Home / Browse projects / Sangli, Maharashtra / Shiv City Center

Completed No litigation declared Others project

Shiv City Center

By Shiv City Center Joint Venture

RG-MH-26880 · RERA P53100017288 · Last updated on MahaRERA portal: 3 Apr 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 27 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Mar 2023Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

Shiv City Center is a Others project by Shiv City Center Joint Venture in Sangli, Maharashtra, registered with MahaRERA as P53100017288 on 27 Jul 2018. The registration is recorded completed; possession was promised by 15 Mar 2023. The completion date has moved by 27 months from the original filing.

At a glance

Project

  • NameShiv City Center
  • TypeOthers
  • Location
    • Sangli-Miraj Road
    • Wanlesswadi
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416415
  • Pincode416415
  • RERA no.P53100017288
  • ReraGenie IDRG-MH-26880

Builder

  • NameShiv City Center Joint Venture
  • Entity typePartnership
  • PartnersSonia Rajesh Gangwani, Rajesh Lakhmichand Gangwani

Key dates

this monthRegisteredJul 2018First promiseDec 2020Revised toMar 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2018
  • Promised completion15 Mar 2023
  • Revised completionRevised to 15 Mar 2023 (originally 30 Dec 2020)
  • Buildings1 building record
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
City CenterNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

City Center: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 3 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
Common ParkingYes0%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area935 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2344.68
Proposed, not sanctioned2,345 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSangli

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Vivekanand Murlidhar Deshpande
PartnerRole in project
Shiv City Center Joint Venture-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53100008658Dec 2020 → Dec 2021

Reason as filed by the promoterBecause Of ,Flood and ,COVID 19 And Increses Sanction FSI

EXT53100012240Dec 2020 → Aug 2022

Reason as filed by the promoterchange in sanction plan obtained from Local Authority and construction according to revised plan .

EXT53100012497Dec 2020 → Mar 2023

Reason as filed by the promoterBuilt- up area increases as TDR got for the Project so that FSI available increased . Therefore for the completion of construction extension need.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Mar 2023

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form-4.pdf3 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COmplition.pdf25 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion 2022.pdf25 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: city center Completion2023.pdf25 Mar 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form-4.pdf25 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: Comencement 22 23.pdf2 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Quality Assurance 2019.pdf18 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Quality Assurance 21.pdf18 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Quality Assurance 2019.pdf27 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Quality Assurance 21.pdf27 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society.pdf22 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual AUfdit 2021-22.pdf8 Dec 2022
Building plan approvalFile: CIty Center Plan 1.pdf30 Nov 2022
Building plan approvalFile: City Center Plan 2.pdf30 Nov 2022
Building Plan Approval (IOD)File: CIty Center Plan 1.pdf30 Nov 2022
Building Plan Approval (IOD)File: City Center Plan 2.pdf30 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht Cert 2022.pdf30 Nov 2022
Certificates of CA (Form 3)File: CA Certificate 2022.pdf30 Nov 2022
Certificates of CA (Form 3)File: ca cERTIFICATE cITY CENTER 2022_11zon.pdf12 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate City center 2022_11zon.pdf4 May 2022
Certificates of CA (Form 3)File: ca cERTIFICATE cITY CENTER 2022_11zon.pdf4 May 2022
Building plan approvalFile: Plan 2021 1_compressed.pdf3 May 2022
Building plan approvalFile: Plan 2021 2_compressed (1).pdf3 May 2022
Building Plan Approval (IOD)File: Plan 2021 1_compressed.pdf3 May 2022
Building Plan Approval (IOD)File: Plan 2021 2_compressed (1).pdf3 May 2022
Commencement Certificates / NA Order for plotted developmentFile: commencement.pdf3 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18 19.pdf23 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 19 20.pdf23 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 20 21.pdf23 Nov 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold29.pdf9 Nov 2021
Declaration about Commencement CertificateFile: Decalration of cc.pdf2 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality certificate.pdf2 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 2021.pdf1 Nov 2021
Disclosure of sold/ booked inventoryFile: Sold.pdf1 Nov 2021
Disclosure of sold/ booked inventoryFile: Sold.pdf1 Nov 2021
Certificates of CA (Form 3)File: Ca cert 21.pdf1 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 19 20.pdf1 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 20 21.pdf1 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20 21.pdf1 Nov 2021
Certificates of CA (Form 3)File: City Center_compressed.pdf25 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCT CITY CENTER.pdf11 Dec 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CA CITY CENTER.pdf11 Dec 2020
Certificates of CA (Form 3)File: NEW CA CERT CITY CENTER-compressed.pdf11 Dec 2020
Building plan approvalFile: CITY CENTER 3 TO 6.pdf10 Dec 2020
Building Plan Approval (IOD)File: CITY CENTER 3 TO 6.pdf10 Dec 2020
OtherFile: rajesh ind.PDF25 Sep 2019
Layout approvalFile: Layout City.PDF4 Jul 2018
Copy of Layout Approval (in case of layout)File: Layout City.PDF4 Jul 2018
PAN CardFile: pan.PDF28 Jun 2018
Copy of the legal title reportFile: fin (1).pdf28 Jun 2018
Details of encumbrancesFile: sakale.PDF28 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: Build per.pdf28 Jun 2018
Declaration in FORM BFile: Form B.pdf28 Jun 2018
Certificates of CA (Form 3)File: Final (1).pdf28 Jun 2018
Proforma of Allotment letterFile: Rera Agree city c (1).pdf28 Jun 2018
Building plan approvalFile: Final Plan.pdf28 Dec 2017
Building Plan Approval (IOD)File: Final Plan.pdf28 Dec 2017

How this compares with Sangli

11%of Sangli projects moved their completion datethis one moved by 27 months
29%of Sangli registrations have lapsed or been cancelledthis one is completed

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep Shiv City Center on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wanlesswadi790+ in Sangli

Builder: Shiv City Center Joint Venture

Shiv City Center Joint Venture has 1 registration on MahaRERA, including Shiv City Center. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if Shiv City Center is delayed beyond 15 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shiv City Center?

The registered promoter entity is Shiv City Center Joint Venture, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shiv City Center?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shiv City Center?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shiv City Center?

The professionals named in the filing: Architect: Ar Vivekanand Murlidhar Deshpande. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shiv City Center?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shiv City Center. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shiv City Center to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.