Home / Browse projects / Thane, Maharashtra / SHIVESH EMERALD

Registered No litigation declared Residential / Group Housing project

SHIVESH EMERALD

By SHIVESH REALTY PRIVATE LIMITED

RG-MH-06332 · RERA P51700052476 · Last updated on MahaRERA portal: 21 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 4 months from the original
9 of 11Construction stages donefurthest along: Basement (if any), 0%
4 of 22Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

SHIVESH EMERALD is a Residential / Group Housing project by SHIVESH REALTY PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700052476 on 8 Sep 2023. Possession is promised by 30 Nov 2026. The completion date has moved by 4 months from the original filing. 18 of the 22 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHIVESH EMERALD
  • TypeResidential / Group Housing
  • Location
    • SECTOR 7 AIROLI
    • AIROLI NAVI MUMBAI
    • Navi Mumbai (M Corp.)
    • Thane
    • 400708
  • Pincode400708
  • RERA no.P51700052476
  • ReraGenie IDRG-MH-06332

Builder

  • NameSHIVESH REALTY PRIVATE LIMITED
  • Entity typeCompany
  • CINU45209MH2021PTC365374
  • DirectorsDHRUV BACHELAL GUPTA, KHUSHBOO OMPRAKASH GUPTA
  • Other registrations2 more →

Key dates

this monthRegisteredSep 2023First promiseJul 2026Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Sep 2023
  • Promised completion30 Nov 2026
  • Revised completionRevised to 30 Nov 2026 (originally 31 Jul 2026)
  • Buildings1 building record
  • Documents filed65 files

Current status

82%18 of 22 units booked
100.0%Work done, per cost certificate

Figures as on 21 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIVESH EMERALDNA6622022

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

SHIVESH EMERALD: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered17

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area399 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Jul 2025

Approvals and building plan

Sanctioning authorityNavi Mumbai Municipal Corporation
Permissible FSI374.19
Proposed, not sanctioned374 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSECTOR 6 NERUL NAVI MUMBAI
Estimated costRs 2.70 cr
Cost incurredRs 2.70 cr
Work done100.0%
BuildingWingEstimatedIncurred
SHIVESH EMERALDNARs 2.70 crRs 2.70 cr

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJESH RC ARCHITECT Radhakishan Chanda
EngineerBUILT TO LAST SERVICES
EngineerKomal Mahendra Pawar
EngineerSai Kadam
EngineerShriram D Dhangare
Chartered AccountantCA DEVYANI SHEJWAL
Chartered AccountantManish Kumar Ramawati
Chartered AccountantMANISH K RAMAWATI AND COMPANY
Chartered AccountantMs K HEMANT & CO
Chartered AccountantMs. S A A N & CO
PartnerRole in project
SHIVESH REALTY PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P51700052476/WarJul 2026 → Nov 2026

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Nov 2026

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2023-2024)File: FORM 5 Shivesh Emerald 23-24.pdf21 Sep 2026
Form 5 (FY 2024-2025)File: FORM 5 Shivesh Emerald 24-25.pdf21 Sep 2026
Form 5 (FY 2025-2026)File: FORM 5 Shivesh Emerald 25-26.pdf21 Sep 2026
Form 2A (FY 2023-2024)File: Form 2A 23-24 Signed.pdf18 Sep 2026
Form 2A (FY 2024-2025)File: Form 2a 24-25 Signed.pdf18 Sep 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26 Signed.pdf18 Sep 2026
Withdrawal Update Form 1File: Form 1 EMERALD 30-06-2026.pdf26 Aug 2026
Withdrawal Update Form 2File: FORM 2 Emerald 31-12-25.pdf26 Aug 2026
Withdrawal Update Form 3File: FORM 3 Shivesh Emerald 30-06-2026.pdf26 Aug 2026
Withdrawal Update Form 1File: Form 1 EMERALD 31-12-25.pdf21 Apr 2026
Withdrawal Update Form 2File: FORM 2 Emerald 31-12-25.pdf21 Apr 2026
Withdrawal Update Form 3File: FORM 3 Emerald 31-12-25 Sign.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1 EMERALD 31-12-25.pdf18 Jan 2026
Withdrawal Update Form 2File: FORM 2 Emerald 31-12-25.pdf18 Jan 2026
Withdrawal Update Form 3File: FORM 3 Emerald 31-12-25 Sign.pdf18 Jan 2026
Withdrawal Update Form 1File: FORM 1 30-06-25.pdf20 Nov 2025
Withdrawal Update Form 1File: FORM 1 Emerald 30-09-25.pdf20 Nov 2025
Withdrawal Update Form 2File: FORM 2 Emerald 30-06-25.pdf20 Nov 2025
Withdrawal Update Form 2File: FORM 2 Emerald 30-09-25.pdf20 Nov 2025
Withdrawal Update Form 3File: FORM 3 Shivesh Emerald 30-06-25.pdf20 Nov 2025
Withdrawal Update Form 3File: FORM 3 Shivesh Emerald 30-09-25.pdf20 Nov 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf9 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf9 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf9 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - converted.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - converted.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf20 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED (2).pdf20 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED (2).pdf20 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED (2).pdf20 Aug 2024
Building plan approvalFile: 1710494096_NMMCC.pdf5 Apr 2024
Layout approvalFile: 1710494096_NMMCC.pdf5 Apr 2024
Copy of Layout Approval (in case of layout)File: 1710494096_NMMCC.pdf5 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 1710494096_NMMCC.pdf5 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: SHIVENSH REVISE CERT.pdf5 Apr 2024
Other - TechnicalFile: PLAN.pdf31 Jul 2023
Other - LegalFile: Agreement To lease.pdf25 Jul 2023
Layout approvalFile: CC_Drawing.pdf15 Jul 2023
Building plan approvalFile: CC_Drawing.pdf15 Jul 2023
PAN CardFile: PAN.pdf15 Jul 2023
Copy of the legal title reportFile: legal tittle report airoli.pdf15 Jul 2023
Details of encumbrances concerned to FinanceFile: no encumbrances cert.pdf15 Jul 2023
Details of encumbrances concerned to LegalFile: no encumbrances cert.pdf15 Jul 2023
Copy of Layout Approval (in case of layout)File: CC_Drawing.pdf15 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: CC_Drawing.pdf15 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: CC (1)_1 (2 files merged).pdf15 Jul 2023
Declaration about Commencement CertificateFile: declaration about comm cert.pdf15 Jul 2023
Declaration in FORM BFile: Form B.pdf15 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200274481504_For_Asset_Based_Search_15_07_2023_17_03_30_308_1 (2 file15 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf15 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of intrest dhruv (2 files merged).pdf15 Jul 2023
Proforma of Agreement for saleFile: AFS.pdf15 Jul 2023
Proforma of Allotment letterFile: ALLOTMENT DRAFT NEW.pdf15 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Bank AC (2).pdf15 Jul 2023
Deviation Report with respect to Allotment letterFile: deviation allotment (2).pdf15 Jul 2023
Deviation Report with respect to model copy of AgreementFile: deviation-draft sale.pdf15 Jul 2023

How this compares with Thane

82%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 4 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVESH EMERALD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AIROLI NAVI MUMBAI7,600+ in Thane

Builder: SHIVESH REALTY PRIVATE LIMITED

SHIVESH REALTY PRIVATE LIMITED has 3 registrations on MahaRERA, including SHIVESH SAPPHIRE and SHIVESH EMERALD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SHIVESH EMERALD is delayed beyond 30 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVESH EMERALD?

The registered promoter entity is SHIVESH REALTY PRIVATE LIMITED, a company as per the filing. Its CIN U45209MH2021PTC365374 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVESH EMERALD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVESH EMERALD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVESH EMERALD?

The professionals named in the filing: Architect: RAJESH RC ARCHITECT Radhakishan Chanda; Engineer: BUILT TO LAST SERVICES; Engineer: Komal Mahendra Pawar; Engineer: Sai Kadam; Engineer: Shriram D Dhangare; Chartered Accountant: CA DEVYANI SHEJWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVESH EMERALD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVESH EMERALD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVESH EMERALD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.