SHREE VASARI HILL SALE BUILDING

By SHREE LAXMIDEVI DEVELOPERS

RG-MH-03097 · RERA P51800020965 · Last updated on MahaRERA portal: 14 Mar 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 50 months past the filed date
  • 10 complaints at MahaRERA
  • Completion date moved by 8 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Aug 2022Possession promised50 months past this date
6 of 11Construction stages donefurthest along: Staircases, 80%
10Complaints at MahaRERAon this registration
Jump to the 130 documents Report an error

SHREE VASARI HILL SALE BUILDING is a Residential / Group Housing project by SHREE LAXMIDEVI DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800020965 on 27 May 2019. Possession was promised by 15 Aug 2022 and is now 50 months past that date. The completion date has moved by 8 months from the original filing. 10 complaints are on record with the regulator.

At a glance

Project

  • NameSHREE VASARI HILL SALE BUILDING
  • TypeResidential / Group Housing
  • Location
    • GOREGAON MULUND LINK ROAD GOREGAON WEST MUMABI 400104
    • GOREGAON WEST
    • Borivali
    • Mumbai Suburban
    • 400104
  • Pincode400104
  • RERA no.P51800020965
  • ReraGenie IDRG-MH-03097

Builder

  • NameSHREE LAXMIDEVI DEVELOPERS
  • Entity typePartnership
  • PartnersBHARAT ASHULAL KOTHARI, RAKESH ASHULAL KOTHARI, GUNWANT ASHULAL KOTHARI, SUNNY DHANSUKHLAL SHAH, SHIRISH DHANSUKLAL SHAH
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

50 months past promisethis monthRegisteredMay 2019First promiseDec 2021Revised toAug 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on27 May 2019
  • Promised completion15 Aug 2022
  • Revised completionRevised to 15 Aug 2022 (originally 31 Dec 2021)
  • Buildings1 building record
  • Documents filed130 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Laxmi RaajvilasNA290000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

Laxmi Raajvilas: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed108

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots108
Closed/Covered87
Open Space21

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,049 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9295.0
Proposed, not sanctioned6,885 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJAWAHR NAGAR SV ROAD GOREGAON WEST

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRASIK P HINGOO
EngineerASHOK KUMAR
Chartered AccountantZUBIN HARIA & ASSOCIATES
Chartered AccountantAKSHAY & COMPANY
PartnerRole in project
SHREE LAXMIDEVI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005584Dec 2021 → Aug 2022

Reason as filed by the promoterplan revised due to new DCR rule 2034 revised approval received in January -20

Litigation declared1

CaseCourtStatus
1714/2018/2018BOMBAY HIGH COURTDisposed

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000198770Anand B. BaldawaChetak Lifespace Pvt. Ltd22/10/2021
CC006000000198773Anand B. BaldawaChetak Lifespace Pvt. Ltd22/10/2021
CC006000000198774Badri N. BaldawaChetak Lifespace Pvt. Ltd22/10/2021
CC006000000198776Pushpa BaldawaChetak Lifespace Pvt. Ltd22/10/2021
CC006000000198778Seema RandiveChetak Lifespace Pvt. Ltd22/10/2021
CC006000000333918Mukesh Mangilal JainM/s Chetak lifespace Pvt. Ltd.13/01/2023
CC006000000334055Ronak Mukesh JainM/s Chetak Lifespace Pvt. Ltd.25/01/2023
CC12400259Mukesh Mangilal JainChetak Lifespace Pvt Ltd28/09/2024
CC12400260Mukesh Mangilal JainChetak Lifespace Pvt Ltd28/09/2024
CC12500969Hiten ShahSHREE LAXMIDEVI DEVELOPERS20/03/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Dec 2023

Documents filed130

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 130 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - LAXMI RAAJVILAS (1).pdf14 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf13 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf13 Feb 2024
Certificates of CA (Form 3)File: form 3.pdf13 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc.pdf29 Dec 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: society regiteration certifcate.pdf29 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 ARCHITECTS CERTIFICATE SIGNED.pdf31 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEERS CERTIFICATE RERA.pdf31 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A ENGINEERS CERT RERA.pdf31 Oct 2023
Certificates of CA (Form 3)File: FORM 3 SHREE VASARI RERA.pdf31 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 - LRV (18-07-23).pdf21 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 10042023.pdf26 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 sld.pdf16 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2 sld001.pdf16 Jun 2023
Certificates of CA (Form 3)File: FORM 3 SHREE VASARI HILLS COMPRESS.pdf16 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf27 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1- Srchitect Certificate_ SLD (Laxmi Raajvilas).pdf3 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2-.pdf3 Mar 2023
Certificates of CA (Form 3)File: FORM 3 SLD VASARI HILLS.pdf3 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 SLD (VH) - 2021-22.pdf3 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 -2021.pdf3 Feb 2023
Details of encumbrancesFile: Encumbrance Certificate.pdf2 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1.pdf18 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineer's Certificate.pdf18 Oct 2022
Certificates of CA (Form 3)File: Rera Certificate Vasari Hills form 3 Shree laxmidevi developers Sep-22.pdf18 Oct 2022
CERSAI detailsFile: CERSAI report.pdf16 Jul 2022
Proforma of Allotment letterFile: allotment letter - Laxmi RaajVilas - rera.pdf15 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 work completion Certificate.pdf12 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 ENGINEERS CERTIFICATE.pdf12 Jul 2022
Certificates of CA (Form 3)File: RERA-FORM-3.pdf11 Jul 2022
Details of encumbrancesFile: Self Declaration - (ADHFL).pdf7 Jul 2022
Details of encumbrances concerned to LegalFile: Index II 30-6-22.pdf4 Jul 2022
Certificates of CA (Form 3)File: Form-3 (6-4-2022).pdf6 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf14 Mar 2022
Certificates of CA (Form 3)File: Form -3 C A SEP -2021.pdf20 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 .pdf18 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 - 2018.pdf8 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - 2019.pdf8 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form -2A Laxmi Raajvilas.pdf6 Jul 2021
Declaration about Commencement CertificateFile: Format-D Raajvilas.pdf1 Jul 2021
Disclosure of sold/ booked inventoryFile: Discolsure of sold -booked inventory Laxmi Raajvilas.pdf1 Jul 2021
Layout approvalFile: Amended Letter.pdf14 Jun 2021
Layout approvalFile: Sheet 1.pdf14 Jun 2021
Layout approvalFile: Sheet 2.pdf14 Jun 2021
Layout approvalFile: Sheet 3.pdf14 Jun 2021
Layout approvalFile: Sheet 4.pdf14 Jun 2021
Layout approvalFile: Sheet 5.pdf14 Jun 2021
Layout approvalFile: Sheet 6.pdf14 Jun 2021
Layout approvalFile: Sheet 7.pdf14 Jun 2021
Layout approvalFile: Sheet 8.pdf14 Jun 2021
Layout approvalFile: Sheet 9.pdf14 Jun 2021
Layout approvalFile: Sheet 10.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Amended Letter.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 1.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 2.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 3.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 4.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 5.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 6.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 7.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 8.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 9.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: Sheet 10.pdf14 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf14 Jun 2021
Certificates of CA (Form 3)File: FORM 3 - RAJVILAS MARCH -21_compressed (1).pdf9 Jun 2021
Proforma of Allotment letterFile: AGREEMENT FOR SALE Revised LRV - jan-21.pdf4 Jan 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: From-5 2019-20.pdf8 Dec 2020
Proforma of Allotment letterFile: Draft Sale Agreement.pdf8 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf26 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf26 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf26 Nov 2020
Certificates of CA (Form 3)File: FORM 3.pdf26 Nov 2020
Certificates of CA (Form 3)File: RERA FORM 3.pdf26 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf21 Nov 2020
Details of encumbrancesFile: Financial Encumbrace.pdf11 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf26 Sep 2020
Certificates of CA (Form 3)File: Form-2.pdf26 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf8 Sep 2020
OtherFile: self declaration_.pdf1 Sep 2020
Layout approvalFile: Letter.pdf28 Aug 2020

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Laxmi Callistaplot no 283 Jawahr Nagar Road No 3Goregaon West Mumabi 40010290CompletedSep 2019Late, Feb 2021
Laxmi Heightsplot no 307 Jawahr Nagar Road No 16 Goregaon West Mumabi 40010235CompletedDec 2018Dec 2018

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 8 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE VASARI HILL SALE BUILDING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GOREGAON WEST6,700+ in Mumbai Suburban

Builder: SHREE LAXMIDEVI DEVELOPERS

SHREE LAXMIDEVI DEVELOPERS has 2 registrations on MahaRERA, including LAXMI ENCLAVE and SHREE VASARI HILL SALE BUILDING. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that SHREE VASARI HILL SALE BUILDING shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHREE VASARI HILL SALE BUILDING is delayed beyond 15 Aug 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE VASARI HILL SALE BUILDING?

The registered promoter entity is SHREE LAXMIDEVI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE VASARI HILL SALE BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHREE VASARI HILL SALE BUILDING?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHREE VASARI HILL SALE BUILDING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE VASARI HILL SALE BUILDING?

The professionals named in the filing: Architect: RASIK P HINGOO; Engineer: ASHOK KUMAR; Chartered Accountant: ZUBIN HARIA & ASSOCIATES; Chartered Accountant: AKSHAY & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE VASARI HILL SALE BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE VASARI HILL SALE BUILDING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE VASARI HILL SALE BUILDING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.