RG-MH-52090 · RERA P52100017721 · Last updated on MahaRERA portal: 27 Feb 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 20 months past the filed date
  • Completion date moved by 38 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2025Possession promised20 months past this date
6 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

SHIVAM HEIGHTS is a Residential / Group Housing project by SHIVRUDRA BUILDERS AND DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100017721 on 6 Sep 2018. Possession was promised by 5 Feb 2025 and is now 20 months past that date. The completion date has moved by 38 months from the original filing.

At a glance

Project

  • NameSHIVAM HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • GULVE WASTI
    • BHOSARI PCMC
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411026
  • Pincode411026
  • RERA no.P52100017721
  • ReraGenie IDRG-MH-52090

Builder

  • NameSHIVRUDRA BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersJAGDEVPRASAD NANURAM KUMAVAT, SANJAY BHIMSEN FULVADE, VIJAY SARJERAO DESHMUKH

Key dates

20 months past promisethis monthRegisteredSep 2018First promiseDec 2021Revised toFeb 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Sep 2018
  • Promised completion5 Feb 2025
  • Revised completionRevised to 5 Feb 2025 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIVAM HEIGHTSNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

SHIVAM HEIGHTS: 78% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 27 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area510 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
PARUBAI DNYANOBA RASKAR AND FAMILYPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Permissible FSI565.0
Proposed, not sanctioned510 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKASPATE WASTI, KALEWADI PHATA, KALEWADI, PCMC, PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHEKHAR KOKANE
EngineerSANJAY BHIMSEN FULWADE
Chartered AccountantCA KAILAS NIPUNGE
PartnerRole in project
SHIVRUDRA BUILDERS AND DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011270Dec 2021 → Dec 2022

Reason as filed by the promoterADDITIONAL AREA SANCTION SAUGHT FROM MUNICIPAL AUTHORITIES UNDER REVISED NOTIFICATIONS. NO CUSTOMER BOOKINGS RECEIVED TILL DATE. NO PRIOR APPROVALS FROM CUSTOMERS REQUIRED.

EXT52100013241Dec 2021 → Dec 2023

Reason as filed by the promoterAPPLICATION FOR REVISED SANCTION PLAN AS PER NEW FSI AND TDR RULES IS TO BE FILED AND ADDITIONAL AREA / UNITS IN THE BUILDING ARE PROPOSED

EXT52100019009Dec 2021 → Feb 2025

Reason as filed by the promoterTHE BUILDER HAS COMPLETED CONSTRUCTION OF PROJECT BUILDING IN SPECIFIED TIME FRAME AND HANDED OVER POSSESSION TO THREE CUSTOMERS ( 1 FLAT EACH) AND LAND OWNER AS PER JOINT DEVELOPMENT AGREEMENT. HOWEVER CONCERNED TOWN PLANNING AUTHORITY HAS NOT YET ISSUED FINAL OCCUPANCY CERTIFICATE. WE REQUEST YOU TO KEEP RERA REGISTRATION ALIVE TO FACILITATE SALE OF BALANCE UNITS TO PROPOSED CUSTOMERS AND VERIFICATION FOR BANKERS.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Aug 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Aug 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Aug 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Shivam Height.pdf27 Feb 2024
Certificates of CA (Form 3)File: form 3 shivam height.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 20212022.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 20222023 shivam.pdf27 Feb 2024
Details of encumbrances concerned to FinanceFile: legal encumbrance shivam heights.pdf19 Feb 2024
Details of encumbrances concerned to LegalFile: legal encumbrance shivam heights.pdf19 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest bhushan.pdf19 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest Jagdev.pdf19 Feb 2024
Proforma of Agreement for saleFile: 1 Proforma of Agreement to sale.pdf19 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: shivrudrajul23.pdf19 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Shivam Heights.pdf17 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: form A shivrudra.pdf17 Feb 2024
Declaration in FORM BFile: form B bhushan.pdf16 Feb 2024
Declaration in FORM BFile: form B jagdev kumawat.pdf16 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate shivrudra.pdf16 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf16 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf16 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2 engg certificate shivrudra.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: disclosure of sold inventory shivrudra.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: disclosure of sold inventory shivrudra.pdf16 Feb 2024
CERSAI detailsFile: CERSAI REPORT Asset Based Search.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 20182019.pdf1 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 20192020.pdf1 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 20202021.pdf1 Feb 2022
Declaration about Commencement CertificateFile: Declaration about commencement certificate.pdf31 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2A.pdf31 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A.pdf31 Jan 2022
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf31 Jan 2022
Layout approvalFile: 02.pdf20 Feb 2019
Copy of Layout Approval (in case of layout)File: 02.pdf20 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Revised Form 1 Architect.pdf20 Feb 2019
OtherFile: Plinth Checking Report.pdf20 Feb 2019
Details of encumbrancesFile: Dlc.pdf3 Sep 2018
Declaration in FORM BFile: Stamp Paper.pdf3 Sep 2018
Building plan approvalFile: sanction plan.pdf10 Aug 2018
Layout approvalFile: layout.pdf10 Aug 2018
PAN CardFile: Firm PAN Card.pdf10 Aug 2018
Copy of the legal title reportFile: Search and Title Report.pdf10 Aug 2018
Copy of Layout Approval (in case of layout)File: layout.pdf10 Aug 2018
Building Plan Approval (IOD)File: sanction plan.pdf10 Aug 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf10 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect.pdf10 Aug 2018
Certificates of CA (Form 3)File: Form 3 CA.pdf10 Aug 2018
Proforma of Allotment letterFile: Shivrudra Sample Agreement.pdf10 Aug 2018
OtherFile: Confirmation Deed.pdf10 Aug 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 38 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVAM HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHOSARI PCMC13,700+ in Pune

Builder: SHIVRUDRA BUILDERS AND DEVELOPERS

SHIVRUDRA BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including SHIVAM HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SHIVAM HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHIVAM HEIGHTS is delayed beyond 5 Feb 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVAM HEIGHTS?

The registered promoter entity is SHIVRUDRA BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVAM HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVAM HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVAM HEIGHTS?

The professionals named in the filing: Architect: SHEKHAR KOKANE; Engineer: SANJAY BHIMSEN FULWADE; Chartered Accountant: CA KAILAS NIPUNGE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVAM HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVAM HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVAM HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.