Home / Browse projects / Sangli, Maharashtra / SHIVAM CAMPUS
SHIVAM CAMPUS
RG-MH-16989 · RERA P53100027502 · Last updated on MahaRERA portal: 18 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHIVAM CAMPUS is a Others project by SHIVAMDEVELOPERS in Sangli, Maharashtra, registered with MahaRERA as P53100027502 on 14 Dec 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 24 months from the original filing.
At a glance
Project
- NameSHIVAM CAMPUS
- TypeOthers
- Location
- DHAMANI ROAD
- NEAR MAHESHWARI GARDEN SFURTI CHOUCK
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- Sangli
- 416415
- Pincode416415
- RERA no.P53100027502
- ReraGenie IDRG-MH-16989
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Dec 2020
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2024)
- Buildings2 building records
- Documents filed102 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHIVAM CAMPUS BUILDING A | NA | 7 | 0 | 0 | 0 | 0 |
| SHIVAM CAMPUS BUILDING B | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 18 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.
SHIVAM CAMPUS BUILDING A83%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
SHIVAM CAMPUS BUILDING B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 75% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 75% |
| Storm Water Drains | Yes | 75% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 75% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed67
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| SHIVAM CAMPUS BUILDING A | 21 | 21 | 42 |
| SHIVAM CAMPUS BUILDING B | 25 | 0 | 25 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AR VIVEK DESHPANDE |
| Engineer | Mr Pritam Dattatray Shinde |
| Chartered Accountant | Mr Shriniwas N Bhosale |
| Partner | Role in project |
|---|---|
| SHIVAMDEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promotershivam campus wing B IS COMPLETED. but shivam campus wing A takan revised sanction also now booking is slow so required extension for wing A
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Dec 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 1 Nov 2023
Documents filed102
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Form 1.pdf | 18 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 18 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Wing A Sold Inventory.pdf | 18 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold inventory B wing.pdf | 18 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Architecture form-2A.pdf | 18 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Ca Certificate Form- 5.pdf | 18 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: campus architecture certificate.pdf | 3 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: campus CA Certificate.pdf | 3 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: campus engineer certificate.pdf | 3 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: campus disclosure of sold unit (1).pdf | 3 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: campus Form 2A.pdf | 3 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 6 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 6 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 6 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD A AND B WING.pdf | 6 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31 03 2024.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 31 03 2024.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31 03 2024.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2 A.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23 TO 24.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD A B WING.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM -2A.pdf | 29 Mar 2024 |
| Declaration in FORM BFile: FORM B.pdf | 11 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 11 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 11 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2 A.pdf | 11 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD WING A SHIVAM CAMPUS 31122023.pdf | 11 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD WING B SHIVAM CAMPUS 31122023.pdf | 11 Mar 2024 |
| CERSAI detailsFile: CERSAI UNDERTAKING.pdf | 11 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 11 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORG SACHIN SANKPAL.pdf | 11 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORG D B SHINDE.pdf | 11 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A SEPARATE BANK AC.pdf | 11 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30062023.pdf | 8 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 06102023.pdf | 8 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 8 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - 30062023.pdf | 8 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - 30092023.pdf | 8 Jan 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLITION CERTIFICATE.pdf | 1 Nov 2023 |
| Building plan approvalFile: DRG NEW MD1.pdf | 14 Oct 2023 |
| Building plan approvalFile: DRG NEW MD2.pdf | 14 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: DRG NEW MD1.pdf | 14 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: DRG NEW MD2.pdf | 14 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: BANDHKAM PARVANA REVISED.pdf | 14 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold 01042021.pdf | 14 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold.pdf | 14 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: discolsure of sold - 05042021.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold -05072021.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: discolsure of sold - 10102021.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold - 09032021.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold - 04042022.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold- 02072022.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: discolsure of sold - 04102023.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold - 07012023.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold - 06042023.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: discolsure of sold - 04072023.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold - 30092023.pdf | 4 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate - 05042021.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate - 07072021.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate - 04102021.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate - 05012022.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 07042022.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 05072022.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate - 03102022.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 6012023.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 04042023.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE - 3062021.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERIFICATE - 3092021.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE - 31122021.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE - 3132022.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE - 3062022.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CRTIFICAE - 3092022.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE - 30122022.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE - 3132023.pdf | 30 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE - 3062023.pdf | 30 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATERS 1012021 31032021.pdf | 30 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE - 142021 TO 3062021.pdf | 30 Sep 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| VARAD VANDAN | PUNE BYPASS ROAD SANGLI | 6 | Completed | Dec 2017 | Mar 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 102 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SHIVAM CAMPUS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR MAHESHWARI GARDEN SFURTI CHOUCK790+ in Sangli
SHIV SAI VANDANA
S P BUILDER
Purva Heights
Kotibhaskar Builders
SHRI KRUPA ICON
TATYASAHEB SAMBHAJI KHOT
VAJE BUSINESS SQAURE
V D VAJE DEVELOPERS
KALESHWAR PRIDE
PRADEEP SHRIDHAR PHADKE
SAICHARAN HEIGHTS
ASHTANG DEVELOPERS
See every Sangli project, with the district possession charts
Builder: SHIVAMDEVELOPERS
SHIVAMDEVELOPERS has 2 registrations on MahaRERA, including SHIVAM IMPERIA and SHIVAM CAMPUS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What does it mean that SHIVAM CAMPUS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHIVAM CAMPUS is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHIVAM CAMPUS?
The registered promoter entity is SHIVAMDEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHIVAM CAMPUS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHIVAM CAMPUS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHIVAM CAMPUS?
The professionals named in the filing: Architect: AR VIVEK DESHPANDE; Engineer: Mr Pritam Dattatray Shinde; Chartered Accountant: Mr Shriniwas N Bhosale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHIVAM CAMPUS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback