ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / SHINE

Valid until 31 Dec 2026 Residential/Group Housing project

SHINE

By SHRINIVAS ORGANISORS PRIVATE LIMITED

RG-GJ-53120 · RERA PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA10854/271022 · Last updated on GujRERA portal: 16 Mar 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2026Possession promisedno revision filed
45 of 81Construction stages doneacross 9 buildings; furthest along: External plumbing and external plaster, 95%
42 of 130Units unsoldnot recorded sold or booked
Jump to the 49 documents Report an error

SHINE is a Residential/Group Housing project by SHRINIVAS ORGANISORS PRIVATE LIMITED in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA10854/271022 on 27 Oct 2022. Possession is promised by 31 Dec 2026. 88 of the 130 units on this registration are recorded sold or booked, and 45 of 81 construction stages are filed complete.

At a glance

Project

  • NameSHINE
  • TypeResidential/Group Housing
  • Location
    • SHINE
    • SUPERCITY
    • BHADAJ DENTAL COLLEGE ROAD
    • NR SCIENCE CITY
    • SANTEJ
    • Kalol
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA10854/271022
  • ReraGenie IDRG-GJ-53120

Builder

  • NameSHRINIVAS ORGANISORS PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations13 more →
  • Past their filed date8

Key dates

this monthRegisteredOct 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on27 Oct 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings9 building records
  • Documents filed49 files

Current status

68%88 of 130 units booked
73.8%Of the estimated cost spent so far

Figures as on 16 Mar 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE D---101
TYPE A---1090109
TYPE A1---101
TYPE A2---202
TYPE A3---101
TYPE B---13013
TYPE B1---101
TYPE C---101
TYPE C1---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building9

As on 16 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

45 of 81 construction stages are filed complete across 9 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

TYPE D68%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE A79%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing87%
TYPE A169%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE A273%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
TYPE A368%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE B76%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%
TYPE B168%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE C68%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE C158%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 16 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes60%
Water supplyYes60%
Sewerage (chamber, lines, septic tank, STP)Yes60%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes50%
Street lightingYes50%
Community buildingsYes60%
Treatment and disposal of sewage and sullage waterYes60%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes60%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes60%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes40%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area43,862 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 109.51 cr
Cost incurredRs 80.78 cr
Spent of the estimate73.77%
BuildingWingEstimatedIncurred
TYPE ANARs 91.95 crRs 67.75 cr
TYPE BNARs 10.54 crRs 7.83 cr
TYPE A2NARs 1.81 crRs 1.34 cr
TYPE DNARs 93.32 lakhRs 70.00 lakh
TYPE B1NARs 91.36 lakhRs 67.00 lakh
TYPE A3NARs 90.61 lakhRs 67.45 lakh
TYPE C1NARs 87.24 lakhRs 64.14 lakh
TYPE CNARs 82.28 lakhRs 60.68 lakh
TYPE A1NARs 76.57 lakhRs 56.72 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJHARNA URMISHKUMAR NAGORI
EngineerNARESH K SHAH

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA10854/271022 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)16 Mar 2026
Engineer's certificate (Form 2)16 Mar 2026
Engineer's certificate annexure16 Mar 2026
Accountant's certificate (Form 3)16 Mar 2026
Site photograph, TYPE D16 Mar 2026
Site photograph, TYPE A16 Mar 2026
Site photograph, TYPE A116 Mar 2026
Site photograph, TYPE A216 Mar 2026
Site photograph, TYPE A316 Mar 2026
Site photograph, TYPE B16 Mar 2026
Site photograph, TYPE B116 Mar 2026
Site photograph, TYPE C16 Mar 2026
Site photograph, TYPE C116 Mar 2026
RERA registration certificate27 Oct 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

68%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SHINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmSHINEOther 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: SHRINIVAS ORGANISORS PRIVATE LIMITED

SHRINIVAS ORGANISORS PRIVATE LIMITED has 14 registrations on GujRERA, including SUPER CITY PHASE 1 and SUPER CITY PHASE 2 DREAM. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SHINE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHINE?

The registered promoter entity is SHRINIVAS ORGANISORS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHINE?

The professionals named in the filing: Architect: JHARNA URMISHKUMAR NAGORI; Engineer: NARESH K SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHINE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.