Home / Browse projects / Sangli, Maharashtra / SHIV SAI VANDANA

Registered No litigation declared Others project

SHIV SAI VANDANA

By S P BUILDER

RG-MH-90278 · RERA P53100076935 · Last updated on MahaRERA portal: 6 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedno revision filed
2 of 11Construction stages donefurthest along: Podiums (if any), 50%
42 of 42Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

SHIV SAI VANDANA is a Others project by S P BUILDER in Sangli, Maharashtra, registered with MahaRERA as P53100076935 on 9 Jul 2024. Possession is promised by 31 Oct 2027. 0 of the 42 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHIV SAI VANDANA
  • TypeOthers
  • Location
    • GOVERNMENT COLONY
    • HASNI ASHRAM
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416415
  • Pincode416415
  • RERA no.P53100076935
  • ReraGenie IDRG-MH-90278

Builder

  • NameS P BUILDER
  • Entity typePartnership
  • PartnerSwapnil Sunil Pirale
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJul 2024PromisedOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Jul 2024
  • Promised completion31 Oct 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed37 files

Current status

0%0 of 42 units booked
16.4%Work done, per cost certificate

Figures as on 6 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIV SAI VANDANANA12035742

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 50%.

SHIV SAI VANDANA: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)50%
Plinth45%
Stilt Floor45%
Slabs of Super Structure45%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes35%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed34

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots34
Closed/Covered28
Open Space6

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area604 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 May 2025
LandownerVillageDistrict
VANDANA NAGNATH MOHITEBaramati RuralPune
SURENDRA DEVSHI SHAHSangli Miraj Kupwad (M Corp.)Sangli

Approvals and building plan

Sanctioning authoritySMKC
Permissible FSI1715.28
Proposed, not sanctioned1,715 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSURYA COMPLEX, KARAD TASGAON ROAD PALUS DIST.SANGLI
Estimated costRs 7.85 cr
Cost incurredRs 1.29 cr
Work done16.43%
BuildingWingEstimatedIncurred
SHIV SAI VANDANANARs 6.60 crRs 1.29 cr
-NARs 1.25 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMIT MOHAN PANDIT
EngineerCHETAN V MANE
EngineerSAGAR S SHETHE
Chartered AccountantRCB AND ASSOCIATES RAJESH BHATE
Chartered AccountantSHREYAS SUHAS SHAH
PartnerRole in project
S P BUILDER-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2027

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Up to Dec 2025.pdf6 Jul 2026
Withdrawal Update Form 1File: Form 1 Up to Dec 2025.pdf6 Jul 2026
Withdrawal Update Form 2File: Form 2 up to 31 dec 2025.pdf6 Jul 2026
Withdrawal Update Form 2File: Form 2 up to 31 Mar 2026.pdf6 Jul 2026
Withdrawal Update Form 3File: Form 3 up to 31 dec 2025.pdf6 Jul 2026
Withdrawal Update Form 3File: Form 3 up to 31 dec 2025.pdf6 Jul 2026
Withdrawal Update Form 1File: Form 1 up to Jun 25.pdf12 Jun 2026
Withdrawal Update Form 2File: Form 2 up to Jun 2025.pdf12 Jun 2026
Withdrawal Update Form 3File: FORM-3 UP TO 30 june 2025.pdf12 Jun 2026
Withdrawal Update Form 1File: Form 1 Up To 30 Sep.pdf9 Dec 2025
Withdrawal Update Form 2File: Form 2 Up to Sep 2025.pdf9 Dec 2025
Withdrawal Update Form 3File: FORM 3 UP TO 30 sep 2025.pdf9 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: from 1.pdf6 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf6 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: BANK DECLARATION.pdf2 Jul 2024
Proforma of Allotment letterFile: Allotment Letter.pdf29 Jun 2024
Proforma of Agreement for saleFile: Updated Agreement to Sale (1).pdf29 Jun 2024
Building plan approvalFile: SMKC CONFIRMATION MAIL.pdf22 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: SMKC CONFIRMATION MAIL.pdf22 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf22 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Allotment Deviatioon.pdf22 Jun 2024
Layout approvalFile: Adobe Scan Apr 23, 2024 (14).pdf24 Apr 2024
Copy of the legal title reportFile: SEARCHR E.pdf24 Apr 2024
Details of encumbrances concerned to FinanceFile: finance encumbrances.pdf24 Apr 2024
Details of encumbrances concerned to FinanceFile: encumbranc legal.pdf24 Apr 2024
Details of encumbrances concerned to LegalFile: finance encumbrances.pdf24 Apr 2024
Details of encumbrances concerned to LegalFile: encumbranc legal.pdf24 Apr 2024
Copy of Layout Approval (in case of layout)File: Adobe Scan Apr 23, 2024 (14).pdf24 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Permission.pdf24 Apr 2024
Declaration about Commencement CertificateFile: format d.pdf24 Apr 2024
CERSAI detailsFile: cersai.pdf24 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ilovepdf_merged.pdf24 Apr 2024
Deviation Report with respect to Allotment letterFile: allotment letter deviation.pdf24 Apr 2024
Building plan approvalFile: scan0682.pdf14 Oct 2023
PAN CardFile: 1 PAN Card.pdf14 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: scan0682.pdf14 Oct 2023
Declaration in FORM BFile: form b frrm.pdf14 Oct 2023

How this compares with Sangli

0%of this project is bookeddistrict median 16%
11%of Sangli projects moved their completion datethis one has not
29%of Sangli registrations have lapsed or been cancelledthis one is on the register

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep SHIV SAI VANDANA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HASNI ASHRAM790+ in Sangli

Builder: S P BUILDER

S P BUILDER has 2 registrations on MahaRERA, including Baraskar Heights and SHIV SAI VANDANA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if SHIV SAI VANDANA is delayed beyond 31 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIV SAI VANDANA?

The registered promoter entity is S P BUILDER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIV SAI VANDANA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIV SAI VANDANA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIV SAI VANDANA?

The professionals named in the filing: Architect: AMIT MOHAN PANDIT; Engineer: CHETAN V MANE; Engineer: SAGAR S SHETHE; Chartered Accountant: RCB AND ASSOCIATES RAJESH BHATE; Chartered Accountant: SHREYAS SUHAS SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIV SAI VANDANA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIV SAI VANDANA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIV SAI VANDANA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.