Home / Browse projects / Raigarh, Maharashtra / Sheltrex Smart Phone City Project 2 - Phase I

Registration lapsed No litigation declared Others project

Sheltrex Smart Phone City Project 2 - Phase I

By Sheltrex Karjat Pvt. Ltd.

RG-MH-27121 · RERA P51800012307 · Last updated on MahaRERA portal: 20 Feb 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date
  • 42 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
49 of 187Construction stages doneacross 17 buildings; furthest along: Stilt Floor, 80%
42Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

Sheltrex Smart Phone City Project 2 - Phase I is a Others project by Sheltrex Karjat Pvt. Ltd. in Raigarh, Maharashtra, registered with MahaRERA as P51800012307 on 1 Sep 2017. Possession was promised by 30 Dec 2022 and is now 46 months past that date. 42 complaints are on record with the regulator.

At a glance

Project

  • NameSheltrex Smart Phone City Project 2 - Phase I
  • TypeOthers
  • Location
    • Karjat
    • Raigarh
    • 401201
  • Pincode401201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012307
  • ReraGenie IDRG-MH-27121

Builder

  • NameSheltrex Karjat Pvt. Ltd.
  • Entity typeCompany
  • DirectorSURESH SINGH
  • Other registrations6 more →
  • No longer live7 lapsed, de-registered or revoked

Key dates

46 months past promisethis monthRegisteredSep 2017PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings17 building records
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
X2NA90000
X3NA90000
X1NA90000
X4NA90000
Y10NA270000
Y11NA260000
Y12NA260000
Y13NA260000
Y14NA260000
Z4NA250000
Z5NA250000
Z6NA250000
Z7 Proposed but not SanctionedNA250000
Z10 Proposed but not sanctionedNA250000
Z9 Proposed but not SanctionedNA250000
Z11 Proposed but not sanctionedNA240000
Z12 Proposed but not SanctionedNA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building17

As on 20 Feb 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

49 of 187 construction stages are filed complete across 17 buildings. The stage furthest along is Stilt Floor, at 80%.

X240%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
X352%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
X152%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
X451%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Y1042%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)65%
Plinth100%
Stilt Floor80%
Slabs of Super Structure14%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Y1142%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)65%
Plinth100%
Stilt Floor80%
Slabs of Super Structure14%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Y1246%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)65%
Plinth100%
Stilt Floor100%
Slabs of Super Structure45%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Y1346%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)65%
Plinth100%
Stilt Floor100%
Slabs of Super Structure41%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Y1446%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)70%
Plinth100%
Stilt Floor100%
Slabs of Super Structure36%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Z438%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure13%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Z538%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure13%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Z637%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure4%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Z7 Proposed but not Sanctioned0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Z10 Proposed but not sanctioned0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Z9 Proposed but not Sanctioned0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Z11 Proposed but not sanctioned0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Z12 Proposed but not Sanctioned0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Feb 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed3469

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3,469
Closed/Covered126
Open Space3,343
BuildingClosed/CoveredOpen SpaceTotal
Y1028224252
Y1128426454
Y1228426454
Y1318436454
Y140454454
Z48454462
Z58454462
Z68469477

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area26,010 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI136497.59
Proposed, not sanctioned70,318 sq m
Buildings approved17
Buildings sanctioned17

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKalina Santacruz East

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRahul Shivaji Agaj
PartnerRole in project
Sheltrex Karjat Pvt. Ltd.-

Complaints filed with MahaRERA42

Case no.ComplainantRespondentFiled
CC006000000023043MANOJKUMAR CHANDRESWAR MHATRESHELTREX SMART PHONE CITY22/01/2018
CC006000000055748Deepak ShettySheltrex smart phone city14/08/2018
CC006000000056465GAUTAM MADHUKAR VAKALESHELTREX SMART PHONE CITY05/10/2018
CC006000000056696Usha Dulichand SharmaSheltrex Karjat Pvt Ltd31/10/2018
CC006000000089632MEHUL KUMARSHELTREX KARJAT PVT. LTD.07/06/2019
CC006000000100452Atmaram ParadkarSheltrex Karjat Pvt. Ltd.08/08/2019
CC006000000110860Talat Amina Anjum Mashooque KhanSheltrex Karjat Private Limited16/09/2019
CC006000000197969Benny George KunjappySheltrex Karjat Pvt Ltd23/08/2021
CC006000000110911Venkat SonkawadeSheltrex Karjat Pvt. Ltd.20/09/2019
CC006000000171493SABHAJIT YADAVSheltex Karjat Pvt. Ltd11/11/2019
CC006000000192429Mangesh BasroorSheltrex Karjat Pvt Ltd17/02/2020
CC006000000193167TRILOCHAN KAUR ALAGMr. Suresh Singh Mr Rajesh Krishnan06/04/2020
CC006000000193206Santosh ShuklaSheltrex Karjat Pvt Ltd03/07/2020
CC006000000193287Bhushan TrivediSheltrex Karjat Pvt Ltd12/06/2020
CC006000000193547Aishwarya MisraSheltrex Karjat Private Limited19/09/2020
CC006000000194680Dr Ms Lalitha Ramchandran IyerSheltrex Karjat Pvt Ltd (also known as Gopi Resorts Pvt Ltd.27/10/2020
CC006000000195769Lakshmi venkatgiriSheltrex Karjat Pvt Ltd11/03/2021
CC006000000195827Jiten Chandrakant KoliSheltrex Karjat Pvt. Ltd.31/01/2021
CC006000000210126Jayesh Joma BhoirSheltrex Karjat Private Limited28/02/2022
CC006000000197235RASIKLAL MEHTASHELTREX KARJAT PVT. LTD.14/06/2021
CC006000000197268RASIKLAL MEHTASHELTREX KARJAT PVT. LTD.14/06/2021
CC006000000197271HARSHAD MEHTASHELTREX KARJAT PVT. LTD.15/06/2021
CC006000000197276KALPANA HARSHAD MEHTASHELTREX KARJAT PVT. LTD.15/06/2021
CC006000000197765RUPAKSHI AMIT DADHICH @ RUPAKSHI DADHICHM/S. SHELTREX KARJAT PVT. LTD.,27/07/2021
CC006000000198056SANJEEV VISHNU MAHAGAONKARSHELTREX KARJAT PRIVATE LTD24/08/2021
CC006000000198640Mr. Vijaykumar Krishnapal Lahot and Mrs. Jyoti Rajendrakumar KanojiyaSheltrex Karjat Pvt Ltd11/10/2021
CC006000000209921Sushma Ravindra TarpheM/s Sheltrex Karjat Pvt Ltd28/02/2022
CC006000000220714SHYAMKUMAR SUKHDEV GUPTAM/s SHELTREX KARJAT PVT. LTD20/04/2022
CC006000000220932SEMANTI MukherjeeGopi Resort PVT. LTD.02/06/2022
CC006000000220836Mamta PawaskarSheltrex Karjat Pvt Ltd18/04/2022
CC006000000241329Rakesh Gangaram KayithiSheltrex Karjat Pvt. Ltd.01/06/2022
CC006000000241330Ali Akbar MukhiSheltrex Karjat Pvt. Ltd.01/06/2022
CC006000000251487Sana Mohd Iftekhar JafreeSheltrex Karjat Pvt Ltd18/06/2022
CC006000000333777BRIJESH VINOD GUPTASHELTREX KARJAT PRIVATE LIMITED24/12/2022
CC006000000303375Swapnil ChincholeSheltrex Karjat Pvt. Ltd.(Suresh Singh)08/12/2022
CC006000000303745VEERBHADRAN NARAYANAN NAIRSHELTREX SMART PHONE CITY PROJECT 2 PHASE 123/12/2022
CC006000000303748VEERBHADRAN NARAYANAN NAIRSHELTREX SMART PHONE CITY PROJECT 2 PHASE 123/12/2022
CC006000000334141Prakash Subrao MaliSheltrex Karjat Pvt Ltd06/02/2023
CC006000000395522DATTARAM JANU KUDEKARSheltrex Karjat Private Limited06/05/2023
CC006000000397165Pratibha Vilas ChaudhariSheltrex Karjat pvt ltd25/08/2023
CC12501474Savita Sandeep SavadimathSheltrex Karjat Pvt. Ltd.01/05/2025
CC12601756Harshwardhan Siddharth MalwadeSheltrex Karjat Pvt. Ltd.27/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Doc - Feb 18 2019 - 18-21-compressed_reduce (1).pdf20 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA-1-c (1).pdf23 Jan 2019
Certificates of CA (Form 5)File: Sheltrex Karjat - Form 5.pdf22 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate.pdf16 Aug 2018
Certificates of CA (Form 3)File: CA Certificate.pdf16 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Arch Cert may 2018.pdf29 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert scanned dec end.pdf28 May 2018
Certificates of CA (Form 3)File: CA Certificate.pdf28 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 2.pdf21 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate 1.pdf21 May 2018
Layout approvalFile: Annexure -02 Master Plan-Low -Phase 1.pdf29 Jul 2017
Building plan approvalFile: Annexure -10 Commencement Certificate-low.pdf29 Jul 2017
Building plan approvalFile: Akurle_CC_13apr2015-low.pdf29 Jul 2017
PAN CardFile: SKPL - Pan card - 170203.pdf29 Jul 2017
Copy of the legal title reportFile: AKURLE TITLE 31052017 - Low.pdf29 Jul 2017
Details of encumbrancesFile: Details of encrumbrances.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Annexure -02 Master Plan-Low -Phase 1.pdf29 Jul 2017
Building Plan Approval (IOD)File: Akurle_CC_13apr2015-low.pdf29 Jul 2017
Building Plan Approval (IOD)File: Annexure -10 Commencement Certificate-low.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Akurle_CC_13apr2015-low.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Annexure -10 Commencement Certificate-low.pdf29 Jul 2017
Declaration in FORM BFile: PHASE I RERA DECLARATION-low.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE - P-1 form 1.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 1.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate - Phase 1 of Akurle.pdf29 Jul 2017
Certificates of CA (Form 3)File: combinepdf-low001.pdf29 Jul 2017
Certificates of CA (Form 3)File: combinepdf-low002.pdf29 Jul 2017
Certificates of CA (Form 3)File: combinepdf-low003.pdf29 Jul 2017
Certificates of CA (Form 3)File: combinepdf-low004.pdf29 Jul 2017
Certificates of CA (Form 3)File: combinepdf-low005.pdf29 Jul 2017
Proforma of Allotment letterFile: Allotment Letter.pdf29 Jul 2017
Proforma of Allotment letterFile: RERA 29072017 Phase I.pdf29 Jul 2017
OtherFile: Annexure -02 Master Plan-Low.pdf29 Jul 2017
OtherFile: Annexure -03 Layout plan-Low.pdf29 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sheltrex Smart Phone City Project 2 - Phase on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Karjat5,900+ in Raigarh

2 kmSheltrex Smart Phone CitCompleted 59Lapsed / revoked 42Other 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 151 registered projects within 2 km.

Builder: Sheltrex Karjat Pvt. Ltd.

Sheltrex Karjat Pvt. Ltd. has 7 registrations on MahaRERA, including Sheltrex Smart Phone City Project 2 - Phase II and Sheltrex Smart Phone City Project 2 - Phase I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Sheltrex Smart Phone City Project 2 - Phase I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sheltrex Smart Phone City Project 2 - Phase I is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sheltrex Smart Phone City Project 2 - Phase I?

The registered promoter entity is Sheltrex Karjat Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sheltrex Smart Phone City Project 2 - Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sheltrex Smart Phone City Project 2 - Phase I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sheltrex Smart Phone City Project 2 - Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sheltrex Smart Phone City Project 2 - Phase I?

The professionals named in the filing: Architect: Rahul Shivaji Agaj. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sheltrex Smart Phone City Project 2 - Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sheltrex Smart Phone City Project 2 - Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sheltrex Smart Phone City Project 2 - Phase to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.