ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Rural, Karnataka / SHRIRAM GREEN FIELD PHASE 2

Registration approved Residential/Group Housing project

SHRIRAM GREEN FIELD PHASE 2

By SHRIVISION TOWERS PRIVATE LIMITED

RG-KA-61080 · RERA PRM/KA/RERA/1250/304/PR/171014/001220 · Last updated on RERA Karnataka portal: 27 Mar 2022

Source: official RERA Karnataka filing

Red flags

  • 92 complaints at RERA Karnataka
  • Completion date moved by 33 months
  • 3 extensions taken

Clear

  • Separate project account declared
Dec 2023Possession promisedmoved 33 months from the original
92Complaints at RERA Karnatakaon this registration
Jump to the 97 documents Report an error

SHRIRAM GREEN FIELD PHASE 2 is a Residential/Group Housing project by SHRIVISION TOWERS PRIVATE LIMITED in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/171014/001220 on 14 Oct 2017. Possession is promised by 30 Dec 2023. The completion date has moved by 33 months from the original filing. 92 complaints are on record with the regulator.

At a glance

Project

  • NameSHRIRAM GREEN FIELD PHASE 2
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1250/304/PR/171014/001220
  • ReraGenie IDRG-KA-61080

Builder

  • NameSHRIVISION TOWERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU70102KA2008PTC047227
  • Authorized SignatoryK.R.RAMESH
  • OthersMALLIKARJUN.M
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredOct 2017First promiseMar 2021Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Oct 2017
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 31 Mar 2021)
  • Buildings3 building records
  • Documents filed97 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
G---2030203
H---2470247
J---2030203

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 27 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 27 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area23,344 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 243.53 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKadur Krishna Siddharth
EngineerINNOTECH ENGINEERING CONSULT PVT LTD

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2021 → Dec 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1250/304/PR/220507/001220Dec 2021 → Dec 2022

Reason as filed by the promoterForce Majeure; Shortage of Building Materials, Concrete, Jalli etc

ExtensionDec 2022 → Dec 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka92

Case no.ComplainantRespondentFiled
CMP/200824/0003290-SHRIVISION TOWERS PRIVATE LIMITED24/08/2020
CMP/210709/0008113-SHRIVISION TOWERS PRIVATE LIMITED09/07/2021
CMP/220112/0008783-SHRIVISION TOWERS PRIVATE LIMITED12/01/2022
CMP/220113/0008790-SHRIVISION TOWERS PRIVATE LIMITED13/01/2022
CMP/220115/0008796-SHRIVISION TOWERS PRIVATE LIMITED15/01/2022
CMP/220124/0008859-SHRIVISION TOWERS PRIVATE LIMITED24/01/2022
CMP/220126/0008874-SHRIVISION TOWERS PRIVATE LIMITED26/01/2022
CMP/220225/0009055-SHRIVISION TOWERS PRIVATE LIMITED25/02/2022
CMP/220225/0009056-SHRIVISION TOWERS PRIVATE LIMITED25/02/2022
CMP/220317/0009146-SHRIVISION TOWERS PRIVATE LIMITED17/03/2022
CMP/220318/0009150-SHRIVISION TOWERS PRIVATE LIMITED18/03/2022
CMP/220328/0009258-SHRIVISION TOWERS PRIVATE LIMITED28/03/2022
CMP/220401/0009306-SHRIVISION TOWERS PRIVATE LIMITED01/04/2022
CMP/220406/0009317-SHRIVISION TOWERS PRIVATE LIMITED06/04/2022
CMP/220406/0009318-SHRIVISION TOWERS PRIVATE LIMITED06/04/2022
CMP/220406/0009320-SHRIVISION TOWERS PRIVATE LIMITED06/04/2022
CMP/220411/0009339-SHRIVISION TOWERS PRIVATE LIMITED11/04/2022
CMP/220412/0009347-SHRIVISION TOWERS PRIVATE LIMITED12/04/2022
CMP/220418/0009366-SHRIVISION TOWERS PRIVATE LIMITED18/04/2022
CMP/220420/0009374-SHRIVISION TOWERS PRIVATE LIMITED20/04/2022
CMP/220426/0009385-SHRIVISION TOWERS PRIVATE LIMITED26/04/2022
CMP/220428/0009394-SHRIVISION TOWERS PRIVATE LIMITED28/04/2022
CMP/220504/0009418-SHRIVISION TOWERS PRIVATE LIMITED04/05/2022
CMP/220509/0009433-SHRIVISION TOWERS PRIVATE LIMITED09/05/2022
CMP/220510/0009446-SHRIVISION TOWERS PRIVATE LIMITED10/05/2022
CMP/220520/0009490-SHRIVISION TOWERS PRIVATE LIMITED20/05/2022
CMP/220525/0009527-SHRIVISION TOWERS PRIVATE LIMITED25/05/2022
CMP/220525/0009528-SHRIVISION TOWERS PRIVATE LIMITED25/05/2022
CMP/220530/0009539-SHRIVISION TOWERS PRIVATE LIMITED30/05/2022
CMP/220602/0009571-SHRIVISION TOWERS PRIVATE LIMITED02/06/2022
CMP/220613/0009617-SHRIVISION TOWERS PRIVATE LIMITED13/06/2022
CMP/220613/0009619-SHRIVISION TOWERS PRIVATE LIMITED13/06/2022
CMP/220706/0009723-SHRIVISION TOWERS PRIVATE LIMITED06/07/2022
CMP/220707/0009724-SHRIVISION TOWERS PRIVATE LIMITED07/07/2022
CMP/220718/0009758-SHRIVISION TOWERS PRIVATE LIMITED18/07/2022
CMP/220719/0009771-SHRIVISION TOWERS PRIVATE LIMITED19/07/2022
CMP/220719/0009773-SHRIVISION TOWERS PRIVATE LIMITED19/07/2022
CMP/220720/0009781-SHRIVISION TOWERS PRIVATE LIMITED20/07/2022
CMP/220721/0009790-SHRIVISION TOWERS PRIVATE LIMITED21/07/2022
CMP/220726/0009813-SHRIVISION TOWERS PRIVATE LIMITED26/07/2022
CMP/220727/0009821-SHRIVISION TOWERS PRIVATE LIMITED27/07/2022
CMP/220801/0009836-SHRIVISION TOWERS PRIVATE LIMITED01/08/2022
CMP/220802/0009837-SHRIVISION TOWERS PRIVATE LIMITED02/08/2022
CMP/220820/0009921-SHRIVISION TOWERS PRIVATE LIMITED20/08/2022
CMP/220826/0009944-SHRIVISION TOWERS PRIVATE LIMITED26/08/2022
CMP/221017/0010110-SHRIVISION TOWERS PRIVATE LIMITED17/10/2022
CMP/221221/0010493-SHRIVISION TOWERS PRIVATE LIMITED21/12/2022
CMP/221221/0010495-SHRIVISION TOWERS PRIVATE LIMITED21/12/2022
CMP/221226/0010519-SHRIVISION TOWERS PRIVATE LIMITED26/12/2022
CMP/221227/0010539-SHRIVISION TOWERS PRIVATE LIMITED27/12/2022
00069/2023-SHRIVISION TOWERS PRIVATE LIMITED13/01/2023
00108/2023-SHRIVISION TOWERS PRIVATE LIMITED20/01/2023
00109/2023-SHRIVISION TOWERS PRIVATE LIMITED20/01/2023
00110/2023-SHRIVISION TOWERS PRIVATE LIMITED20/01/2023
00121/2023-SHRIVISION TOWERS PRIVATE LIMITED30/01/2023
00216/2023-SHRIVISION TOWERS PRIVATE LIMITED20/02/2023
00504/2023-SHRIVISION TOWERS PRIVATE LIMITED18/04/2023
00702/2023-SHRIVISION TOWERS PRIVATE LIMITED06/05/2023
00761/2023-SHRIVISION TOWERS PRIVATE LIMITED17/05/2023
00787/2023-SHRIVISION TOWERS PRIVATE LIMITED20/05/2023

Documents filed97

As listed on the registration, under the names the promoter filed them with; the newest 80 of 97 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/171014/001220 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
legible attested copy of Fire force NOCFile: Partial FIRE NOC-Affedavit for NOC extension-Old FIRE NOC.pdf27 Mar 2022
Affidavit for Airport NOCFile: Affedavit for Airport NOC extension-Old NOC.pdf27 Mar 2022
Affidavit for BESCOM NOCFile: Affedavit for BESCOM NOC extension-Old NOC.pdf27 Mar 2022
Affidavit for KSPCB NOCFile: SEIAA NOC-Affedavit for NOC extension-Old KSPCB NOC.pdf27 Mar 2022
Architect Certificate - Pending workFile: 1-1 Arc certificate- work pending.pdf20 Feb 2022
Revised NOC KSPCB and SEIAAFile: 1-2- Noc-Revised - KSPCB SEIAA.pdf20 Feb 2022
Commencement certificateFile: 1-3 -Commencement Certificate.pdf20 Feb 2022
Renewed building drawings - Part 1File: Sanction plan - part1-min.pdf20 Feb 2022
Renewed building drawings - Part 2File: Sanction plan -part 2-min.pdf20 Feb 2022
Renewed building drawings - Part 3File: Sanction plan -part 3-min.pdf20 Feb 2022
Engineer certificateFile: 2-1 - Engg certificate - work pending.pdf20 Feb 2022
Updated Airport NOCFile: 2-2 Airport updated NOC.pdf20 Feb 2022
Updated NOC Fire SEIAA waterFile: 2-3 Fire-revised- SEIAA - water NOC.pdf20 Feb 2022
Site plan - STP locationFile: 2-4 Site plan with STP location marked.PDF20 Feb 2022
Updated NOC BESCOMFile: 2-3 BESCOM-updated NOC.pdf20 Feb 2022
STP - drawingsFile: STP drawings.pdf20 Feb 2022
Latitude and Longitude of project locationFile: 2-6 Latitude and Longitude details.pdf20 Feb 2022
Project SpecificationsFile: Signed - Specifications.pdf20 Feb 2022
Proforma Agreement of Sale (AOS)File: 2-7 Proforma AOS-GF wing-B.pdf20 Feb 2022
Agreement of Sale (AOS) - customer signedFile: 03 Agreement for Sale.pdf20 Feb 2022
1. Charted Account CertificateFile: Form 4_Greenfield Ph 2 Sept 21.pdf18 Jan 2022
2.Covid extension registration certificateFile: PRMKARERA1250304PR171014001220-GF P2-covid.pdf18 Jan 2022
2. revised form-B.File: Form-B.pdf18 Jan 2022
3. 1) Affidavit in prescribed formatFile: Affidavit 1.pdf18 Jan 2022
3. 3)sold and unsold summaryFile: Sold & Unsold summary-GF P2.xlsx18 Jan 2022
3. 4) Proforma sale deedFile: Proforma sale deed-GF Phase-2.pdf18 Jan 2022
3. 5) Proforma allotment letterFile: Proforma allotment Letter-GF P-2.pdf18 Jan 2022
3. 5) current brochureFile: GreenfieldBrochure-compressed.pdf18 Jan 2022
3. 6) STP drawingsFile: STP drawings-merged.pdf18 Jan 2022
3. 6) STP documents -NOC CFEFile: STP NOC-CFE-GF Phase-2.pdf18 Jan 2022
3. 7) Nocs-Airport, Fire, Bescom, Kspcb & BSNLFile: Airport, Fire, Bescom, KSPCB, Bsnl Nocs.pdf18 Jan 2022
3.7) Nocs-Fire-revised, SEIAA and Water NOCFile: Nocs-Fire-revised, SEIAA & water NOC.pdf18 Jan 2022
3. 9) Certificate from Registered Engineer indicating the structural safety of the buildingFile: WING-B STRL STABILITY CERTIFICATE.pdf18 Jan 2022
3. 10) Engineers certificate for or Work Completion Schedule till Date and Pending Work Completion SFile: Engineer certiifcates for Pending work and work completion till date.pdf18 Jan 2022
3. 11) Latitude and longitude details-details given in Airport NocFile: Airport NOC (1).pdf18 Jan 2022
3. 12) Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate for pending work completion schedule as on date.pdf18 Jan 2022
CertificateFile: ENC-1 COI-Shrivision towers.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Arc certificate- work completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engg certificate - work completed.pdf-
CA Certificate for Funds UtilizationFile: CA certificate - fund utilized GFII.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arc certificate- work completed.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engg certificate - work completed.pdf-
CA Certificate for Funds required for Project CompletionFile: CA certificate - funds required GFII-2.pdf-
AffidavitFile: Affidavit for extension of Project.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails GF-2.xlsx-
Document 1File: Reasons 1 - Greenfeild-P2.pdf-
Document 2File: Note Reason for delay attachment.pdf-
ENC-13 PH2 CC-min-
ENC-14 PH2 APPROVED BUILDING PLAN-
ENC-15 APPROVED LAYOUT PLAN-
ENC-27 PROFORMA FOR SALE DEED-
ENC-16 PROFORMA FOR SALE OF AGREEMENT-
ENC-19 LAND DOCS Development Agreement - Gardencity-
ENC-20 PH2 APPROVED SECTION-
ENC-21 AREA DEVELOPMENT PLAN greenfields master plan-
ENC-22 Proforma of Allotment letter-
ENC-23 BROCHURE-
ENC-24 ALL NOC-
ENC-25 Specifications - Greenfield-
ENC-12 EC - Greenfield-
ENC-A-2-Mutation or katha-
FIRE 1-
AIRPORT_AUTHORITY-
BESCOM-
KSPCB-
SLEIAAK 1-
BSNL-
Balance Sheet 2015 - 2016File: ENC-5 2016 BALANCE SHEET.pdf-
Balance Sheet 2014 - 2015File: ENC-5 2015 BALANCE SHEET.pdf-
Balance Sheet 2013 - 2014File: ENC-5 2014 BALANCE SHEET.pdf-
Audited Profit and Loss Statement 2015 - 2016File: ENC-6 2016 P AND L.pdf-
Audited Profit and Loss Statement 2014 - 2015File: ENC-6 2015 P AND L.pdf-
Audited Profit and Loss Statement 2013 - 2014File: ENC-6 2014 P AND L.pdf-
Director's Report 2015 - 2016File: ENC-7 2016 Directors Report-Shrivison Towers.pdf-
Director's Report 2014 - 2015File: ENC-7 2015 Directors Report-Shrivison Towers.pdf-
Director's Report 2013 - 2014File: ENC-7 2014 Directors Report-Shrivison Towers.pdf-
Cash Flow Statement 2015 - 2016File: ENC-8 2016 CASH FLOW.pdf-
Cash Flow Statement 2014 - 2015File: ENC-8 2015 CASH FLOW.pdf-
Auditor's Report 2015 - 2016File: ENC-9 2016 AUDITORS REPORT-min.pdf-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
SHRIRAM SUMMIT-OngoingAug 2017Not delivered
SHRIRAM SAMEEKSHA-OngoingAug 2017Not delivered

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one moved by 33 months
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep SHRIRAM GREEN FIELD PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

Builder: SHRIVISION TOWERS PRIVATE LIMITED

SHRIVISION TOWERS PRIVATE LIMITED has 2 registrations on RERA Karnataka, including SHRIRAM GREEN FIELD PHASE 1 and SHRIRAM GREEN FIELD PHASE 2. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if SHRIRAM GREEN FIELD PHASE 2 is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRIRAM GREEN FIELD PHASE 2?

The registered promoter entity is SHRIVISION TOWERS PRIVATE LIMITED, a company as per the filing. Its CIN U70102KA2008PTC047227 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRIRAM GREEN FIELD PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHRIRAM GREEN FIELD PHASE 2?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SHRIRAM GREEN FIELD PHASE 2?

The professionals named in the filing: Architect: Kadur Krishna Siddharth; Engineer: INNOTECH ENGINEERING CONSULT PVT LTD. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRIRAM GREEN FIELD PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRIRAM GREEN FIELD PHASE 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRIRAM GREEN FIELD PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.