Home / Browse projects / Gandhinagar, Gujarat / SHIVANSH ARIANNA

Valid until 1 Sep 2027 Mixed Development project

SHIVANSH ARIANNA

By ARIANNA DEVELOPERS

RG-GJ-64387 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12200/290823 · Last updated on GujRERA portal: 8 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Sep 2027Possession promisedno revision filed
8 of 18Construction stages doneacross 2 buildings; furthest along: Internal walls, 47%
89 of 117Units unsoldnot recorded sold or booked
Jump to the 36 documents Report an error

SHIVANSH ARIANNA is a Mixed Development project by ARIANNA DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12200/290823 on 29 Aug 2023. Possession is promised by 1 Sep 2027. 28 of the 117 units on this registration are recorded sold or booked, and 8 of 18 construction stages are filed complete.

At a glance

Project

  • NameSHIVANSH ARIANNA
  • TypeMixed Development
  • Location
    • Shivansh Arianna
    • Near Pramukh Greens Party Plot
    • Sargasan Cross Roads
    • Sargasan
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12200/290823
  • ReraGenie IDRG-GJ-64387

Builder

  • NameARIANNA DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredAug 2023PromisedSep 2027

Key facts

Registration and timeline

  • StatusValid until 1 Sep 2027
  • Registered on29 Aug 2023
  • Promised completion1 Sep 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed36 files

Current status

24%28 of 117 units booked
31.1%Of the estimated cost spent so far

Figures as on 8 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK-A---54963
BLOCK-B---54054

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 8 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 47%.

BLOCK-A52%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor16%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats47%
Sanitary fittings within the flats3%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing3%
BLOCK-B50%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor19%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats27%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing9%

Progress on shared amenities23

As on 8 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,969 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 27.35 cr
Cost incurredRs 8.51 cr
Spent of the estimate31.12%
BuildingWingEstimatedIncurred
BLOCK-ANARs 13.68 crRs 4.26 cr
BLOCK-BNARs 13.68 crRs 4.26 cr

Documents filed36

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA12200/290823 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)8 Oct 2024
Engineer's certificate annexure8 Oct 2024
RERA registration certificate29 Aug 2023
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

24%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SHIVANSH ARIANNA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmSHIVANSH ARIANNAOther 153Dot size: filed unitsN

Filed coordinates, straight-line distance. 153 registered projects within 2 km.

Builder: ARIANNA DEVELOPERS

ARIANNA DEVELOPERS has 1 registration on GujRERA, including SHIVANSH ARIANNA. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SHIVANSH ARIANNA is delayed beyond 1 Sep 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHIVANSH ARIANNA?

The registered promoter entity is ARIANNA DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHIVANSH ARIANNA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in SHIVANSH ARIANNA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVANSH ARIANNA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVANSH ARIANNA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.