ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / SHRI KRISHNA NAGARI

Registered No litigation declared Plotted project

SHRI KRISHNA NAGARI

By JAGGUMAL SACHANI, MAHESH SACHANI, JYOTI SACHANI

RG-MH-18936 · RERA P50500077890 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 15 months from the original
53 of 58Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

SHRI KRISHNA NAGARI is a Plotted project by JAGGUMAL SACHANI, MAHESH SACHANI, JYOTI SACHANI in Nagpur, Maharashtra, registered with MahaRERA as P50500077890 on 13 Nov 2024. Possession is promised by 31 Mar 2027. The completion date has moved by 15 months from the original filing. 5 of the 58 units on this registration are recorded sold or booked.

At a glance

Project

  • NameSHRI KRISHNA NAGARI
  • TypePlotted
  • Location
    • MOUZA-GODHANI(RLY)
    • Godhani (Railway)
    • Nagpur (Rural)
    • Nagpur
    • 441203
  • Pincode441203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500077890
  • ReraGenie IDRG-MH-18936

Builder

  • NameJAGGUMAL SACHANI, MAHESH SACHANI, JYOTI SACHANI
  • Entity typeOthers

Key dates

this monthRegisteredNov 2024First promiseDec 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on13 Nov 2024
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2025)
  • BuildingsNot stated in filing
  • Documents filed75 files

Current status

9%5 of 58 units booked

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes52%
Water SupplyYes48%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes42%
Storm Water DrainsYes35%
Landscaping & Tree PlantingYes0%
Street LightingYes8%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes15%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes35%
Aggregate area of recreational Open SpaceYes40%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,167 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityNagpur Metropolitan Region Development Authority (MNRDA)

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Akarshan Busiplex, 26, Central Bazaar Road, Ramdaspeth, Nagpur Maharashtra.440010

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAVIN DHONE AND ASSOCIATES
EngineerPRAVIN DHONE AND ASSOCIATES
Chartered AccountantCA ANKIT TALREJA
Chartered AccountantSUMIT SANTOSH AGARWAL & ASSOCIATES
PartnerRole in project
JAGGUMAL SACHANI, MAHESH SACHANI, JYOTI SACHANI-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA12022619814Dec 2025 → Mar 2027

Reason as filed by the promoterI, MAHESH JAGGUMAL SACHANI, Promoter of the real estate project “SHRI KRISHNA NAGARI” bearing MahaRERA Registration No. P50500077890, hereby request an extension of 15 months, i.e. up to 31/03/2027, for completion of the said project. I respectfully submit that despite sincere efforts, the project progress was delayed due to unavoidable circumstances beyond the promoter’s control. The delay was mainly caused due to delay in approvals / permissions from competent authority, increase in construction material and labour costs, labour shortage, and cash flow constraints due to delayed receivables,

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 DEC-25.pdf18 Jul 2026
Withdrawal Update Form 1File: FORM-1 DEC-25.pdf18 Jul 2026
Withdrawal Update Form 2File: FORM-2 DEC-25.pdf18 Jul 2026
Withdrawal Update Form 2File: FORM-2 DEC-25.pdf18 Jul 2026
Withdrawal Update Form 3File: FORM-3 DEC-2025 SHRI KRISHNA NAGARI SCANNED COMPRESSED.pdf18 Jul 2026
Withdrawal Update Form 3File: FORM-3 DEC-2025 SHRI KRISHNA NAGARI SCANNED COMPRESSED.pdf18 Jul 2026
Form 1File: FORM-1 DEC-2024.pdf11 Feb 2026
Form 2File: FORM-2 DEC-2024.pdf11 Feb 2026
Form 3File: FORM-3 DEC-2024 SHRI KRISHNA NAGARI SCANNED COMPRESSED.pdf11 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD DEC-2024 SHRI KRISHNA NAGARI.pdf11 Feb 2026
Form 1File: FORM-1 MAR-2025.pdf11 Feb 2026
Form 2File: FORM-2 MARCH-2025.pdf11 Feb 2026
Form 3File: FORM-3 MAR-2025 SHRI KRISHNA NAGARI SCANNED COMPRESSED.pdf11 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD MAR-2025 SHRI KRISHNA NAGARI.pdf11 Feb 2026
Withdrawal Update Form 1File: FORM-1 JUN-25.pdf11 Feb 2026
Withdrawal Update Form 1File: FORM-1 SEPT-25.pdf11 Feb 2026
Withdrawal Update Form 1File: FORM-1 DEC-25.pdf11 Feb 2026
Withdrawal Update Form 2File: FORM-2 JUN-2025.pdf11 Feb 2026
Withdrawal Update Form 2File: FORM-2 SEPT-25.pdf11 Feb 2026
Withdrawal Update Form 2File: FORM-2 DEC-25.pdf11 Feb 2026
Withdrawal Update Form 3File: FORM-3 JUN-2025 SHRI KRISHNA NAGARI SCANNED COMPRESSED.pdf11 Feb 2026
Withdrawal Update Form 3File: FORM-3 SEPT-2025 SHRI KRISHNA NAGARI SCANNED COMPRESSED.pdf11 Feb 2026
Withdrawal Update Form 3File: FORM-3 DEC-2025 SHRI KRISHNA NAGARI SCANNED COMPRESSED.pdf11 Feb 2026
Form 2A (FY 2024-2025)File: FORM-2A MARCH-2025.pdf11 Feb 2026
Form 5 (FY 2024-2025)File: FORM-5 MARCH-2025 SCANNED.pdf31 Jan 2026
Other - TechnicalFile: MAil.pdf8 Nov 2024
CERSAI detailsFile: Cersai Declaration.pdf25 Oct 2024
Details of encumbrances concerned to FinanceFile: Search_Report_-_SHRI_KRISHNA_NAGARI[1].pdf23 Oct 2024
Other - LegalFile: Search_Report_-_SHRI_KRISHNA_NAGARI[1].pdf23 Oct 2024
Details of encumbrances concerned to LegalFile: Search_Report_-_SHRI_KRISHNA_NAGARI[1].pdf23 Oct 2024
Other - FinanceFile: Cersai Declaration.pdf23 Oct 2024
Building plan approval or NA orderFile: LAYOUT PLAN_compressed (1).pdf10 Oct 2024
Layout approvalFile: LAYOUT PLAN_compressed (1).pdf10 Oct 2024
Copy of the legal title reportFile: Search Report - SHRI KRISHNA NAGARI.pdf10 Oct 2024
Details of encumbrances concerned to FinanceFile: ENCUM_Finance_Shri Krishna Nagari.pdf10 Oct 2024
Details of encumbrances concerned to FinanceFile: ENCUM_LEGAL_Shri Krishna Nagari.pdf10 Oct 2024
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN_compressed (1).pdf10 Oct 2024
Proforma of Allotment letterFile: allotment.pdf10 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER SKN.pdf10 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: LAYOUT PLAN_compressed (1).pdf10 Oct 2024
Other - LegalFile: DECLARATION (4)_Joint Account.pdf10 Oct 2024
Declaration about Commencement CertificateFile: form d.pdf10 Oct 2024
Deviation Report with respect to Allotment letterFile: Deviation Report - ALLOTMENT LETTER_L - S-K NAGARI.pdf10 Oct 2024
Details of encumbrances concerned to LegalFile: ENCUM_Finance_Shri Krishna Nagari.pdf10 Oct 2024
Details of encumbrances concerned to LegalFile: ENCUM_LEGAL_Shri Krishna Nagari.pdf10 Oct 2024
Other - FinanceFile: DECLARATION (4)_Joint Account.pdf10 Oct 2024
Other - TechnicalFile: DECLARATION (4)_Joint Account.pdf10 Oct 2024
Other - TechnicalFile: Quality-Annexure A _ SKN.pdf10 Oct 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT_ATS.pdf10 Oct 2024
Proforma of Agreement for saleFile: Agreement to Sale.pdf10 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: INTERES DEC_Mahesh Sachani.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fORM 3.pdf9 Oct 2024
PAN CardFile: mahesh sachani pan.pdf8 Oct 2024
PAN CardFile: jaggumal sachani pan.pdf8 Oct 2024
PAN CardFile: jyoti sachani pan.pdf8 Oct 2024
Declaration in FORM BFile: form b.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Ar_Certificate.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC_1.pdf8 Oct 2024
Other - LegalFile: WILL DEED_compressed.pdf8 Oct 2024
Other - LegalFile: DEV AGREEMENT.pdf8 Oct 2024
Other - LegalFile: authorized_signatory_SKN.pdf8 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf8 Oct 2024
Other - FinanceFile: DECLARATION (4)_Joint Account.pdf8 Oct 2024
Other - FinanceFile: WILL DEED_compressed.pdf8 Oct 2024
Other - FinanceFile: DEV AGREEMENT.pdf8 Oct 2024
Other - FinanceFile: authorized_signatory_SKN.pdf8 Oct 2024
Other - TechnicalFile: DEV AGREEMENT.pdf8 Oct 2024
Other - TechnicalFile: 1107- BDASR0-1107- Jaggumal Jeevanmal Sachani-2.pdf8 Oct 2024
Other - TechnicalFile: authorized_signatory_SKN.pdf8 Oct 2024
Other - TechnicalFile: WILL DEED_compressed.pdf8 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: INTERES DEC_Jaggumal Sachani.pdf8 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: INTERES DEC_Jyoti Sachani.pdf8 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: format b_.pdf8 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for securedunsecured finance availed for the project.pdf8 Oct 2024

How this compares with Nagpur

9%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 15 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHRI KRISHNA NAGARI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOUZA-GODHANI(RLY)2,800+ in Nagpur

2 kmSHRI KRISHNA NAGARICompleted 20Lapsed / revoked 6Other 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 56 registered projects within 2 km.

Builder: JAGGUMAL SACHANI, MAHESH SACHANI, JYOTI SACHANI

JAGGUMAL SACHANI, MAHESH SACHANI, JYOTI SACHANI has 1 registration on MahaRERA, including SHRI KRISHNA NAGARI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if SHRI KRISHNA NAGARI is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRI KRISHNA NAGARI?

The registered promoter entity is JAGGUMAL SACHANI, MAHESH SACHANI, JYOTI SACHANI, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRI KRISHNA NAGARI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRI KRISHNA NAGARI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRI KRISHNA NAGARI?

The professionals named in the filing: Architect: PRAVIN DHONE AND ASSOCIATES; Engineer: PRAVIN DHONE AND ASSOCIATES; Chartered Accountant: CA ANKIT TALREJA; Chartered Accountant: SUMIT SANTOSH AGARWAL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRI KRISHNA NAGARI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRI KRISHNA NAGARI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRI KRISHNA NAGARI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.