Completed No litigation declared Others project

SHRI MARYAMBI VANSH PARK

By NARENDRA NAMDEO DHADVE

RG-MH-45056 · RERA P52800013301 · Last updated on MahaRERA portal: 10 Aug 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Stilt Floor, 50%
0Complaints at MahaRERAon this registration
Jump to the 30 documents Report an error

SHRI MARYAMBI VANSH PARK is a Others project by NARENDRA NAMDEO DHADVE in Ratnagiri, Maharashtra, registered with MahaRERA as P52800013301 on 22 Sep 2017. The registration is recorded completed; possession was promised by 30 Jun 2023. The completion date has moved by 42 months from the original filing.

At a glance

Project

  • NameSHRI MARYAMBI VANSH PARK
  • TypeOthers
  • Location
    • Shringartali
    • Guhagar
    • Ratnagiri
    • 415724
  • Pincode415724
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800013301
  • ReraGenie IDRG-MH-45056

Builder

  • NameNARENDRA NAMDEO DHADVE
  • Entity typeIndividual

Key dates

this monthRegisteredSep 2017First promiseDec 2019Revised toJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Sep 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed30 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRI MARYAMBI VANSH PARKNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 50%.

SHRI MARYAMBI VANSH PARK: 35% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed151

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots151
Closed/Covered1
Open Space150

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,900 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
YUSUF EBRAHIM DINGANKARShringartaliRatnagiri

Approvals and building plan

Permissible FSI1846.8
Proposed, not sanctioned1,847 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPahat,near St Depo At Post Guhagar City Guhagar Dist ratnagiri Pin 415703 Maharashtra

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHAY KAANEKAR
EngineerRAVINDRA PATIL
PartnerRole in project
NARENDRA NAMDEO DHADVE-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800005169Dec 2019 → Dec 2020

Reason as filed by the promoterThe Owner Yusuf Dingankar expired on 31.01.2018. His legal heirs are not giving Power of Attorney in favour of builder. In the absence of Power of Attorney by the legal heirs the builder is unable to proceed with the work. Filed application in the Guhagar court for the same.

EXT52800009478Dec 2019 → Dec 2022

Reason as filed by the promoterThe Landowner expired in the year 2018. His legal heirs were not giving NOC to continue with the project. We approached the honorable court for continuation of the project. The court has passed order in feb, 2021 in our favor. Since the project was stuck up due to court case we shall be glad if our project completion is extended to 31/12/2022. We have the court order but are unable to upload it as there is no option to upload.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Aug 2023

Documents filed30

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PHOTO-2023-06-19-13-52-14.pdf10 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 1920.pdf13 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2122.pdf13 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2021.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 2021.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 1920.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 2021.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2122.pdf13 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 1 1920.pdf13 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2021.pdf13 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2122.pdf13 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: annual report.pdf26 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Report 18-19.pdf26 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf12 Oct 2019
PAN CardFile: PAN.pdf16 Sep 2017
Copy of the legal title reportFile: TITLE REPORT.pdf16 Sep 2017
Details of encumbrancesFile: encumbrance.pdf16 Sep 2017
Declaration in FORM BFile: form b.pdf16 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf16 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf16 Sep 2017
Certificates of CA (Form 3)File: Form 3 new.pdf16 Sep 2017
Proforma of Allotment letterFile: SAMPLE AGREEMENT.pdf16 Sep 2017
Layout approvalFile: Scan-0006.pdf14 Sep 2017
Layout approvalFile: Scan-0007.pdf14 Sep 2017
Building plan approvalFile: Scan-0006.pdf14 Sep 2017
Building plan approvalFile: Scan-0007.pdf14 Sep 2017
Copy of Layout Approval (in case of layout)File: Scan-0006.pdf14 Sep 2017
Copy of Layout Approval (in case of layout)File: Scan-0007.pdf14 Sep 2017
Building Plan Approval (IOD)File: Scan-0006.pdf14 Sep 2017
Building Plan Approval (IOD)File: Scan-0007.pdf14 Sep 2017

How this compares with Ratnagiri

15%of Ratnagiri projects moved their completion datethis one moved by 42 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is completed

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep SHRI MARYAMBI VANSH PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shringartali1,100+ in Ratnagiri

2 kmSHRI MARYAMBI VANSH PARKCompleted 3Lapsed / revoked 8Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: NARENDRA NAMDEO DHADVE

NARENDRA NAMDEO DHADVE has 1 registration on MahaRERA, including SHRI MARYAMBI VANSH PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if SHRI MARYAMBI VANSH PARK is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRI MARYAMBI VANSH PARK?

The registered promoter entity is NARENDRA NAMDEO DHADVE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRI MARYAMBI VANSH PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRI MARYAMBI VANSH PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRI MARYAMBI VANSH PARK?

The professionals named in the filing: Architect: ABHAY KAANEKAR; Engineer: RAVINDRA PATIL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRI MARYAMBI VANSH PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRI MARYAMBI VANSH PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRI MARYAMBI VANSH PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.