ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / SHREE GANESH COMPLEX

Registered No litigation declared Residential / Group Housing project

SHREE GANESH COMPLEX

By MSD SHIVAY ENTERPRISE LLP

RG-MH-28205 · RERA P99000025438 · Last updated on MahaRERA portal: 18 Apr 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 51 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 51 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 30%
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

SHREE GANESH COMPLEX is a Residential / Group Housing project by MSD SHIVAY ENTERPRISE LLP in Palghar, Maharashtra, registered with MahaRERA as P99000025438 on 30 May 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 51 months from the original filing.

At a glance

Project

  • NameSHREE GANESH COMPLEX
  • TypeResidential / Group Housing
  • Location
    • MYKHOP
    • Palghar
    • 401401
  • Pincode401401
  • RERA no.P99000025438
  • ReraGenie IDRG-MH-28205

Builder

  • NameMSD SHIVAY ENTERPRISE LLP
  • Entity typePartnership
  • PartnersMADHUKAR YASHWANT SHINDE, HEMANT DHARMENDRA CHALKE

Key dates

this monthRegisteredMay 2020First promiseSep 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 May 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 7 Sep 2022)
  • Buildings1 building record
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE GANESH COMPLEXNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 30%.

SHREE GANESH COMPLEX: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure30%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,360 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Chetan GawadThane (M Corp.)Thane

Approvals and building plan

Permissible FSI1018.66
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEAR RAILWAY STATION, KELVE ROAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEmpire Architects
EngineerShah and Associates
Chartered AccountantAMAR JAIN & ASSOCIATES LLP
PartnerRole in project
MSD SHIVAY ENTERPRISE LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000013530Sep 2022 → Sep 2024

Reason as filed by the promoterDue to global pandemic Covid 19 lockdown the work could not be completed within the state time and therefore need further extension till 30-09-2024 to complete the work. thanking you

EXT99000027134Sep 2022 → Dec 2026

Reason as filed by the promoterDear Sir, Due to Post Covid Effect and market slow down we are not able sale our inventory, till date we have manage to sale only 3 units therby causing the slow down of construction works. therefore, your goodeself is requested to provide further time till 31-12-2026. Thanking you, yours faithfully

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-MSD SHIVAY-SIGNED.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2_Mar 2025 duo signed.pdf18 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5_FY 2022 23-SIGNED.pdf18 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_FY 2023 24-SIGNED.pdf18 Apr 2025
Declaration in FORM BFile: FORM B PROMOTER REVISED.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sep 2024 duo signed.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Dec 2024 duo signed.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 _ Mar 2025 duo signed.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2_Sep 2024 duo signed.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2_Dec 2024 duo signed.pdf15 Apr 2025
Other - FinanceFile: FORM 2A_FY 2024-25 SIGNED.pdf15 Apr 2025
Other - FinanceFile: REASON FOR EXTENSION.pdf15 Apr 2025
Other - FinanceFile: STATUS OF WORk CPM PERT.pdf15 Apr 2025
Other - TechnicalFile: FORM 2A_FY 2024-25 SIGNED.pdf15 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A_FY 2022-23 SIGNED.pdf15 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_FY 2023-24 SIGNED.pdf15 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD TILL 31 12 2024 SIGNED.pdf11 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020-21 REVISED_opt.pdf29 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021-22 REVISED_opt.pdf29 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: NON APPLICABILITY OF DETAILS SIGNED.pdf20 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: NON APPLICABILITY OF DETAILS SIGNED.pdf20 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: NON APPLICABILITY OF DETAILS SIGNED.pdf20 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: NON APPLICABILITY OF DETAILS SIGNED.pdf20 Mar 2023
Disclosure of sold/ booked inventoryFile: MSD SOLD UNSOLD.pdf28 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: MSD FORM 5_2021.pdf28 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: MSD FORM 5_2022.pdf28 Jan 2023
Declaration about Commencement CertificateFile: DECLARATION FOR CC SIGNED.pdf21 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020-21.pdf16 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021-22.pdf16 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200255860007_For_Asset_Based_Search_26_12_2022_16_39_16_896.pdf16 Jan 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD OPT.pdf16 Jan 2023
Details of encumbrancesFile: Non Encumbrance Certificate.pdf26 May 2020
Declaration in FORM BFile: Merged File Form B.pdf26 May 2020
Proforma of Allotment letterFile: Allotment Letter in PDF.pdf26 May 2020
Layout approvalFile: Layout Plan.pdf20 Mar 2020
Building plan approvalFile: Building Development Agreement.pdf20 Mar 2020
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf20 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Development Agreement.pdf20 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Building Development Agreement.pdf20 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate_AnnexureA.pdf20 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificates_compressed.pdf13 Mar 2020
PAN CardFile: pan.pdf12 Mar 2020
Copy of the legal title reportFile: title clearance report (1)_compressed.pdf12 Mar 2020
Details of encumbrancesFile: title clearance report (1)_compressed.pdf12 Mar 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect report.pdf12 Mar 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer report_.pdf12 Mar 2020
Proforma of Allotment letterFile: agreement for sale-1_compressed (1).pdf12 Mar 2020
Proforma of Allotment letterFile: agreement for sale -2_compressed (4).pdf12 Mar 2020
Proforma of Allotment letterFile: agreement for sale-4_compressed.pdf12 Mar 2020
Proforma of Allotment letterFile: agreement for sale-3A (1)_compressed.pdf12 Mar 2020
Proforma of Allotment letterFile: agreement for sale-3A (2)_compressed.pdf12 Mar 2020

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 51 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE GANESH COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MYKHOP3,200+ in Palghar

Builder: MSD SHIVAY ENTERPRISE LLP

MSD SHIVAY ENTERPRISE LLP has 1 registration on MahaRERA, including SHREE GANESH COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SHREE GANESH COMPLEX is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE GANESH COMPLEX?

The registered promoter entity is MSD SHIVAY ENTERPRISE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE GANESH COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE GANESH COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE GANESH COMPLEX?

The professionals named in the filing: Architect: Empire Architects; Engineer: Shah and Associates; Chartered Accountant: AMAR JAIN & ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE GANESH COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE GANESH COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE GANESH COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.