Home / Browse projects / Aurangabad, Maharashtra / SHRINIWASA HOUSING SOCIRTY

Registration lapsed No litigation declared Others project

SHRINIWASA HOUSING SOCIRTY

By TULSI DEVELOPERS

RG-MH-91910 · RERA P51500026367 · Last updated on MahaRERA portal: 10 Sep 2020

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 37 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Sep 2023Possession promised37 months past this date
0 of 55Construction stages doneacross 5 buildings; furthest along: Excavation, 25%
0Complaints at MahaRERAon this registration
Jump to the 13 documents Report an error

SHRINIWASA HOUSING SOCIRTY is a Others project by TULSI DEVELOPERS in Aurangabad, Maharashtra, registered with MahaRERA as P51500026367 on 11 Sep 2020. Possession was promised by 30 Sep 2023 and is now 37 months past that date.

At a glance

Project

  • NameSHRINIWASA HOUSING SOCIRTY
  • TypeOthers
  • Location
    • JALGAON ROAD
    • SILLOD
    • Sillod (M Cl)
    • Aurangabad
    • 431112
  • Pincode431112
  • RERA no.P51500026367
  • ReraGenie IDRG-MH-91910

Builder

  • NameTULSI DEVELOPERS
  • Entity typeOthers
  • Named personTULSI DEVELOPER
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live2 lapsed, de-registered or revoked

Key dates

37 months past promisethis monthRegisteredSep 2020PromisedSep 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Sep 2020
  • Promised completion30 Sep 2023
  • Revised completionNone
  • Buildings5 building records
  • Documents filed13 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RESIDENTAL BUILDING A1 TO A3NA30000
RESIDENTAIL BUILDING A4 TO A6NA30000
RESIDENTAL BUILDING A7 TO A9NA30000
COMMERCIAL BUILDING B1 TO B6, B14, B15, B19, B20NA40000
COMMERCIALBUILDING C7 TO C12, C16 TO C18, C21 TO C23NA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 10 Sep 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Excavation, at 25%.

RESIDENTAL BUILDING A1 TO A312%
ActivityProgress
Excavation25%
Basement (if any)25%
Podiums (if any)0%
Plinth25%
Stilt Floor0%
Slabs of Super Structure25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RESIDENTAIL BUILDING A4 TO A60%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RESIDENTAL BUILDING A7 TO A90%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
COMMERCIAL BUILDING B1 TO B6, B14, B15, B19, B200%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
COMMERCIALBUILDING C7 TO C12, C16 TO C18, C21 TO C230%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Sep 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Open Space12
BuildingOpen SpaceTotal
COMMERCIAL BUILDING B1 TO B6, B14, B15, B19, B2066
COMMERCIALBUILDING C7 TO C12, C16 TO C18, C21 TO C2366

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,897 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
TULSI DEVELOPERSSillod (M Cl)Aurangabad

Approvals and building plan

Permissible FSI2566.97
Proposed, not sanctioned2,567 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSARAFA MARKET SILLOD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNITESH R ZALWAR
EngineerSAMEER CHANWADKAR
Chartered AccountantCA AJAY P DAULATABADKAR
PartnerRole in project
TULSI DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed13

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrancesFile: SEARCH AND TITALE CERTIFICATE_compressed.pdf10 Sep 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf10 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf10 Sep 2020
Layout approvalFile: layout block plan.pdf18 Aug 2020
Building plan approvalFile: BUILDINGPERMISSION.pdf18 Aug 2020
Copy of the legal title reportFile: SEARCH AND TITALE CERTIFICATE_compressed.pdf18 Aug 2020
Copy of Layout Approval (in case of layout)File: layout block plan.pdf18 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: BUILDINGPERMISSION.pdf18 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: BUILDINGPERMISSION.pdf18 Aug 2020
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION-FORMB.pdf18 Aug 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA ENGINEER Certificate.pdf18 Aug 2020
Proforma of Allotment letterFile: AGREEMENT TO SALE.pdf18 Aug 2020
PAN CardFile: PAN CARD RNZ.pdf22 Jan 2020

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep SHRINIWASA HOUSING SOCIRTY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SILLOD1,400+ in Aurangabad

Builder: TULSI DEVELOPERS

Tulsi Developers has 6 registrations on MahaRERA, including Tulsi Developers and SHRINIWASA HOUSING SOCIRTY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that SHRINIWASA HOUSING SOCIRTY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHRINIWASA HOUSING SOCIRTY is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRINIWASA HOUSING SOCIRTY?

The registered promoter entity is TULSI DEVELOPERS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRINIWASA HOUSING SOCIRTY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRINIWASA HOUSING SOCIRTY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRINIWASA HOUSING SOCIRTY?

The professionals named in the filing: Architect: NITESH R ZALWAR; Engineer: SAMEER CHANWADKAR; Chartered Accountant: CA AJAY P DAULATABADKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRINIWASA HOUSING SOCIRTY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRINIWASA HOUSING SOCIRTY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRINIWASA HOUSING SOCIRTY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.