Home / Browse projects / Nashik, Maharashtra / shivalayheights

Registered No litigation declared Residential / Group Housing project

shivalayheights

By SHIVALAY CONSTRUCTION

RG-MH-15075 · RERA P51600034487 · Last updated on MahaRERA portal: 14 Feb 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
8 of 11Construction stages donefurthest along: Installation of Lifts, 90%
16 of 60Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

shivalayheights is a Residential / Group Housing project by SHIVALAY CONSTRUCTION in Nashik, Maharashtra, registered with MahaRERA as P51600034487 on 11 Apr 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 44 of the 60 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • Nameshivalayheights
  • TypeResidential / Group Housing
  • Location
    • makhmalabad area
    • behind sharadchandra pawar market yard
    • Nashik (M Corp.)
    • Nashik
    • 422001
  • Pincode422001
  • RERA no.P51600034487
  • ReraGenie IDRG-MH-15075

Builder

  • NameSHIVALAY CONSTRUCTION
  • Entity typePartnership
  • PartnersVAISHALI SANJAY DAPTARE, SANJAY PANDURANG DAPTARE, AKASH SHYAM KAPADANE, SUNITA SHYAM KAPADANE, SONAM AKASH KAPADANE, KIRAN LAXMAN TALREJA, RUSHAB LAXMAN TALREJA, DIVYA LAXMAN TALREJA

Key dates

this monthRegisteredApr 2022First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Apr 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed27 files

Current status

73%44 of 60 units booked
91.5%Work done, per cost certificate

Figures as on 14 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shivalay HeightsNA9956460

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

Shivalay Heights: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 14 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered56
Open Space4

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,100 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Jan 2026

Approvals and building plan

Sanctioning authorityNASHIK MUNCIPAL CORPORATION
Permissible FSI4286.0
Proposed, not sanctioned4,286 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchdwarka nshik
Estimated costRs 9.64 cr
Cost incurredRs 8.82 cr
Work done91.53%
BuildingWingEstimatedIncurred
Shivalay HeightsNARs 9.64 crRs 8.82 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architecthemant pawar
EngineerAditya Naik
Chartered AccountantRodi Dabir and company
Chartered AccountantSWATI KOLTE
PartnerRole in project
SHIVALAY CONSTRUCTION-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600027949Dec 2024 → Dec 2025

Reason as filed by the promoterFUND ISSUE.

EA27012619592Dec 2024 → Dec 2026

Reason as filed by the promoterTECHNICAL ISSUE

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: FORM 5 2425.pdf14 Feb 2026
Withdrawal Update Form 1File: JUNE 25 ARCH CERT.pdf27 Jan 2026
Withdrawal Update Form 1File: JUNE 25 ARCH CERT.pdf27 Jan 2026
Withdrawal Update Form 1File: JUNE 25 ARCH CERT.pdf27 Jan 2026
Withdrawal Update Form 1File: JUNE 25 ARCH CERT.pdf27 Jan 2026
Withdrawal Update Form 2File: JUNE 25 ENG.pdf27 Jan 2026
Withdrawal Update Form 2File: JUNE 25 ENG.pdf27 Jan 2026
Withdrawal Update Form 2File: JUNE 25 ENG.pdf27 Jan 2026
Withdrawal Update Form 2File: JUNE 25 ENG.pdf27 Jan 2026
Withdrawal Update Form 3File: Registration Application Form3 (9).pdf27 Jan 2026
Withdrawal Update Form 3File: SEPT 25 CA.pdf27 Jan 2026
Withdrawal Update Form 3File: SEPT 25 CA.pdf27 Jan 2026
Withdrawal Update Form 3File: SEPT 25 CA.pdf27 Jan 2026
Declaration about Commencement CertificateFile: Declaration about Commencement certificate.pdf1 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200234164213_For_Asset_Based_Search_01_04_2022_14_52_36_595.pdf1 Apr 2022
Copy of the legal title reportFile: Format A Legal title report.pdf29 Mar 2022
Copy of the legal title reportFile: Title search Report.pdf29 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate.pdf29 Mar 2022
Proforma of Allotment letterFile: Draft.pdf29 Mar 2022
Layout approvalFile: Shivalay layout.pdf14 Mar 2022
Details of encumbrancesFile: Non Encumbrances Certificate.pdf14 Mar 2022
Copy of Layout Approval (in case of layout)File: Shivalay layout.pdf14 Mar 2022
Declaration in FORM BFile: Affidavit cum Declaration_compressed.pdf14 Mar 2022
Building plan approvalFile: Building Plan.pdf12 Mar 2022
PAN CardFile: Shivalay pan card.pdf12 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf12 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf12 Mar 2022

How this compares with Nashik

73%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 24 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep shivalayheights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near behind sharadchandra pawar market yard4,100+ in Nashik

Builder: SHIVALAY CONSTRUCTION

SHIVALAY CONSTRUCTION has 1 registration on MahaRERA, including shivalayheights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if shivalayheights is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of shivalayheights?

The registered promoter entity is SHIVALAY CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in shivalayheights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for shivalayheights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at shivalayheights?

The professionals named in the filing: Architect: hemant pawar; Engineer: Aditya Naik; Chartered Accountant: Rodi Dabir and company; Chartered Accountant: SWATI KOLTE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in shivalayheights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About shivalayheights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save shivalayheights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.