Home / Browse projects / Nashik, Maharashtra / SHRINIVASA CASTLE

Registered No litigation declared Residential / Group Housing project

SHRINIVASA CASTLE

By JAYWANT DEORAM AHER

RG-MH-99151 · RERA P51600053850 · Last updated on MahaRERA portal: 12 Dec 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 24 months from the original
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 70%
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

SHRINIVASA CASTLE is a Residential / Group Housing project by JAYWANT DEORAM AHER in Nashik, Maharashtra, registered with MahaRERA as P51600053850 on 5 Dec 2023. Possession is promised by 30 Jun 2027. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameSHRINIVASA CASTLE
  • TypeResidential / Group Housing
  • Location
    • PLOT NO 23
    • SURVEY NO 163/2/12 SHRIRAM NAGAR
    • OPP AUNDUMBER LAWN
    • Nashik (M Corp.)
    • Nashik
    • 422006
  • Pincode422006
  • RERA no.P51600053850
  • ReraGenie IDRG-MH-99151

Builder

  • NameJAYWANT DEORAM AHER
  • Entity typeIndividual

Key dates

this monthRegisteredDec 2023First promiseJun 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Dec 2023
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRINIVASA CASTLENA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.

SHRINIVASA CASTLE: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 12 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes50%

Parking filed90

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots90
Closed/Covered40
Open Space50

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area709 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
JAYWANT DEVRAM AHERNashikNashik
PRAKASH NANAJI BHAMARENashik (M Corp.)Nashik
DIGAMBAR VITTHAL PAWARMumbai CityMumbai City
RAVINDRA DAGA SHINDENashik (M Corp.)Nashik

Approvals and building plan

Permissible FSI2452.41
Proposed, not sanctioned2,452 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGURUDARSHAN, OPP POLICE AYUKT KARYALAYA, SHARANPUR TRIMBAK, NASHIK-422005

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLILADHARA JAWALE
EngineerPANKAJ MAHALE
Chartered AccountantABHIJEET SHINDE & ASSOCIATES
Chartered AccountantTUSHAR LOKHANDEBHALGAT BOTHARA & ASSOCIATES
PartnerRole in project
JAYWANT DEORAM AHER-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600028431Jun 2025 → Jun 2027

Reason as filed by the promoterWE WISH TO INFORM YOU THAT APPROXIMATELY 80% OF THE CONSTRUCTION WORK HAS BEEN COMPLETED. HOWEVER, DUE TO CERTAIN UNFORESEEN CIRCUMSTANCES AND CHALLENGES ENCOUNTERED DURING THE CONSTRUCTION PROCESS, THERE HAS BEEN A DELAY IN COMPLETING THE REMAINING WORK AS PER THE ORIGINALLY COMMITTED TIMELINES. IN LIGHT OF THE ABOVE, AND AS PER THE PROVISIONS UNDER SECTION 7(3) OF THE REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016, WE REQUEST YOUR KIND APPROVAL TO GRANT AN EXTENSION OF THE PROJECT REGISTRATION UP TO 30.06.2027 ENABLE US TO COMPLETE THE BALANCE WORK AND FULFILL THE PENDING RERA COMPLIANCE

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 23-24.pdf12 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1 24-25_11zon.pdf12 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 24-25_11zon.pdf12 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4_.pdf12 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera Form 3 Q1_.pdf12 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2_.pdf12 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 23-24_11zon.pdf12 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q 1 24-25_11zon.pdf12 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q 2 24-25_11zon.pdf12 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf5 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2_11zon.pdf5 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera Form 3_11zon.pdf5 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DP Disclosure.pdf22 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: JA Disclosure.pdf22 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: PB Disclosure.pdf22 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: RS-Disclosure.pdf22 Nov 2023
Other - LegalFile: REA51600148241.pdf22 Nov 2023
Details of encumbrances concerned to FinanceFile: NO FINANCIAL ENCUMBRENCE.pdf4 Nov 2023
Details of encumbrances concerned to FinanceFile: NO ENCUMRENCE LEGAL.pdf4 Nov 2023
Details of encumbrances concerned to LegalFile: NO FINANCIAL ENCUMBRENCE.pdf4 Nov 2023
Details of encumbrances concerned to LegalFile: NO ENCUMRENCE LEGAL.pdf4 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration.pdf4 Nov 2023
Deviation Report with respect to Allotment letterFile: NO DEVIATION REGARDING ALLOTMENT LETTER.pdf4 Nov 2023
Deviation Report with respect to model copy of AgreementFile: NO DEVIATION REGARDING AGREEMENT.pdf4 Nov 2023
Other - FinanceFile: Declaration.pdf4 Nov 2023
Other - FinanceFile: Authorization Letter.pdf4 Nov 2023
Other - FinanceFile: MOU.pdf4 Nov 2023
Proforma of Agreement for saleFile: FINAL DRAFT AGREEMENT.pdf19 Oct 2023
Proforma of Allotment letterFile: FINAL DRAFT ALLOTMENT.pdf19 Oct 2023
Declaration in FORM BFile: Form-B Digambar Vitthal Pawar_2_11zon.pdf18 Oct 2023
Declaration in FORM BFile: Form-B Jaywant Deoram Aher_3_11zon.pdf18 Oct 2023
Declaration in FORM BFile: Form-B Prakash Nanaji Bhamre_4_11zon.pdf18 Oct 2023
Declaration in FORM BFile: Form-B Ravindra Daga Shinde_1_11zon.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 With Udin_compressed.pdf18 Oct 2023
Layout approvalFile: LAYOUT_compressed.pdf17 Oct 2023
Building plan approvalFile: PLAN_compressed.pdf17 Oct 2023
Copy of Layout Approval (in case of layout)File: LAYOUT_compressed.pdf17 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN_compressed.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf17 Oct 2023
Details of encumbrances concerned to FinanceFile: NO ENCUMBERENCE LEGAL.pdf11 Oct 2023
Details of encumbrances concerned to LegalFile: NO ENCUMBERENCE LEGAL.pdf11 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Rera Commencement Certificate_7_11zon.pdf11 Oct 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCMENT CERTIFICATE.pdf11 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPERATE BANK AC.pdf11 Oct 2023
PAN CardFile: Rera Jaywant Aher_PAN.pdf10 Oct 2023
PAN CardFile: Rera Prakash Bhamare PAN.pdf10 Oct 2023
PAN CardFile: Rera Ravindra Shinde PAN.pdf10 Oct 2023
PAN CardFile: Rera Digambar Pawar PAN.pdf10 Oct 2023
Copy of the legal title reportFile: shrinivasa castle rera title report_compressed.pdf10 Oct 2023
CERSAI detailsFile: CERSAI REPORT_merged.pdf10 Oct 2023

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 24 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHRINIVASA CASTLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OPP AUNDUMBER LAWN4,100+ in Nashik

Builder: JAYWANT DEORAM AHER

JAYWANT DEORAM AHER has 1 registration on MahaRERA, including SHRINIVASA CASTLE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SHRINIVASA CASTLE is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRINIVASA CASTLE?

The registered promoter entity is JAYWANT DEORAM AHER, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRINIVASA CASTLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRINIVASA CASTLE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRINIVASA CASTLE?

The professionals named in the filing: Architect: LILADHARA JAWALE; Engineer: PANKAJ MAHALE; Chartered Accountant: ABHIJEET SHINDE & ASSOCIATES; Chartered Accountant: TUSHAR LOKHANDEBHALGAT BOTHARA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRINIVASA CASTLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRINIVASA CASTLE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRINIVASA CASTLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.