 Feb 2020
Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Shubh Mangal_RBLLP-1Qtr.pdf5 Nov 2019
Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Shubh Mangal_RBLLP-2Qtr.pdf5 Nov 2019
Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Shubh Mangal_RBLLP-3Qtr.pdf5 Nov 2019
Certificates of CA (Form 5)File: Certificate of CA (Form 5) _ Annual Report.pdf7 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf5 Apr 2018
Building plan approvalFile: Building plan apporval (IOD).pdf28 Jul 2017
Layout approvalFile: Copy of Layout Approval.pdf28 Jul 2017
PAN CardFile: Rajpurohit Builders LLP _ Pan Card.pdf28 Jul 2017
Copy of the legal title reportFile: Copy of the Legal Title Report.pdf28 Jul 2017
Details of encumbrancesFile: Self Declaration for encumbrances_Shubh Mangal.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Approval.pdf28 Jul 2017
Building Plan Approval (IOD)File: Building plan apporval (IOD).pdf28 Jul 2017
Declaration in FORM BFile: Declaration in Form B - Shubh Mangal.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1).pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate _Shubh Mangal.pdf28 Jul 2017
Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Shubh Mangal.pdf28 Jul 2017
Proforma of Allotment letterFile: Proforma of the allotment letter and agreement for sale.pdf28 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shubh Mangal on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Santacruz East6,700+ in Mumbai Suburban

2 kmShubh MangalCompleted 52Lapsed / revoked 45Other 85Dot size: filed unitsN

Filed coordinates, straight-line distance. 182 registered projects within 2 km.

Builder: Rajpurohit Builders LLP

Rajpurohit Builders LLP has 1 registration on MahaRERA, including Shubh Mangal. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Shubh Mangal shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shubh Mangal is delayed beyond 29 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shubh Mangal?

The registered promoter entity is Rajpurohit Builders LLP, an others as per the filing. Its GSTIN 27AATFR6167N1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shubh Mangal?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Shubh Mangal?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Shubh Mangal?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shubh Mangal?

The professionals named in the filing: Architect: Atul Situt and Assocates; Engineer: N. S.Lele & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shubh Mangal?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shubh Mangal. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shubh Mangal to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.