Home / Browse projects / Aurangabad, Maharashtra / SHIV PARK-2

Registered No litigation declared Residential / Group Housing project

SHIV PARK-2

By BALAJI INFRA

RG-MH-29982 · RERA P51500051760 · Last updated on MahaRERA portal: 16 Jan 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 15 other registrations.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
63 of 99Construction stages doneacross 9 buildings; furthest along: Internal walls, 70%
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

SHIV PARK-2 is a Residential / Group Housing project by BALAJI INFRA in Aurangabad, Maharashtra, registered with MahaRERA as P51500051760 on 27 Jun 2023. Possession is promised by 31 Dec 2028.

At a glance

Project

  • NameSHIV PARK-2
  • TypeResidential / Group Housing
  • Location
    • PALSHI
    • PALSHI PISADEVI
    • Aurangabad
    • 431008
  • Pincode431008
  • RERA no.P51500051760
  • ReraGenie IDRG-MH-29982

Builder

  • NameBALAJI INFRA
  • Entity typePartnership
  • PartnerPANDHARINATH SONAJI GADEKAR
  • Other registrations15 more →
  • Completed6 of 16
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredJun 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jun 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings9 building records
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA10000
A2NA10000
A3NA10000
A4NA10000
A5NA10000
A6NA10000
B1NA20000
B2NA20000
B3NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building9

As on 16 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

63 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Internal walls, at 70%.

A191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A231%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor40%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A352%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A452%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A552%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A652%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes20%
Street LightingYes20%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed66

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots66
Open Space66
BuildingOpen SpaceTotal
A166
A266
A366
A466
A566
A666
B11010
B21010
B31010

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,000 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI8564.62
Proposed, not sanctioned3,065 sq m
Buildings approved9
Buildings sanctioned9

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHUDCO AURANGABAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParmeshwar Govind Gawali
EngineerAbhay Patil
Chartered AccountantBangad Parjane and Co
PartnerRole in project
BALAJI INFRA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 13-07-24.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 12-10-24.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 02-01-25.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self-Declaration 13-07-24.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self-Declaration 12-10-24.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self-Declaration 02-01-25.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 13-07-24.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 12-10-24.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 02-01-25.pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold 30-06-24.pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold 30-09-24.pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold 31-12-24.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Balaji Infra Form 1 16 10 2023.pdf24 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Balaji Infra Form 1 06 01 2024.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Balaji Infra Form 2 16 10 2023.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Balaji Infra Form 2 06 01 2024.pdf24 Jan 2024
Disclosure of sold/ booked inventoryFile: Balaji Infra Sold Unsold Detail 30 09 2023.pdf24 Jan 2024
Disclosure of sold/ booked inventoryFile: Balaji Infra Sold Unsold Detail 31 12 2023.pdf24 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Balaji Infra Form 3 18 10 2023.pdf24 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Balaji Infra Form 3 06 01 2024.pdf24 Jan 2024
Details of encumbrances concerned to FinanceFile: No ENC FIN.pdf23 Jun 2023
Details of encumbrances concerned to LegalFile: No ENC FIN.pdf23 Jun 2023
CERSAI detailsFile: CERSAI Declaration.pdf23 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Balaji Infra.pdf7 Jun 2023
Layout approvalFile: SHIV PARK-2 PLANS-1.pdf3 Jun 2023
Building plan approvalFile: SHIV PARK-2 PLANS-2.pdf3 Jun 2023
Building plan approvalFile: SHIV PARK-2 PLANS-3.pdf3 Jun 2023
Building plan approvalFile: SHIV PARK-2 PLANS-5.pdf3 Jun 2023
Building plan approvalFile: SHIV PARK-2 PLANS-6.pdf3 Jun 2023
Building plan approvalFile: SHIV PARK-2 PLANS-4.pdf3 Jun 2023
PAN CardFile: FIRM PAN.pdf3 Jun 2023
Copy of the legal title reportFile: Search Report.pdf3 Jun 2023
Details of encumbrances concerned to FinanceFile: No ENC Legal.pdf3 Jun 2023
Details of encumbrances concerned to LegalFile: No ENC Legal.pdf3 Jun 2023
Copy of Layout Approval (in case of layout)File: SHIV PARK-2 PLANS-1.pdf3 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: SHIV PARK-2 PLANS-2.pdf3 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: SHIV PARK-2 PLANS-3.pdf3 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: SHIV PARK-2 PLANS-5.pdf3 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: SHIV PARK-2 PLANS-6.pdf3 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: SHIV PARK-2 PLANS-4.pdf3 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: Cert_B_241515_402Nz9ZASign.pdf3 Jun 2023
Declaration about Commencement CertificateFile: Format D.pdf3 Jun 2023
Declaration in FORM BFile: Form B.pdf3 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Kapre Sir.pdf3 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Gadekar Sir.pdf3 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Jadhav Sir.pdf3 Jun 2023
Proforma of Agreement for saleFile: 12 ATS Draft RERA.pdf3 Jun 2023
Proforma of Allotment letterFile: Modal Form Of Allotment Letter.pdf3 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf3 Jun 2023
Deviation Report with respect to Allotment letterFile: DEVI Allotment Letter.pdf3 Jun 2023
Deviation Report with respect to model copy of AgreementFile: DEVI Agreement to Sale.pdf3 Jun 2023

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep SHIV PARK-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALSHI PISADEVI1,400+ in Aurangabad

Builder: BALAJI INFRA

BALAJI INFRA has 16 registrations on MahaRERA, including FLORENCE and BALAJI COMPLEX - PLOT NO 11, 12, 13. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if SHIV PARK-2 is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIV PARK-2?

The registered promoter entity is BALAJI INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIV PARK-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIV PARK-2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIV PARK-2?

The professionals named in the filing: Architect: Parmeshwar Govind Gawali; Engineer: Abhay Patil; Chartered Accountant: Bangad Parjane and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIV PARK-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIV PARK-2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIV PARK-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.