Home / Browse projects / Pune, Maharashtra / SHREE SWAMI SAMARTH RESIDENCY

Registered No litigation declared Residential / Group Housing project

SHREE SWAMI SAMARTH RESIDENCY

By NITIN TUKARAM PADWAL

RG-MH-23060 · RERA P52100032762 · Last updated on MahaRERA portal: 16 Aug 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 39 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 39 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 35%
11 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

SHREE SWAMI SAMARTH RESIDENCY is a Residential / Group Housing project by NITIN TUKARAM PADWAL in Pune, Maharashtra, registered with MahaRERA as P52100032762 on 29 Jan 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 39 months from the original filing. 3 of the 14 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHREE SWAMI SAMARTH RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • MOSHI
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • RERA no.P52100032762
  • ReraGenie IDRG-MH-23060

Builder

  • NameNITIN TUKARAM PADWAL
  • Entity typeIndividual

Key dates

this monthRegisteredJan 2022First promiseDec 2023Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jan 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed51 files

Current status

21%3 of 14 units booked

Figures as on 16 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE SWAMI SAMARTH RESIDENCYNA6514014

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 35%.

SHREE SWAMI SAMARTH RESIDENCY: 34% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area394 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Sep 2025
LandownerVillageDistrict
LILADHAR MITHARAM FIRKEMumbai CityMumbai City
LALI KASHINATH WARKEPimpri Chinchawad (M Corp.)Pune
AJIT KISHOR PATILPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Permissible FSI783.0
Proposed, not sanctioned375 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPIMPRI CHOWK PIMPRI PUNE - 411017

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRECISION ARCHITECT AND PLANNER
EngineerRAVINDRA ASHOK KARNAVAT
EngineerBONY DCOSTA and CO
Chartered AccountantM S KUMBHAR AND ASSOCIATES
Chartered AccountantPrashantsing M Pardeshi
PartnerRole in project
NITIN TUKARAM PADWAL-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA13092502580Dec 2023 → Mar 2027

Reason as filed by the promoterI, Mr. Nitin Padaval, proprietor of Sheetal Construction, promoter of the registered real estate project “Shree Swamisamartha Residency” (Project Registration No. 952100032762), respectfully submit this application for extension of project registration. Due to unfavourable market conditions and low demand in the project location, we were unable to achieve the expected sales during the earlier period. Consequently, several flats remained unsold, and the process of agreement registrations with the prospective buyers could not be completed within the stipulated project registration period. Now, w

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: form13132022.pdf16 Aug 2025
Form 2File: form13132022.pdf16 Aug 2025
Form 3File: March 22.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: sold unsold 31032022.pdf16 Aug 2025
Form 1File: form 1 Q 1.pdf16 Aug 2025
Form 2File: Form 2 june 2022.pdf16 Aug 2025
Form 3File: June 22 Q1.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold date 30-06-2022.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Stock 30092022.pdf16 Aug 2025
Form 1File: form 1 Q2.pdf16 Aug 2025
Form 3File: SEP 22 Q2.pdf16 Aug 2025
Form 2File: Form 2 September 22.pdf16 Aug 2025
Form 1File: form 1 Q3.pdf16 Aug 2025
Form 2File: Form 2 December 22.pdf16 Aug 2025
Form 3File: December 22 Q3.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Stock 31-12-2022.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Stock 31-03-2023.pdf16 Aug 2025
Form 1File: form 1 Q4.pdf16 Aug 2025
Form 3File: MARCH 23.pdf16 Aug 2025
Form 2File: Form 2 March 23.pdf16 Aug 2025
Form 2File: Form 2 June 23.pdf16 Aug 2025
Form 1File: FORM 1 Q1.pdf16 Aug 2025
Form 3File: June 23 Q1.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Stock 30-06-2023.pdf16 Aug 2025
Form 1File: form 1 Q2.pdf16 Aug 2025
Form 2File: form 2 sep 2023.pdf16 Aug 2025
Form 3File: Sep 23 Q 2.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold Date 30-09-2023.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Stock 31-12-2023.pdf16 Aug 2025
Form 1File: form 1 Q3.pdf16 Aug 2025
Form 2File: Form 2 Dec 23.pdf16 Aug 2025
Form 3File: DEC 23 Q3.pdf16 Aug 2025
Copy of the legal title reportFile: 1 Copy of the legal title report.pdf24 Dec 2021
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate.pdf24 Dec 2021
Layout approvalFile: Plan Pass 01.pdf18 Dec 2021
Building plan approvalFile: Plan Pass 01.pdf18 Dec 2021
Building plan approvalFile: Plan Pass 02.pdf18 Dec 2021
PAN CardFile: Aadhar and PAN.pdf18 Dec 2021
Details of encumbrancesFile: encubrance certificate.pdf18 Dec 2021
Copy of Layout Approval (in case of layout)File: Plan Pass 01.pdf18 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan Pass 01.pdf18 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan Pass 02.pdf18 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf18 Dec 2021
Declaration in FORM BFile: Declaration Developers.pdf18 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 01.pdf18 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02.pdf18 Dec 2021
CERSAI detailsFile: CERSAI_Search_Report_200226090932_For_Asset_Based_Search_18_12_2021_12_28_22_059.pdf18 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf18 Dec 2021
Proforma of Allotment letterFile: Maha RERA A2S Draft.pdf18 Dec 2021
Proforma of Allotment letterFile: allotment letter.pdf18 Dec 2021
OtherFile: RERA Credai.pdf18 Dec 2021

How this compares with Pune

21%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 39 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE SWAMI SAMARTH RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOSHI13,700+ in Pune

Builder: NITIN TUKARAM PADWAL

NITIN TUKARAM PADWAL has 1 registration on MahaRERA, including SHREE SWAMI SAMARTH RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SHREE SWAMI SAMARTH RESIDENCY is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE SWAMI SAMARTH RESIDENCY?

The registered promoter entity is NITIN TUKARAM PADWAL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE SWAMI SAMARTH RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE SWAMI SAMARTH RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE SWAMI SAMARTH RESIDENCY?

The professionals named in the filing: Architect: PRECISION ARCHITECT AND PLANNER; Engineer: RAVINDRA ASHOK KARNAVAT; Engineer: BONY DCOSTA and CO; Chartered Accountant: M S KUMBHAR AND ASSOCIATES; Chartered Accountant: Prashantsing M Pardeshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SWAMI SAMARTH RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SWAMI SAMARTH RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SWAMI SAMARTH RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.