Home / Browse projects / Mumbai Suburban, Maharashtra / Shubh Mangal
Shubh Mangal
RG-MH-25590 · RERA P51800002774 · Last updated on MahaRERA portal: 19 Aug 2021
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 40 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 48 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shubh Mangal is a Residential / Group Housing project by Rajpurohit Builders LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002774 on 4 Aug 2017. Possession was promised by 29 Jun 2023 and is now 40 months past that date. The completion date has moved by 48 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameShubh Mangal
- TypeResidential / Group Housing
- Location
- C.S.T. Road
- Kalina
- Santacruz East
- Andheri
- Mumbai Suburban
- 400098
- Pincode400098
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800002774
- ReraGenie IDRG-MH-25590
Builder
- NameRajpurohit Builders LLP
- Entity typeOthers
- GSTIN27AATFR6167N1Z5
- PartnersPradeep Ramkripal Mishra, Saurabh Kundan Borida Bordia
- Designated PartnersShrem Karmvir Construction LLP NA, Ashtavinayak Highrise LLP NA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Aug 2017
- Promised completion29 Jun 2023
- Revised completionRevised to 29 Jun 2023 (originally 30 Jun 2019)
- Buildings1 building record
- Documents filed32 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Shubh Mangal | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 19 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 80%.
Shubh Mangal: 25% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 10% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 19 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Atul Situt and Assocates |
| Engineer | N. S.Lele & Associates |
| Partner | Role in project |
|---|---|
| Rajpurohit Builders LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. The development control and promotions regulations 2034 for Greater Mumbai was sanctioned on 8th May, 2018. However, a major part of the same was under Excluded Part. Hence, the implementation of the same was not possible. 2. The earlier DCR 1991, stopped being in existence from 31st August, 2018. 3. The Government sanctioned the Excluded Part on 21st September, 2018 and stated that implementation of DCPR 2034 would commence form 24th October, 2018. 4. However, the Government notified on 23rd October, 2018 that there were lots of typographical errors in the notification dated 21st September
Reason as filed by the promoterDelay caused by supply of materials, services of contractors, market conditions of the Real Estate Sector, followed by COVID-19 Pandemic and Prolonged delay in obtaining necessary approvals from the Authority
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196324 | Mr. Issac John D'souza and Mrs. Cynthia Issac D'souza | Rajpurohit Builders LLP | 19/03/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed32
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineers Certificate on Quality Assurance (Form 2A)_Shubh Mangal-FY 19-20.pdf | 19 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers Certificate on Quality Assurance (Form 2A)_Shubh Mangal-FY 20-21.pdf | 19 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Shubh Mangal-Disclsoure of Sold Inventory details Circular No 29.pdf | 19 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Certificate of CA (Form 5) _ Annual Report_RBLLP-18-19.pdf | 19 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificate of CA (Form 5) _ Annual Report_RBLLP-19-20.pdf | 19 Aug 2021 |
| Certificates of CA (Form 5)File: Certificate of CA (Form 5) _ Annual Report_RBLLP-19-20.pdf | 19 Apr 2021 |
| Certificates of CA (Form 3)File: 8-Certificate of CA (Form 3)_Shubh Mangal_RBLLP-3Qtr-2019.pdf | 23 Nov 2020 |
| Certificates of CA (Form 3)File: 9-Certificate of CA (Form 3)_Shubh Mangal_RBLLP-4Qtr-2019.pdf | 23 Nov 2020 |
| Certificates of CA (Form 3)File: 10-Certificate of CA (Form 3)_Shubh Mangal_RBLLP-1Qtr-2020.pdf | 23 Nov 2020 |
| Certificates of CA (Form 3)File: 11-Certificate of CA (Form 3)_Shubh Mangal_RBLLP-2Qtr-2020.pdf | 23 Nov 2020 |
| Certificates of CA (Form 3)File: Form 3_RBLLP_Q1_18-19.pdf | 23 May 2020 |
| Certificates of CA (Form 3)File: Form 3_RBLLP_Q2_18-19.pdf | 23 May 2020 |
| Certificates of CA (Form 3)File: Form 3_RBLLP_Q3_18-19.pdf | 23 May 2020 |
| Certificates of CA (Form 3)File: Form 3_RBLLP_Q4_18-19.pdf | 23 May 2020 |
| Certificates of CA (Form 5)File: D:\SAMEER PANCHAL - CS\Company Secretary\03_MahaRERA\00_PROJECTS\00_ PROJECTS\03_Shubh Man | 3 Feb 2020 |
| Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Shubh Mangal_RBLLP-1Qtr.pdf | 5 Nov 2019 |
| Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Shubh Mangal_RBLLP-2Qtr.pdf | 5 Nov 2019 |
| Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Shubh Mangal_RBLLP-3Qtr.pdf | 5 Nov 2019 |
| Certificates of CA (Form 5)File: Certificate of CA (Form 5) _ Annual Report.pdf | 7 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf | 5 Apr 2018 |
| Building plan approvalFile: Building plan apporval (IOD).pdf | 28 Jul 2017 |
| Layout approvalFile: Copy of Layout Approval.pdf | 28 Jul 2017 |
| PAN CardFile: Rajpurohit Builders LLP _ Pan Card.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: Copy of the Legal Title Report.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: Self Declaration for encumbrances_Shubh Mangal.pdf | 28 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Copy of Layout Approval.pdf | 28 Jul 2017 |
| Building Plan Approval (IOD)File: Building plan apporval (IOD).pdf | 28 Jul 2017 |
| Declaration in FORM BFile: Declaration in Form B - Shubh Mangal.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1).pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate _Shubh Mangal.pdf | 28 Jul 2017 |
| Certificates of CA (Form 3)File: Certificate of CA (Form 3)_Shubh Mangal.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: Proforma of the allotment letter and agreement for sale.pdf | 28 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 32 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Shubh Mangal on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Santacruz East6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 182 registered projects within 2 km.
ALORA
KOLTE-PATIL DEVELOPERS LIMITED
GOLDEN VISTA
BLUE DIAMOND SPACES PRIVATE LIMITED
UNO
Transcon Bellaviu Private Limited
9 BKC
RESHAM SINGH DEVELOPERS LLP
Green Bay
Global Infraprojects SJ LLp
Courtyard
Royal Minerva Realty LLP
See every Mumbai Suburban project, with the district possession charts
Builder: Rajpurohit Builders LLP
Rajpurohit Builders LLP has 1 registration on MahaRERA, including Shubh Mangal. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Shubh Mangal shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Shubh Mangal is delayed beyond 29 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shubh Mangal?
The registered promoter entity is Rajpurohit Builders LLP, an others as per the filing. Its GSTIN 27AATFR6167N1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shubh Mangal?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Shubh Mangal?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Shubh Mangal?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shubh Mangal?
The professionals named in the filing: Architect: Atul Situt and Assocates; Engineer: N. S.Lele & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shubh Mangal?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback