Home / Browse projects / Gandhinagar, Gujarat / SHIKSHAPATRI SKY NINE

Valid until 30 Jan 2027 Mixed Development project

SHIKSHAPATRI SKY NINE

By SHIKSHAPATRI FIVE

RG-GJ-78849 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11083/281222 · Last updated on GujRERA portal: 21 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jan 2027Possession promisedno revision filed
4 of 9Construction stages donefurthest along: Staircases, 79%
74 of 140Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

SHIKSHAPATRI SKY NINE is a Mixed Development project by SHIKSHAPATRI FIVE in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11083/281222 on 28 Dec 2022. Possession is promised by 30 Jan 2027. 66 of the 140 units on this registration are recorded sold or booked, and 4 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHIKSHAPATRI SKY NINE
  • TypeMixed Development
  • Location
    • FP No. 5
    • TP No. 26
    • Block No 8-B-1
    • Vasana Hadmatiya Sargasan Vavol
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11083/281222
  • ReraGenie IDRG-GJ-78849

Builder

  • NameSHIKSHAPATRI FIVE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2022PromisedJan 2027

Key facts

Registration and timeline

  • StatusValid until 30 Jan 2027
  • Registered on28 Dec 2022
  • Promised completion30 Jan 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed37 files

Current status

47%66 of 140 units booked
31.8%Of the estimated cost spent so far

Figures as on 21 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B+C+D---10139140

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 21 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 9 construction stages are filed complete. The stage furthest along is Staircases, at 79%.

A+B+C+D: 54% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor1%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats1%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks79%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing1%

Progress on shared amenities23

As on 21 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes100%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,541 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 70.80 cr
Cost incurredRs 22.50 cr
Spent of the estimate31.78%
BuildingWingEstimatedIncurred
A+B+C+DNARs 70.80 crRs 22.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMONIKABA R JADEJA
EngineerVIREN D PAREKH

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11083/281222 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)21 Oct 2024
Engineer's certificate annexure21 Oct 2024
RERA registration certificate28 Dec 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

47%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SHIKSHAPATRI SKY NINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmSHIKSHAPATRI SKY NINEOther 194Dot size: filed unitsN

Filed coordinates, straight-line distance. 194 registered projects within 2 km.

Builder: SHIKSHAPATRI FIVE

SHIKSHAPATRI FIVE has 1 registration on GujRERA, including SHIKSHAPATRI SKY NINE. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SHIKSHAPATRI SKY NINE is delayed beyond 30 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHIKSHAPATRI SKY NINE?

The registered promoter entity is SHIKSHAPATRI FIVE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHIKSHAPATRI SKY NINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHIKSHAPATRI SKY NINE?

The professionals named in the filing: Architect: MONIKABA R JADEJA; Engineer: VIREN D PAREKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIKSHAPATRI SKY NINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIKSHAPATRI SKY NINE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIKSHAPATRI SKY NINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.