Home / Browse projects / Mumbai Suburban, Maharashtra / SHREE MANIK VISHWA

Registered No litigation declared Others project

SHREE MANIK VISHWA

By ANIL GANGARAM SAWANT

RG-MH-56661 · RERA P51800015282 · Last updated on MahaRERA portal: 15 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 64 months
  • 4 extensions taken
  • Rs 15.00 crore secured on the land, in favour of Aditya Birla Capital
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 64 months from the original
5 of 11Construction stages donefurthest along: External plumbing and external plaster, 90%
19 of 67Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 129 documents Report an error

SHREE MANIK VISHWA is a Others project by ANIL GANGARAM SAWANT in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800015282 on 12 Feb 2018. Possession is promised by 31 Dec 2027. The completion date has moved by 64 months from the original filing. 48 of the 67 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHREE MANIK VISHWA
  • TypeOthers
  • Location
    • L T ROAD
    • DAHISAR WEST
    • Borivali
    • Mumbai Suburban
    • 400068
  • Pincode400068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800015282
  • ReraGenie IDRG-MH-56661

Builder

  • NameANIL GANGARAM SAWANT
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects2 →

Key dates

this monthRegisteredFeb 2018First promiseAug 2022Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Feb 2018
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 28 Aug 2022)
  • Buildings1 building record
  • Documents filed129 files

Current status

72%48 of 67 units booked
72.6%Work done, per cost certificate

Figures as on 15 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE MANIK VISHWANA1818511667

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.

SHREE MANIK VISHWA: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises1%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%

Progress on shared amenities15

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed28

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots28
Closed/Covered28

Land and ownership4

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,281 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Capital
Secured amountRs 15.00 crore
CERSAI search filedYes
Declared on7 Jul 2025
LandownerVillageDistrict
LATA SHAILENDRA PATHAREBorivaliMumbai Suburban
SANKET SHAILENDRA PATHAREBorivaliMumbai Suburban
NIYATI NAIKThane (M Corp.)Thane
CHITRA SURESH PATHAREBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityBMC
Permissible FSI1494.43
Proposed, not sanctioned1,494 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 16 AND 17 PANKAJ PARAG BLDG L T ROAD DAHISAR WEST MUMBAI 400068
Estimated costRs 12.51 cr
Cost incurredRs 9.08 cr
Work done72.56%
BuildingWingEstimatedIncurred
SHREE MANIK VISHWANARs 12.51 crRs 9.08 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMEY P MORE
EngineerK C SHAH
EngineerBAL GOVIND SHUKLA
Chartered AccountantBHARAT KANTILAL SHAH
Chartered AccountantNarendrakumar Badrinarayan Patel
Chartered AccountantHarsh Shah
PartnerRole in project
ANIL GANGARAM SAWANT-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012290Aug 2022 → Aug 2023

Reason as filed by the promoterSHORTAGE OF LABOUR AND MATERIAL DUE TO COVID. PLEASE GRANT EXTENSION AS REQUESTED ABOVE

EXT51800017543Aug 2022 → Jun 2025

Reason as filed by the promoterDUE TO COVID AFTER EFFECTS RESULT IN LABOR PROBLEM AND ALSO RESULTS IN FINACIAL MISMATCH. NOW FINANCIAL PLANNING IS UNDER CONTROL.

EA07072501974Aug 2022 → Jun 2026

Reason as filed by the promoterDue to Further permission from the competent authority is pending

EA16072621763Aug 2022 → Dec 2027

Reason as filed by the promoterDear Sir/Ma’am, We, ANIL GANGARAM SAWANT, hereby declare the following with respect to the project “SHREE MANIK VISHWA” bearing registration number P51800015282 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the Balance, finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Feb 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Feb 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed129

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 129 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Final.pdf15 Jul 2026
Withdrawal Update Form 2File: Form 2 Final.pdf15 Jul 2026
Withdrawal Update Form 3File: Form 3 Final.pdf15 Jul 2026
Form 2A (FY 2021-2022)File: FORM 2A 31032024.pdf15 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A 31032026.pdf15 Jul 2026
Form 2A (FY 2017-2018)File: FORM 2A 31032020.pdf15 Jul 2026
Form 2A (FY 2018-2019)File: FORM 2A 31032020.pdf15 Jul 2026
Form 5 (FY 2017-2018)File: FORM 5 31032018.pdf15 Jul 2026
Form 5 (FY 2018-2019)File: FORM 5 31032019.pdf15 Jul 2026
Form 5 (FY 2019-2020)File: FORM 5 31032020.pdf15 Jul 2026
Form 5 (FY 2020-2021)File: FORM 5 31032021.pdf15 Jul 2026
Form 5 (FY 2021-2022)File: FORM 5 31032022.pdf15 Jul 2026
Form 5 (FY 2022-2023)File: FORM 5 31032023.pdf15 Jul 2026
Form 5 (FY 2023-2024)File: FORM 5 31032024.pdf15 Jul 2026
Form 5 (FY 2025-2026)File: FORM 5 31032026.pdf15 Jul 2026
Withdrawal Update Form 1File: FORM 1 OCT 25 TO DEC 25.pdf18 May 2026
Withdrawal Update Form 2File: FORM 2 OCT 25 To DEC 25.pdf18 May 2026
Withdrawal Update Form 3File: FORM 3 DEC 25.pdf18 May 2026
Withdrawal Update Form 1File: FORM 1 JAN 26 To MAR 26.pdf13 May 2026
Withdrawal Update Form 1File: FORM 1 JAN 26 To MAR 26.pdf13 May 2026
Withdrawal Update Form 2File: FORM 2 JAN 26 To MAR 26.pdf13 May 2026
Withdrawal Update Form 2File: FORM 2 JAN 26 To MAR 26.pdf13 May 2026
Withdrawal Update Form 3File: FORM 3 MAR 26.pdf13 May 2026
Withdrawal Update Form 3File: FORM 3 MAR 26.pdf13 May 2026
Withdrawal Update Form 1File: FORM 1 Q1 25-26.pdf12 Feb 2026
Withdrawal Update Form 2File: FORM 2 30062025.pdf12 Feb 2026
Withdrawal Update Form 3File: Form 3 30062025.pdf12 Feb 2026
Form 5 (FY 2024-2025)File: FORM 5 31032025.pdf16 Sep 2025
Form 2A (FY 2019-2020)File: Form 2A FY 19-20.pdf18 Aug 2025
Form 2A (FY 2020-2021)File: Form 2A FY 20-21.pdf18 Aug 2025
Form 2A (FY 2022-2023)File: Form 2A FY 22-23.pdf18 Aug 2025
Form 2A (FY 2023-2024)File: Form 2A FY 23-24.pdf18 Aug 2025
Form 2A (FY 2024-2025)File: Form 2A FY 24-25.pdf18 Aug 2025
Form 1File: Form 1 Q4 24-25.pdf14 Aug 2025
Form 2File: Form 2 Q4 24-25.pdf14 Aug 2025
Form 3File: Form 3 Q4 24-25.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure sold inventary.pdf14 Aug 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31032025.pdf10 May 2025
Certificates of CA (Form 3)File: FORM 3 NEW 31032025.pdf21 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31032024.pdf13 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30062024.pdf13 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30092024.pdf13 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31122024.pdf13 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 310324.pdf13 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 300624.pdf13 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 300924.pdf13 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 311224.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold Booked Inventory 311224.pdf13 Mar 2025
Proforma of Agreement for saleFile: RERA AGR FOR SALE SHREE MAINK VISHWA Final Draft.pdf13 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST IN ANY OTHER PROJECT.pdf13 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 310324.pdf13 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 300624.pdf13 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 300924.pdf13 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 311224.pdf13 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 31032024.pdf13 Mar 2025
Certificates of CA (Form 3)File: FORM 3 NEW 30092023.pdf8 Mar 2025
Certificates of CA (Form 3)File: FORM 3 NEW 31122023.pdf8 Mar 2025
Certificates of CA (Form 3)File: FORM 3 NEW 31032024.pdf8 Mar 2025
Certificates of CA (Form 3)File: FORM 3 NEW 30062024.pdf8 Mar 2025
Certificates of CA (Form 3)File: FORM 3 NEW 30092024.pdf8 Mar 2025
Certificates of CA (Form 3)File: FORM 3 NEW 31122024 REVISED.pdf8 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A 310320.pdf8 Mar 2025
Other - LegalFile: Reply to Non Submission qtly progess.pdf28 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: FCC 19TH FLOOR.pdf28 Jan 2025
Details of encumbrances concerned to FinanceFile: ENCRUMBRANCES REPORT.pdf20 Sep 2023
Details of encumbrances concerned to LegalFile: ENCRUMBRANCES REPORT.pdf20 Sep 2023
Declaration in FORM BFile: FORM B 20092023.pdf20 Sep 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION FLAT.pdf20 Sep 2023
Declaration in FORM BFile: FORM B.pdf13 Sep 2023
Disclosure of sold/ booked inventoryFile: SMV SOLD UNSOLD.pdf13 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 31 03 2023.pdf13 Sep 2023
Other - TechnicalFile: AFFIDAVIT.pdf13 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf9 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: CHEQUE.pdf9 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.pdf8 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE FORM -2.pdf8 Sep 2023
Disclosure of sold/ booked inventoryFile: SMV SOLD UNSOLD.pdf8 Sep 2023
Certificates of CA (Form 3)File: FORM 3 NEW 31 12 2022.pdf8 Sep 2023
Certificates of CA (Form 3)File: FORM 3 NEW 31 03 2023.pdf8 Sep 2023
Certificates of CA (Form 3)File: FORM 3 NEW 30 06 2023.pdf8 Sep 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SAI VAIBHAV1134 PART 1135 RAMKUVAR THAKUR34CompletedMar 2018Feb 2018

How this compares with Mumbai Suburban

72%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 64 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE MANIK VISHWA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DAHISAR WEST6,700+ in Mumbai Suburban

2 kmSHREE MANIK VISHWACompleted 54Lapsed / revoked 39Other 87Dot size: filed unitsN

Filed coordinates, straight-line distance. 180 registered projects within 2 km.

Builder: ANIL GANGARAM SAWANT

ANIL GANGARAM SAWANT has 2 registrations on MahaRERA, including SAI VAIBHAV and SHREE MANIK VISHWA. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHREE MANIK VISHWA is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE MANIK VISHWA?

The registered promoter entity is ANIL GANGARAM SAWANT, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE MANIK VISHWA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE MANIK VISHWA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE MANIK VISHWA?

The professionals named in the filing: Architect: AMEY P MORE; Engineer: K C SHAH; Engineer: BAL GOVIND SHUKLA; Chartered Accountant: BHARAT KANTILAL SHAH; Chartered Accountant: Narendrakumar Badrinarayan Patel; Chartered Accountant: Harsh Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE MANIK VISHWA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE MANIK VISHWA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE MANIK VISHWA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.