Home / Browse projects / Gandhinagar, Gujarat / SHIVALAY HARITAGE

Valid until 31 Dec 2026 Residential/Group Housing project

SHIVALAY HARITAGE

By SHREE SAI CORPORATION

RG-GJ-11024 · RERA PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11635/210423 · Last updated on GujRERA portal: 5 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2026Possession promisedno revision filed
49 of 54Construction stages doneacross 6 buildings; furthest along: External plumbing and external plaster, 95%
21 of 57Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SHIVALAY HARITAGE is a Residential/Group Housing project by SHREE SAI CORPORATION in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11635/210423 on 21 Apr 2023. Possession is promised by 31 Dec 2026. 36 of the 57 units on this registration are recorded sold or booked, and 49 of 54 construction stages are filed complete.

At a glance

Project

  • NameSHIVALAY HARITAGE
  • TypeResidential/Group Housing
  • Location
    • SHIVALAY HARITAGE
    • FP NO 149
    • B/H PANCHVATI FARM
    • BESIDE SHIVALAY WHITE HOUSE
    • DAHEGAM RING ROAD
    • DAHEGAM
    • GANDHINAGAR
    • Dehgam
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11635/210423
  • ReraGenie IDRG-GJ-11024

Builder

  • NameSHREE SAI CORPORATION
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on21 Apr 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings6 building records
  • Documents filed38 files

Current status

63%36 of 57 units booked
59.8%Of the estimated cost spent so far

Figures as on 5 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---202
B C---12012
A E---24024
D---16016
C---101
E---202

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 5 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

49 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

A98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing85%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A E99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing72%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C97%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing74%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E98%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing83%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities23

As on 5 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable
Compound wallYes100%
Plinth protectionYes100%
Water tankYes100%
Other requirementsYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,042 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 12.25 cr
Cost incurredRs 7.33 cr
Spent of the estimate59.84%
BuildingWingEstimatedIncurred
A ENARs 4.76 crRs 3.36 cr
DNARs 3.48 crRs 1.07 cr
B CNARs 2.97 crRs 2.11 cr
ANARs 39.39 lakhRs 29.92 lakh
ENARs 39.39 lakhRs 28.62 lakh
CNARs 24.67 lakhRs 20.25 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPANKTI B DHOLAKIA
EngineerROHIT B PRAJAPATI

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/DEHGAM/AUDA/RAA11635/210423 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)5 Oct 2024
Engineer's certificate annexure5 Oct 2024
RERA registration certificate21 Apr 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

63%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SHIVALAY HARITAGE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmSHIVALAY HARITAGEOther 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: SHREE SAI CORPORATION

SHREE SAI CORPORATION has 1 registration on GujRERA, including SHIVALAY HARITAGE. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SHIVALAY HARITAGE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHIVALAY HARITAGE?

The registered promoter entity is SHREE SAI CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHIVALAY HARITAGE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHIVALAY HARITAGE?

The professionals named in the filing: Architect: PANKTI B DHOLAKIA; Engineer: ROHIT B PRAJAPATI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVALAY HARITAGE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVALAY HARITAGE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVALAY HARITAGE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.