Home / Browse projects / Gandhinagar, Gujarat / SHREEJI LANDMARK

Valid until 30 Jan 2027 Mixed Development project

SHREEJI LANDMARK

By SHREEJI INFRA

RG-GJ-88389 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10579/240822 · Last updated on GujRERA portal: 15 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jan 2027Possession promisedno revision filed
12 of 45Construction stages doneacross 5 buildings; furthest along: Slabs of Super Structure, 91%
144 of 174Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

SHREEJI LANDMARK is a Mixed Development project by SHREEJI INFRA in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10579/240822 on 24 Aug 2022. Possession is promised by 30 Jan 2027. 30 of the 174 units on this registration are recorded sold or booked, and 12 of 45 construction stages are filed complete.

At a glance

Project

  • NameSHREEJI LANDMARK
  • TypeMixed Development
  • Location
    • Survey No 123/1
    • 123/2
    • 125 & 126
    • F P No. 140+143+144+141
    • Draft TP 26 Vavol
    • Gandhinagar
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10579/240822
  • ReraGenie IDRG-GJ-88389

Builder

  • NameSHREEJI INFRA
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →
  • Past their filed date1

Key dates

this monthRegisteredAug 2022PromisedJan 2027

Key facts

Registration and timeline

  • StatusValid until 30 Jan 2027
  • Registered on24 Aug 2022
  • Promised completion30 Jan 2027
  • Revised completionNone
  • Buildings5 building records
  • Documents filed37 files

Current status

17%30 of 174 units booked
53.9%Of the estimated cost spent so far

Figures as on 15 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---471764
BLOCK B+C---94094
BLOCK TYPE A---12012
BLOCK TYPE A1---202
BLOCK TYPE A2---202

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 15 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is Slabs of Super Structure, at 91%.

BLOCK A59%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor3%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats64%
Sanitary fittings within the flats3%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing44%
BLOCK B+C46%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure91%
Internal walls, internal plaster, floorings, doors and windows within flats27%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks91%
External plumbing and external plaster, elevation, completion of terraces with waterproofing2%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK TYPE A42%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth75%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing25%
BLOCK TYPE A150%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK TYPE A244%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities23

As on 15 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,713 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 46.66 cr
Cost incurredRs 25.15 cr
Spent of the estimate53.89%
BuildingWingEstimatedIncurred
BLOCK B+CNARs 26.56 crRs 9.30 cr
BLOCK ANARs 13.14 crRs 10.90 cr
BLOCK TYPE ANARs 4.47 crRs 2.95 cr
BLOCK TYPE A1NARs 1.25 crRs 1.06 cr
BLOCK TYPE A2NARs 1.24 crRs 93.01 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTHE GRID-Vishwajeet Hada
EngineerJAYKUMAR J ASSUDANI

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA10579/240822 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)15 Oct 2024
Engineer's certificate annexure15 Oct 2024
RERA registration certificate24 Aug 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

17%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SHREEJI LANDMARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmSHREEJI LANDMARKOther 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 122 registered projects within 2 km.

Builder: SHREEJI INFRA

SHREEJI INFRA has 3 registrations on GujRERA, including CAPITAL CROWN and SHREEJI LANDMARK. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SHREEJI LANDMARK is delayed beyond 30 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREEJI LANDMARK?

The registered promoter entity is SHREEJI INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREEJI LANDMARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREEJI LANDMARK?

The professionals named in the filing: Architect: THE GRID-Vishwajeet Hada; Engineer: JAYKUMAR J ASSUDANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREEJI LANDMARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREEJI LANDMARK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREEJI LANDMARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.