Home / Browse projects / Mumbai Suburban, Maharashtra / Shri Sai Vishram CHSL
Shri Sai Vishram CHSL
By Aaryadeep Builders & Developers
RG-MH-11668 · RERA P51700006499 · Last updated on MahaRERA portal: 26 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 7 complaints at MahaRERA
- Completion date moved by 72 months
- 5 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shri Sai Vishram CHSL is a Residential / Group Housing project by Aaryadeep Builders & Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51700006499 on 14 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 72 months from the original filing. 7 complaints are on record with the regulator.
At a glance
Project
- NameShri Sai Vishram CHSL
- TypeResidential / Group Housing
- Location
- Laxman Mhatre Road
- Dahisar
- Borivali
- Mumbai Suburban
- 400068
- Pincode400068
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700006499
- ReraGenie IDRG-MH-11668
Builder
- NameAaryadeep Builders & Developers
- Entity typePartnership
- PartnerSayed Mohammed Hussain
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed133 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Shri Sai Vishram CHSL | NA | 24 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.
Shri Sai Vishram CHSL: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 26 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 5% |
| Storm Water Drains | Yes | 10% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed10
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Tangents Design Cell |
| Engineer | PROFILES Structural Consultants |
| Chartered Accountant | Bhumika C Agrawal |
| Chartered Accountant | Motilal & Associates LLP |
| Partner | Role in project |
|---|---|
| Aaryadeep Builders & Developers | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the pandemic of Covid 19 and subsequent lockdown of almost14 months, we are facing a shortage of labour. Considering this fact we are sure the work on this project is bound to get delayed. We are trying to finish the remaining work as early as possible with whatever resources available at our disposal as of now. The improvement in the pandemic situation is very unpredictable. And hence we request the authority to extend the date of completion up to 30th December, 2022.
Reason as filed by the promoterThe Development plan for 2014-2034 was published by the Municipal Corporation of Greater Mumbai (MCGM) on 25th February 2015. The revised D.P. as stated above was scrapped on 23rd April 2015 due to various anomalies, by the Government of Maharashtra. The new draft Development Plan (D.P.) was published on 5th February 2016. The MCGM had no clarity for ongoing proposals whether they should apply D.C. Rules 1991 or DCPR 2034. Thus it is a well-known and documented fact that the ambiguity in D.C. Regulations 1991 & DCPR 2034 created confusion and chaos in the MCGM Building Department Further C.C.
Reason as filed by the promoterDear Sir, We had applied for extension of the project on 22/02/2023 vide extension application no: EXT51800013926. We had submitted the consents of the allottees along with the letter to yourself giving the reasons in brief for the extension applied. In both, the consents as well as the covering letter we had requested to extend the project deadline by one year i.e. by 31/12/2023. But somehow due to typographic error in the online application, the date of extension was typed as 13/10/2023 instead of 31/12/2023. We regret this error on our part and hence we had applied for correction in the cer
Reason as filed by the promoterThe project had slowed down due to Corona pandemic till August 2021. On September 30th 2021 The Airport Authority Of India asked the MCGM to stop all the permissions given vide their email of the same date. ( Copy attached in Other Column below). After a process of reapplying, we received the permission after three months on 31/12/2021. Due to this delay of three months our contractor raised some issues of loss due to stoppage of work in this period. The dispute was ultimately resolved after settlement with him in ..... This has caused tremendous financial stress on the project. We have now ap
Reason as filed by the promoterWe were not receiving payments from allottees who have borrowed from banks via housing loan as their banker were asking us to get the project completion date extended from Maharera. Other buyers were also waiting for the same. we have completed the rehab portion of earlier society members and have applied for part occupancy certificate from MCGM. Now we have made additional finance available and the remaining 15% work of structural construction and 60% of finishing work is being carried out in a phased manner to avoid additional interest cost on fresh borrowings. Once we get the extension appr
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 305/2016 | High Court Mumbai | Not Listed Pending |
| 259/2017 | High Court Mumbai | Not Listed Pending |
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000056559 | MR. PRANIL A. CHAVAN | M/S AARYADEEP BUILDERS | 13/10/2018 |
| CC006000000057863 | SHRIKANT JOSHI & AARTI JOSHI | AARYADEEP BUILDERS AND DEVELOPERS | 29/01/2019 |
| CC006000000194964 | Meera P. Paralkar | Saaga InfraProjects Pvt Ltd | 20/11/2020 |
| CC006000000194972 | Ninad Paralkar | Saaga InfraProjects Pvt Ltd | 20/11/2020 |
| CC006000000195667 | HITESH ICHHASHANKAR TRIVEDI | Saaga Infraprojects Pvt Ltd | 16/01/2021 |
| CC006000000195730 | Shreya Hitesh Trivedi | Saaga Infraprojects Pvt Ltd | 23/01/2021 |
| CC006000000195730 | Shreya Hitesh Trivedi | Saaga Infraprojects Pvt Ltd | 23/01/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed133
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: Affidavit cum Declaration Form B.pdf | 26 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3 march 25.pdf | 12 Jul 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf | 12 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate MAR 25.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate MAR 25.pdf | 9 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure or sold unsold inventory.pdf | 24 Apr 2025 |
| Certificates of CA (Form 3)File: Ca Certificate Form 3.pdf | 8 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Microsoft Word - Architect Certificate Maha RERA Sai Vishram_18_01_2025.pdf | 3 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Microsoft Word - Engineer_Certificate_Dahisar_DEC 24_13012025.pdf | 3 Feb 2025 |
| Layout approvalFile: Plan with BU Area.pdf | 9 Dec 2024 |
| Building plan approvalFile: Plan with BU Area.pdf | 9 Dec 2024 |
| Building plan approvalFile: Plan Sanctioned.pdf | 9 Dec 2024 |
| Building plan approvalFile: Plan Sanctioned 2.pdf | 9 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: Plan with BU Area.pdf | 9 Dec 2024 |
| Declaration in FORM BFile: Affidavit cum declaration FORM B.pdf | 9 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate June 24.pdf | 9 Dec 2024 |
| Building Plan Approval (IOD)File: Plan with BU Area.pdf | 9 Dec 2024 |
| Building Plan Approval (IOD)File: Plan Sanctioned 2.pdf | 9 Dec 2024 |
| Building Plan Approval (IOD)File: Plan Sanctioned.pdf | 9 Dec 2024 |
| Other - LegalFile: High court order CT_Shri Sai Vishram_Aaryadeep.pdf | 9 Dec 2024 |
| Other - LegalFile: Aarayadeep affidavit.pdf | 9 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure inventory.pdf | 9 Dec 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Bank Account.pdf | 9 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality engineer certificate.pdf | 9 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CaA Certificate Form 5.pdf | 9 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 23_08_20244 ext.pdf | 11 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate_June 24 ext.pdf | 11 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate_ext.pdf | 11 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 23_08_20244 ext.pdf | 11 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate_June 24 ext.pdf | 11 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate_ext.pdf | 11 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate june 23.pdf | 30 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate sep 23.pdf | 30 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate_june 23.pdf | 30 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate_Dahisar_sep 23.pdf | 30 Oct 2023 |
| Certificates of CA (Form 3)File: CA Certificate june 23.pdf | 30 Oct 2023 |
| Certificates of CA (Form 3)File: CA Certificate sep 23.pdf | 30 Oct 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration of interest in other Rera regd projects Munnabhai.pdf | 23 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 22 Feb 2023 |
| Proforma of Agreement for saleFile: Proforma of Agreement for Sale.pdf | 22 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance to Legal.pdf | 21 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance to Legal.pdf | 21 Feb 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation for Allotment .pdf | 21 Feb 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement.pdf | 21 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Archit certificate.pdf | 18 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assu certificate Dec-22.pdf | 18 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 18 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Separate bank Account.pdf | 23 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 2 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 2 Nov 2022 |
| Certificates of CA (Form 3)File: CA Certificate Form 3.pdf | 2 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certificate Form 5 21.pdf | 2 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate Form 5 22.pdf | 2 Nov 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200226141163_For_Debtor_Based_Search_18_12_2021_19_37_42_234.pdf | 10 May 2022 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 10 May 2022 |
| Certificates of CA (Form 3)File: CA certificate Form 3.pdf | 1 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate 2020.pdf | 29 Jun 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate 2021.pdf | 29 Jun 2021 |
| Details of Restarting of Construction work post lockdownFile: Details of restart of work post lockdown.pdf | 29 Jun 2021 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf | 26 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 17-18.pdf | 26 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf | 26 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf | 26 Jun 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC 20 Floors.pdf | 21 Jun 2021 |
| Disclosure of sold/ booked inventoryFile: Inventory of Sold-Unsold Units.pdf | 21 Jun 2021 |
| Building plan approvalFile: 21 Floor Plan page 1.pdf | 28 Jan 2020 |
| Building plan approvalFile: 21 Floor Plan page 2.pdf | 28 Jan 2020 |
| Building plan approvalFile: 21 floors NoteSheet signed.pdf | 28 Jan 2020 |
| Building Plan Approval (IOD)File: 21 Floor Plan page 1.pdf | 28 Jan 2020 |
| Building Plan Approval (IOD)File: 21 Floor Plan page 2.pdf | 28 Jan 2020 |
| Building Plan Approval (IOD)File: 21 floors NoteSheet signed.pdf | 28 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 12 Dec 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 12 Dec 2019 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 12 Dec 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: FurtherCC_signed.pdf | 29 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 21 Aug 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 21 Aug 2019 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 21 Aug 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 9 Feb 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 9 Feb 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 133 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Shri Sai Vishram CHSL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dahisar6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 177 registered projects within 2 km.
ICON
RAGHU LEELA REALTORS PRIVATE LIMITED
ORNATE SOLITAIRE
ORNATE DAHISAR DEVELOPERS
EMPIRE HEIGHTS
EMPIRE REALTY
SHAKTI DHAM-WING A, VRINDAVAN-WING B RESIDENTI
DHARTI DEVELOPERS
RAGHUKUL CHSL
RAMNIYATI REALITIES LLP
Earth Residency Wing C and Wing D
Earth Estate Developers Pvt Ltd
See every Mumbai Suburban project, with the district possession charts
Builder: Aaryadeep Builders & Developers
Aaryadeep Builders & Developers has 1 registration on MahaRERA, including Shri Sai Vishram CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Shri Sai Vishram CHSL shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Shri Sai Vishram CHSL is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shri Sai Vishram CHSL?
The registered promoter entity is Aaryadeep Builders & Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shri Sai Vishram CHSL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Shri Sai Vishram CHSL?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Shri Sai Vishram CHSL?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shri Sai Vishram CHSL?
The professionals named in the filing: Architect: Tangents Design Cell; Engineer: PROFILES Structural Consultants; Chartered Accountant: Bhumika C Agrawal; Chartered Accountant: Motilal & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shri Sai Vishram CHSL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback