Home / Browse projects / Palghar, Maharashtra / SHREEJI NIWAS A B C WING
SHREEJI NIWAS A B C WING
RG-MH-12509 · RERA P99000002088 · Last updated on MahaRERA portal: 25 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 43 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREEJI NIWAS A B C WING is a Residential / Group Housing project by SHREEJI DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000002088 on 31 Jul 2017. Possession was promised by 30 Mar 2023 and is now 43 months past that date.
At a glance
Project
- NameSHREEJI NIWAS A B C WING
- TypeResidential / Group Housing
- Location
- pasthal
- Palghar
- 401506
- Pincode401506
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000002088
- ReraGenie IDRG-MH-12509
Builder
- NameSHREEJI DEVELOPERS
- Entity typePartnership
- PartnersJAY RAJESH PARIKH, JASMIN KANAIYALAL MEHTA, TEJAS SHAILESH MEHTA, SHAILESH JUGALDAS MEHTA, NALIN BHUPATRAI MEHTA, BHUPATRAI MANGILAL MEHTA, KEVAL JASMIN MEHTA, RAJESH KANTILAL PARIKH HUF, TEJAS SHAILESH MEHTA, SHAILESH JUGALDAS MEHTA, KEVAL JASMIN MEHTA, RAJESH KANTILAL PARIKH HUF and 12 more
- Other registrations26 more →
- Completed11 of 27
- No longer live4 lapsed, de-registered or revoked
- Past their filed date1
- Declared earlier projects7 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Jul 2017
- Promised completion30 Mar 2023
- Revised completionNone
- Buildings1 building record
- Documents filed48 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREEJI NIWAS A B C WING | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 30%.
SHREEJI NIWAS A B C WING: 39% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 30% |
| Slabs of Super Structure | 30% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NISHANT P PATIL |
| Engineer | GANESH AWAD |
| Chartered Accountant | CA ALPESH BHOGILAL SHAH |
| Chartered Accountant | CA DEVESH KANTILAL PARIKH |
| Partner | Role in project |
|---|---|
| SHREEJI DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed48
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: SHREEJI NIWAS-FORM 3 30-09-2024.PDF | 25 Nov 2024 |
| Certificates of CA (Form 3)File: SHREEJI NIWAS FORM - 3.PDF | 22 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SHREEJI NIWAS A B C WING FORM - 5.PDF | 22 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: SHREEJI ASHISH NO ENCUMBRANCES.PDF | 3 May 2024 |
| Details of encumbrancesFile: SHREEJI NIWAS NO ENCUMBRANCES.PDF | 3 May 2024 |
| Details of encumbrances concerned to LegalFile: SHREEJI ASHISH NO ENCUMBRANCES.PDF | 3 May 2024 |
| Declaration about Commencement CertificateFile: SHREEJI NIWAS FORMAT D.PDF | 3 May 2024 |
| CERSAI detailsFile: SHREEJI ASHISH CERSAI CERTIFICATE.PDF | 3 May 2024 |
| Disclosure of sold/ booked inventoryFile: SHREEJI NIWAS SOLD BOOKED INVENTORY.PDF | 3 May 2024 |
| CERSAI detailsFile: SHREEJI NIWAS CERSAI CERTIFICAT.PDF | 3 May 2024 |
| Certificates of CA (Form 3)File: SHREEJI DEVELOPERS NIWAS - FORM 3 - 31- 03 - 2022.PDF | 25 Apr 2024 |
| Certificates of CA (Form 3)File: SHREEJI DEVELOPERS NIWAS - FORM 3 - 31-03-2023.PDF | 25 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SHREEJI DEVELOPERS SHREEJI NIWAS - FORM 5 - 31-03-2022.PDF | 25 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SHREEJI DEVELOPERS SHREEJI NIWAS - FORM 5 - 31-03-2023.PDF | 25 Apr 2024 |
| Certificates of CA (Form 3)File: FORM-3 SHREEJI NIWAS-BOISAR.PDF | 19 Aug 2021 |
| Certificates of CA (Form 3)File: FORM-3 SHREEJI NIWAS.PDF | 14 Aug 2021 |
| Certificates of CA (Form 3)File: FORM-3 SHREEJI NIWAS.PDF | 14 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5 SHREEJI NIWAS.PDF | 14 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5 SHREEJI NIWAS.PDF | 14 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5.PDF | 27 Nov 2019 |
| Certificates of CA (Form 3)File: FORM 3.PDF | 27 Sep 2019 |
| Certificates of CA (Form 5)File: FORM 5.PDF | 27 Sep 2019 |
| Certificates of CA (Form 3)File: Shreeji Niwas- Boisar [form3].PDF | 26 Jun 2019 |
| Certificates of CA (Form 5)File: form 5 Shreeji NIwas Boisar.PDF | 26 Jun 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shreeji Developers - Shreeji Niwas-Architect certificat 30-09-2017.PDF | 24 May 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shreeji Developers-Shreeji Niwas- Architect certificat 30-12-2017.PDF | 24 May 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE SHREEJI NIWAS 30-12-2017.PDF | 24 May 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICATE shreeji developers shreeji niwas 30-09-2017.PDF | 24 May 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE SHREEJI NIWAS 30-09-2017.PDF | 29 Mar 2018 |
| Proforma of Allotment letterFile: Final Allotment letter Shreeji niwas.pdf | 26 Jul 2017 |
| Building plan approvalFile: Type B1 (2).pdf | 25 Jul 2017 |
| Building Plan Approval (IOD)File: Type B1 (2).pdf | 25 Jul 2017 |
| Certificates of CA (Form 3)File: form 3 shreeji niwas_CA (2 files merged) (2).pdf | 25 Jul 2017 |
| Layout approvalFile: scan0030 (2).pdf | 24 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: scan0030 (2).pdf | 24 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Collector Permission NA Order.pdf | 24 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC SHREEJI NIWAS.pdf | 24 Jul 2017 |
| Building plan approvalFile: Type A C (1).pdf | 21 Jul 2017 |
| Building plan approvalFile: Type B (2).pdf | 21 Jul 2017 |
| PAN CardFile: Company PAN Card.PDF | 21 Jul 2017 |
| Copy of the legal title reportFile: Tital Clearance Certificate.pdf | 21 Jul 2017 |
| Details of encumbrancesFile: Encumbrances Shreeji Niwas.pdf | 21 Jul 2017 |
| Building Plan Approval (IOD)File: Type A C (1).pdf | 21 Jul 2017 |
| Building Plan Approval (IOD)File: Type B (2).pdf | 21 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Permission Pradhikaran (2).pdf | 21 Jul 2017 |
| Declaration in FORM BFile: Form B Shreeji niwas.pdf | 21 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archt certificate Form A Shreeji niwas.pdf | 21 Jul 2017 |
| Proforma of Allotment letterFile: shreeji niwas agreement (2).pdf | 21 Jul 2017 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHREEJI ARCADE | SURVEY NO 198 HISSA NO 1 3 - 1 3- 2A BUNGLI HOSPITAL ROAD SANDOR VAISAI WEST 401202 | 8 | Completed | Jul 2015 | Jun 2015 |
| SHREEJI ASHISH | S NO 198 SHREEJI ASHISH BUILDING BUNGLI HOSPITAL ROAD SANDOR BHAGOLA NAKA VASAI WEST DIST PALGHAR PIN 401202 | 59 | Completed | Jun 2013 | May 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 26 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 48 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SHREEJI NIWAS A B C WING on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near pasthal3,200+ in Palghar
Filed coordinates, straight-line distance. 33 registered projects within 2 km.
Mahavir Emerald Wing D, E & F
Mahavir Estate and Properties
MAHAVIR EMERALD
RAJESH BUILDCON
GLOBE PRATHAM
GLOBE CORP
MAHAVIR KUNJ D WING A TYPE C1
Rajesh Realtors
MAHAVIR KUNJ D WING B TYPE C
Rajesh Realtors
MAHAVIR UTSAV B
Rajesh Construction
See every Palghar project, with the district possession charts
Builder: SHREEJI DEVELOPERS
SHREEJI DEVELOPERS has 27 registrations on MahaRERA, including SAHAJANAND INTEGRITY and SHREEJI DREAMS. Its filings disclose 7 earlier MahaRERA projects: declares 6 of 7 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that SHREEJI NIWAS A B C WING shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHREEJI NIWAS A B C WING is delayed beyond 30 Mar 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREEJI NIWAS A B C WING?
The registered promoter entity is SHREEJI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREEJI NIWAS A B C WING?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREEJI NIWAS A B C WING?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREEJI NIWAS A B C WING?
The professionals named in the filing: Architect: NISHANT P PATIL; Engineer: GANESH AWAD; Chartered Accountant: CA ALPESH BHOGILAL SHAH; Chartered Accountant: CA DEVESH KANTILAL PARIKH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREEJI NIWAS A B C WING?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.