Registered No litigation declared Residential / Group Housing project

Shrivega

By SHRIVEGA

RG-MH-83685 · RERA P52000050339 · Last updated on MahaRERA portal: 10 Nov 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jan 2028Possession promisedno revision filed
64 of 1749Construction stages doneacross 159 buildings; furthest along: Slabs of Super Structure, 80%
106 of 159Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Shrivega is a Residential / Group Housing project by SHRIVEGA in Raigarh, Maharashtra, registered with MahaRERA as P52000050339 on 5 Apr 2023. Possession is promised by 1 Jan 2028. 53 of the 159 units on this registration are recorded sold or booked, and 64 of 1749 construction stages are filed complete.

At a glance

Project

  • NameShrivega
  • TypeResidential / Group Housing
  • Location
    • Near Coastal Highway
    • Shekhadi
    • Shrivardhan
    • Raigarh
    • 402113
  • Pincode402113
  • RERA no.P52000050339
  • ReraGenie IDRG-MH-83685

Builder

  • NameSHRIVEGA
  • Entity typeOthers
  • Named personsGirish Ravindra Amonker, Sahil Shrikant Paranjape, Amit Shashank Paranjape

Key dates

this monthRegisteredApr 2023PromisedJan 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Apr 2023
  • Promised completion1 Jan 2028
  • Revised completionNone
  • Buildings159 building records
  • Documents filed56 files

Current status

33%53 of 159 units booked

Figures as on 10 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Villa- 01ANA11101
Villa- 01BNA11101
Villa- 02ANA10101
Villa- 02BNA10101
Villa- 03ANA10101
Villa- 03BNA10101
Villa- 04ANA10101
Villa- 04BNA10101
Villa- 05ANA10101
Villa- 05BNA10101
Villa- 06ANA10101
Villa- 06BNA10101
Villa- 07ANA10101
Villa- 07BNA10101
Villa- 08ANA10101
Villa- 08BNA10101
Villa- 09ANA10101
Villa- 09BNA10101
Villa- 10ANA10101
Villa- 10BNA10101
Villa- 11ANA10101
Villa- 11BNA10101
Villa- 12ANA10101
Villa- 12BNA10101
Villa- 13ANA10101
Villa- 13BNA10101
Villa- 14ANA10101
Villa- 14BNA10101
Villa- 15ANA10101
Villa- 15BNA10101
Villa- 16ANA10101
Villa- 16BNA10101
Villa- 17ANA10101
Villa- 17BNA10101
Villa- 18ANA10101
Villa- 18BNA10101
Villa- 19ANA10101
Villa- 19BNA10101
Villa- 20ANA10101
Villa- 20BNA10101
Villa- 21ANA10101
Villa- 21BNA10101
Villa- 22ANA10101
Villa- 22BNA10101
Villa- 23ANA10101
Villa- 23BNA10101
Villa- 24ANA10101
Villa- 24BNA10101
Villa- 25ANA10101
Villa- 25BNA10101
Villa- 26ANA10101
Villa- 26BNA10101
Villa- 27ANA10101
Villa- 27BNA10101
Villa- 28ANA10101
Villa- 28BNA10101
Villa- 29ANA10101
Villa- 29BNA10101
Villa- 30ANA10101
Villa- 30BNA10101
Villa- 31ANA10101
Villa- 31BNA10101
Villa- 32ANA10101
Villa- 32BNA10101
Villa- 33ANA10101
Villa- 33BNA10101
Villa- 34ANA10101
Villa- 34BNA10101
Villa- 35ANA10101
Villa- 35BNA10101
Villa- 36ANA10101
Villa- 36BNA10101
Villa- 37ANA10101
Villa- 37BNA10101
Villa- 38ANA10101
Villa- 38BNA10101
Villa- 39ANA10101
Villa- 39BNA10101
Villa- 40ANA10101
Villa- 40BNA10101
Villa- 41ANA10101
Villa- 41BNA10101
Villa- 42ANA10101
Villa- 42BNA10101
Villa- 43ANA10101
Villa- 43BNA10101
Villa- 44ANA10101
Villa- 44BNA10101
Villa- 45ANA10101
Villa- 45BNA10101
Villa- 46ANA10101
Villa- 46BNA10101
Villa- 47ANA10101
Villa- 47BNA10101
Villa- 51ANA10101
Villa- 48BNA10101
Villa- 49ANA10101
Villa- 49BNA10101
Villa- 50ANA10101
Villa- 50BNA10101
Villa- 52ANA10101
Villa- 53ANA10101
Villa- 54ANA10101
Villa- 55ANA10101
Villa- 57ANA10101
Villa- 56ANA10101
Villa- 56BNA10101
Villa- 57BNA10101
Villa- 58ANA10101
Villa- 58BNA10101
Villa- 59ANA10101
Villa- 59BNA10101
Villa- 60ANA10101
Villa- 60BNA10101
Villa-61ANA10101
Villa- 61BNA10101
Villa- 62ANA10101
Villa- 62BNA10101
Villa- 63ANA10101
Villa- 64ANA10101
Villa- 63BNA10101
Villa- 64BNA10101
Villa- 65ANA10101
Villa- 66ANA10101
Villa- 66BNA10101
Villa- 67ANA10101
Villa- 67BNA10101
Villa- 68ANA10101
Villa- 68BNA10101
Villa- 69ANA10101
Villa- 69BNA10101
Villa- 70ANA10101
Villa- 70BNA10101
Villa- 71ANA10101
Villa- 71BNA10101
Villa- 72ANA10101
Villa- 48ANA10101
Villa- 73ANA10101
Villa- 73BNA10101
Villa- 74ANA10101
Villa- 74BNA10101
Villa- 75ANA10101
Villa- 75BNA10101
Villa- 76ANA10101
Villa- 76BNA10101
Villa-77ANA10101
Villa- 77BNA10101
Villa- 78ANA10101
Villa- 78BNA10101
Villa- 79ANA10101
Villa- 79BNA10101
Villa- 80ANA10101
Villa- 80BNA10101
Villa- 85ANA10101
Villa- 85BNA10101
Villa- 86ANA10101
Villa- 86BNA10101
Villa- 87ANA10101
Villa- 87BNA10101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 10 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 159 buildings; the table lists the first 20.

64 of 1749 construction stages are filed complete across 159 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

Villa- 01A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 01B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 02A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 02B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 03A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 03B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 04A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 04B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 05A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 05B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 06A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 06B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 07A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 07B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 08A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 08B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 09A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 09B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 10A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa- 10B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes10%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed159

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots159
Open Space159
BuildingOpen SpaceTotal
Villa- 01A11
Villa- 01B11
Villa- 02A11
Villa- 02B11
Villa- 03A11
Villa- 03B11
Villa- 04A11
Villa- 04B11
Villa- 05A11
Villa- 05B11
Villa- 06A11
Villa- 06B11
Villa- 07A11
Villa- 07B11
Villa- 08A11
Villa- 08B11
Villa- 09A11
Villa- 09B11
Villa- 10A11
Villa- 10B11
Villa- 11A11
Villa- 11B11
Villa- 12A11
Villa- 12B11
Villa- 13A11
Villa- 13B11
Villa- 14A11
Villa- 14B11
Villa- 15A11
Villa- 15B11
Villa- 16A11
Villa- 16B11
Villa- 17A11
Villa- 17B11
Villa- 18A11
Villa- 18B11
Villa- 19A11
Villa- 19B11
Villa- 20A11
Villa- 20B11
Villa- 21A11
Villa- 21B11
Villa- 22A11
Villa- 22B11
Villa- 23A11
Villa- 23B11
Villa- 24A11
Villa- 24B11
Villa- 25A11
Villa- 25B11
Villa- 26A11
Villa- 26B11
Villa- 27A11
Villa- 27B11
Villa- 28A11
Villa- 28B11
Villa- 29A11
Villa- 29B11
Villa- 30A11
Villa- 30B11
Villa- 31A11
Villa- 31B11
Villa- 32A11
Villa- 32B11
Villa- 33A11
Villa- 33B11
Villa- 34A11
Villa- 34B11
Villa- 35A11
Villa- 35B11
Villa- 36A11
Villa- 36B11
Villa- 37A11
Villa- 37B11
Villa- 38A11
Villa- 38B11
Villa- 39A11
Villa- 39B11
Villa- 40A11
Villa- 40B11
Villa- 41A11
Villa- 41B11
Villa- 42A11
Villa- 42B11
Villa- 43A11
Villa- 43B11
Villa- 44A11
Villa- 44B11
Villa- 45A11
Villa- 45B11
Villa- 46A11
Villa- 46B11
Villa- 47A11
Villa- 47B11
Villa- 51A11
Villa- 48B11
Villa- 49A11
Villa- 49B11
Villa- 50A11
Villa- 50B11
Villa- 52A11
Villa- 53A11
Villa- 54A11
Villa- 55A11
Villa- 57A11
Villa- 56A11
Villa- 56B11
Villa- 57B11
Villa- 58A11
Villa- 58B11
Villa- 59A11
Villa- 59B11
Villa- 60A11
Villa- 60B11
Villa-61A11
Villa- 61B11
Villa- 62A11
Villa- 62B11
Villa- 63A11
Villa- 64A11
Villa- 63B11
Villa- 64B11
Villa- 65A11
Villa- 66A11
Villa- 66B11
Villa- 67A11
Villa- 67B11
Villa- 68A11
Villa- 68B11
Villa- 69A11
Villa- 69B11
Villa- 70A11
Villa- 70B11
Villa- 71A11
Villa- 71B11
Villa- 72A11
Villa- 48A11
Villa- 73A11
Villa- 73B11
Villa- 74A11
Villa- 74B11
Villa- 75A11
Villa- 75B11
Villa- 76A11
Villa- 76B11
Villa-77A11
Villa- 77B11
Villa- 78A11
Villa- 78B11
Villa- 79A11
Villa- 79B11
Villa- 80A11
Villa- 80B11
Villa- 85A11
Villa- 85B11
Villa- 86A11
Villa- 86B11
Villa- 87A11
Villa- 87B11

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area157,271 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Sep 2025
LandownerVillageDistrict
Rajashri Girish AmonkerAndheriMumbai Suburban
Shrivega AOPKarve NagarPune

Approvals and building plan

Sanctioning authorityCollector Office Raigad
Permissible FSI12284.53
Proposed, not sanctioned12,285 sq m
Buildings approved159
Buildings sanctioned159

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLaukik Apartments, Ground Floor, Plot No 3, CTS No 870, Bhandarkar Road, Pune, Maharashtra- 411004

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchland Architects PVT. Ltd
EngineerDilip Akode
Chartered AccountantKapure & Kapure
Chartered AccountantSTP & Associates
Chartered AccountantGosavi Yardi & Co
PartnerRole in project
SHRIVEGA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 1 Jan 2028

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: SHRIVEGA FORM 5 March 25.pdf10 Nov 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2-SHRIVEGA-MAR'25-uplaoded.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Shrivega-Mar'25-uploaded.pdf8 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-Shrivega-Sept'24-uploaded.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Shrivega.pdf10 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Shrivega-Dec'24-uploaded.pdf15 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-Shrivega-June '24-uploaded.pdf22 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure- Update Shrivega-Sept'24-uploaded-.pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Shrivega FY23-24-compressed-uploaded.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Shrivega-Sept'24-uploaded.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Shrivega-Sept'24-uploaded.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure-Sold-Unsold-Abhiruchi Mhada 3-June'24-uploaded.pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 26 FORM 2- Shrivega-June'24-uploaded.pdf9 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 23 Shrivega -Form 1-June'24-uploaded.pdf4 Jul 2024
Disclosure of sold/ booked inventoryFile: Inventory Report- Shrivega-Mar'24-compressed-uploaded.pdf15 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Shrivega-Mar'24-uploaded.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-Shrivega 30-06-2023-uploaded.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-Shrivega 30-09-2023-uploaded.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-Shrivega 31-12-2023-uploaded.pdf12 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Shrivega - 30-04-2023 -uploaded.pdf1 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Shrivega 31-07-2023-uploaded.pdf1 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Shrivega- 30-09-2023-uploaded.pdf1 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Shrivega- 31-12-2023-uploaded.pdf1 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Shrivega-June'23-uploaded.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Shrivega-Sept'23-uploaded.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-Shrivega- Dec'23-uploaded.pdf16 Jan 2024
Disclosure of sold/ booked inventoryFile: Inventory data-Shrivega- Sept'23-compressed.pdf19 Oct 2023
Proforma of Agreement for saleFile: AFS_Shrivega_Shrivega Hosuing Home_03032023 (1).pdf4 Mar 2023
Deviation Report with respect to model copy of AgreementFile: 15 Deviation Report AFS_ Shrivega -04-03-2023.pdf4 Mar 2023
Declaration about Commencement CertificateFile: Declaration about Comencement Certificate.pdf1 Mar 2023
Layout approvalFile: 1Sanctioned plan-Shrivega-Sheet 1 (2)_11zon_11zon.pdf28 Feb 2023
Building plan approvalFile: 2Sanctioned plan- Shrivega-Sheet 2.pdf28 Feb 2023
Building plan approvalFile: 3Sactioned plan-Shrivega-Sheet 3.pdf28 Feb 2023
Building plan approvalFile: 4Shrivega Scan Plan Sheet No 04.pdf28 Feb 2023
Building plan approvalFile: 5Shrivega Scan Plan Sheet No 05.pdf28 Feb 2023
Building plan approvalFile: 6Shrivega Scan Plan Sheet No06_11zon.pdf28 Feb 2023
Copy of Layout Approval (in case of layout)File: 1Sanctioned plan-Shrivega-Sheet 1 (2)_11zon_11zon.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 2Sanctioned plan- Shrivega-Sheet 2.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 3Sactioned plan-Shrivega-Sheet 3.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 4Shrivega Scan Plan Sheet No 04.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 5Shrivega Scan Plan Sheet No 05.pdf28 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 6Shrivega Scan Plan Sheet No06_11zon.pdf28 Feb 2023
Copy of the legal title reportFile: organized (64)_11zon.pdf16 Feb 2023
Proforma of Allotment letterFile: Allotment Letter_Shrivega_Shrivega Hosuing Home_13012023 (1).pdf16 Feb 2023
Deviation Report with respect to Allotment letterFile: 22-Deviation Report-Allotment Letter -Shrivega.pdf16 Feb 2023
PAN CardFile: 1 PAN Card.pdf15 Feb 2023
Details of encumbrances concerned to FinanceFile: 1 a Details of encumbrances concerned to Finance.pdf15 Feb 2023
Details of encumbrances concerned to FinanceFile: 2 a Details of encumbrances concerned to Finance.pdf15 Feb 2023
Details of encumbrances concerned to LegalFile: 1 a Details of encumbrances concerned to Finance.pdf15 Feb 2023
Details of encumbrances concerned to LegalFile: 2 a Details of encumbrances concerned to Finance.pdf15 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development.pdf15 Feb 2023
Declaration in FORM BFile: 1 Declaration in FORM B.pdf15 Feb 2023
CERSAI detailsFile: 1 CERSAI details.pdf15 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf15 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf15 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow15 Feb 2023

How this compares with Raigarh

33%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shrivega on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shekhadi5,900+ in Raigarh

Builder: SHRIVEGA

SHRIVEGA has 1 registration on MahaRERA, including Shrivega. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Shrivega is delayed beyond 1 Jan 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shrivega?

The registered promoter entity is SHRIVEGA, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shrivega?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shrivega?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shrivega?

The professionals named in the filing: Architect: Archland Architects PVT. Ltd; Engineer: Dilip Akode; Chartered Accountant: Kapure & Kapure; Chartered Accountant: STP & Associates; Chartered Accountant: Gosavi Yardi & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shrivega?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shrivega. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shrivega to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.