Home / Browse projects / Pune, Maharashtra / SHREEJI SHARAN
SHREEJI SHARAN
RG-MH-15423 · RERA P52100024039 · Last updated on MahaRERA portal: 22 Feb 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREEJI SHARAN is a Residential / Group Housing project by PRESTIGE INFRA in Pune, Maharashtra, registered with MahaRERA as P52100024039 on 16 Jan 2020. The registration is recorded completed; possession was promised by 29 Jun 2024. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameSHREEJI SHARAN
- TypeResidential / Group Housing
- Location
- CHOVISAWADI
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412105
- Pincode412105
- RERA no.P52100024039
- ReraGenie IDRG-MH-15423
Builder
- NamePRESTIGE INFRA
- Entity typePartnership
- Other registrations2 more →
- Completed1 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on16 Jan 2020
- Promised completion29 Jun 2024
- Revised completionRevised to 29 Jun 2024 (originally 30 Jun 2023)
- Buildings1 building record
- Documents filed99 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A BUILDING | NA | 16 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
A BUILDING: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 22 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| BAJRANG GULAB TAPKIR | CHARHOLI | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DREAM SPACE |
| Engineer | AADHAR ENGINEERS |
| Chartered Accountant | M S KUMBHAR AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| PRESTIGE INFRA | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoteras per letter of request attached
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Dec 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Dec 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 20 Dec 2024
Documents filed99
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 ARCH CERT A WING SEPT-23.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 ARCH CERT A WING DEC-23.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 ARCH CERT A WING MAR-24.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 ARCH CERT A WING JUN-24.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 ARCH CERT A WING SEP-24.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 ARCH CERT A WING OCT-24.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 4 A WING.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 ENG CERT A WING SEP-23.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 ENG CERT A WING DEC-23.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 ENG CERT A WING MAR-24.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 ENG CERT A WING JUN-24.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 ENG CERT A WING SEP-24.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 ENG CERT A WING OCT-24.pdf | 22 Feb 2025 |
| Other - LegalFile: FORM 4 A WING.pdf | 22 Feb 2025 |
| Other - TechnicalFile: FORM 4 A WING.pdf | 22 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate A and B Wing.pdf | 20 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 FORM 3 A WING SEPT-21.pdf | 30 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 FORM 3 A WING DEC-21.pdf | 30 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3 A WING MAR-22.pdf | 30 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 FORM 3 A WING JUN-22.pdf | 30 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 FORM 3 A WING SEPT-22.pdf | 30 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 FORM 3 A WING DEC-22.pdf | 30 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 FORM 3 A WING MAR-23.pdf | 30 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: AUDIT REPORT A WING 21-22.pdf | 30 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: AUDIT REPORT A WING 22-23.pdf | 30 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Not Applicable A Wing.pdf | 28 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Not Applicable A Wing.pdf | 28 Nov 2023 |
| Proforma of Agreement for saleFile: Agreement to Sales A Wing.pdf | 28 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: A WING QUAL ASSU 2020.pdf | 15 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: A WING QUAL ASSU 2021.pdf | 15 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: A WING QUAL ASSU 2022.pdf | 15 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: A WING QUAL ASSU 2023.pdf | 15 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 1 SOLD UNSOLD Sept-2021 A Wing.pdf | 15 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 2 SOLD UNSOLD Dec-2021 A Wing.pdf | 15 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 3 SOLD UNSOLD Mar-2022 A Wing.pdf | 15 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 4 SOLD UNSOLD Jun-2022 A Wing.pdf | 15 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 5 SOLD UNSOLD Sept-2022 A Wing.pdf | 15 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 6 SOLD UNSOLD Dec-2022 A Wing.pdf | 15 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 7 SOLD UNSOLD Mar-2023 A Wing.pdf | 15 Nov 2023 |
| Declaration in FORM BFile: AFFIDAVIT NOTARY.pdf | 19 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 4 ARCHITECTS WING-A 31-12-2021.pdf | 25 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 ARCHITECTS WING-A 30-06-2021 001.pdf | 25 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 ARCHITECTS WING -A 30-09-2021 001.pdf | 25 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 ARCHITECTS WING-A 31-12-2021.pdf | 25 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 ARCHITECTS (WING -A ) 31-03-2022.pdf | 25 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 ARCITECT WING -A 30-06-22.pdf | 25 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Architect (Wing A) 30-09-2022.pdf | 25 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 ARCHITECT 31-12-2022 001.pdf | 25 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 ARCHITECT WING A 31-03-2023 001.pdf | 25 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 ARCHITECT WING A 30-06-2023 001.pdf | 25 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 AADHAR 30-6-2021 001.pdf | 25 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 AADHAR 30-09-2021 001.pdf | 25 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 AADHAR 31-12-2021 001 (1).pdf | 25 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 AADHAR 31-03-2022 001.pdf | 25 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 ADHAR 30-06-22 001.pdf | 25 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7 Aadhar 30-09-2022 001.pdf | 25 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 aadhar 31-12-22 001.pdf | 25 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 AADHAR 31-03-2023 001.pdf | 25 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 AADHAR 30-6-2023 001.pdf | 25 Aug 2023 |
| Building plan approvalFile: Plan Pass 01.pdf | 5 Feb 2022 |
| Building plan approvalFile: Plan Pass 02.pdf | 5 Feb 2022 |
| Building plan approvalFile: Plan Pass 03.pdf | 5 Feb 2022 |
| Building plan approvalFile: Plan Pass 04.pdf | 5 Feb 2022 |
| Building plan approvalFile: Plan Pass 06.pdf | 5 Feb 2022 |
| Details of encumbrancesFile: Loan Details Updation.pdf | 5 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Pass 01.pdf | 5 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Pass 02.pdf | 5 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Pass 03.pdf | 5 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Pass 04.pdf | 5 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Pass 06.pdf | 5 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf | 5 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Plan Pass 05.pdf | 5 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 02_compressed.pdf | 5 Feb 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_DCB.pdf | 5 Feb 2022 |
| CERSAI detailsFile: Cersai report 01_compressed.pdf | 5 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: AUDIT REPORT F Y 2020-21.pdf | 5 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Prestige iNFRA 19-20.pdf | 16 Oct 2020 |
| PAN CardFile: Prestige Infra Pan.pdf | 10 Jan 2020 |
| Proforma of Allotment letterFile: AGREEMENT AS PER RERA.pdf | 3 Jan 2020 |
| Layout approvalFile: LAYOUT.pdf | 31 Dec 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 99 filed documents as one ZIP, foldered, with a manifest
Keep SHREEJI SHARAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHOVISAWADI13,700+ in Pune
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: PRESTIGE INFRA
PRESTIGE INFRA has 3 registrations on MahaRERA, including SHREEJI SHARAN and SHREEJI SHARAN B WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SHREEJI SHARAN is delayed beyond 29 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREEJI SHARAN?
The registered promoter entity is PRESTIGE INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREEJI SHARAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREEJI SHARAN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREEJI SHARAN?
The professionals named in the filing: Architect: DREAM SPACE; Engineer: AADHAR ENGINEERS; Chartered Accountant: M S KUMBHAR AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREEJI SHARAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.