Home / Browse projects / Mumbai Suburban, Maharashtra / SHEETAL SHREE KAILASH

Registered No litigation declared Residential / Group Housing project

SHEETAL SHREE KAILASH

By TOUGHCONS REALTORS PRIVATE LIMITED

RG-MH-73551 · RERA P51800048719 · Last updated on MahaRERA portal: 8 Apr 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 32 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 32 months from the original
7 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 81%
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

SHEETAL SHREE KAILASH is a Residential / Group Housing project by TOUGHCONS REALTORS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800048719 on 13 Jan 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 32 months from the original filing.

At a glance

Project

  • NameSHEETAL SHREE KAILASH
  • TypeResidential / Group Housing
  • Location
    • DATTA MANDIR ROAD
    • VAKOLA
    • Andheri
    • Mumbai Suburban
    • 400055
  • Pincode400055
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800048719
  • ReraGenie IDRG-MH-73551

Builder

  • NameTOUGHCONS REALTORS PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsBRAHMDEV DUDHNATH SHUKLA, SURAJDEV DUDHNATH SHUKLA
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJan 2023First promiseApr 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on13 Jan 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 1 Apr 2024)
  • Buildings2 building records
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHEETAL KAILASH WING ANA60000
sheetal kailash B WINGNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 81%.

SHEETAL KAILASH WING A57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure81%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises34%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks74%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
sheetal kailash B WING41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure63%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks63%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Closed/Covered45
BuildingClosed/CoveredTotal
SHEETAL KAILASH WING A2222
sheetal kailash B WING2323

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area850 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHREE KAILASH CO OP HSG SOC LTDBandraMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2303.0
Proposed, not sanctioned2,303 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIDC ANDHERI EAST MUMBAI 400093

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHIJIT UDANI
EngineerUNISTEPS CONSULTANT PVT LTD
Chartered AccountantRAJPUROHIT & TIWARI
PartnerRole in project
TOUGHCONS REALTORS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800019688Apr 2024 → Dec 2026

Reason as filed by the promoterWe are under process of completion of our project we need extension till 31 Dec 2026

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Dec 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-SEP.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec.pdf8 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Sep_compressed.pdf8 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Dec_compressed.pdf8 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Sep.pdf8 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Dec.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM NO 1 - June-2024.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- June-24.pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM NO 2 -June-24.pdf25 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2-A- FY-23-24.pdf12 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-5 -FY-23-24.pdf12 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3- March-24_compressed.pdf13 May 2024
Declaration in FORM BFile: Notary Toughcons.pdf30 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf27 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf27 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2-A_1 (2 files merged).pdf27 Apr 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf27 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf27 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 dec.pdf23 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 dec.pdf23 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sheetal shree kailash.pdf27 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sheetal shree kailash.pdf27 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SHREE KAILESH FORM FORM-B_001.pdf27 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SHREE KAILESH FORM FORM-B SEP 2023_001.pdf27 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 March-23.pdf27 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 june-23.pdf27 Sep 2023
Copy of the legal title reportFile: TITLE NEW.pdf31 Dec 2022
Details of encumbrances concerned to FinanceFile: No encumbrances Certificate FINANCE and LEGAL new.pdf31 Dec 2022
Details of encumbrances concerned to LegalFile: No encumbrances Certificate FINANCE and LEGAL new.pdf31 Dec 2022
Declaration about Commencement CertificateFile: Decleration about CC New.pdf31 Dec 2022
Declaration in FORM BFile: Form b sheetal kailas.pdf31 Dec 2022
CERSAI detailsFile: CERSAI Search Report.pdf31 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost.pdf31 Dec 2022
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclouser of Interest in other real estate organization.pdf31 Dec 2022
Proforma of Allotment letterFile: allotment letter new.pdf31 Dec 2022
Proforma of Agreement for saleFile: AFS NEW.pdf31 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A bank account decla (1).pdf31 Dec 2022
Deviation Report with respect to Allotment letterFile: deviation-allotment New.pdf31 Dec 2022
Deviation Report with respect to model copy of AgreementFile: deviation-draft sale new.pdf31 Dec 2022
Layout approvalFile: Concessiion Plan.pdf29 Dec 2022
Building plan approvalFile: Concessiion Plan 1.pdf29 Dec 2022
Copy of Layout Approval (in case of layout)File: Concessiion Plan.pdf29 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Concessiion Plan 1.pdf29 Dec 2022
PAN CardFile: PAN TOUGHCON.pdf23 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: CC_signed_first (1).pdf23 Sep 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 32 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHEETAL SHREE KAILASH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VAKOLA6,700+ in Mumbai Suburban

2 kmSHEETAL SHREE KAILASHCompleted 120Lapsed / revoked 76Other 136Dot size: filed unitsN

Filed coordinates, straight-line distance. 332 registered projects within 2 km.

Builder: TOUGHCONS REALTORS PRIVATE LIMITED

TOUGHCONS REALTORS PRIVATE LIMITED has 3 registrations on MahaRERA, including SHEETAL AIRWING and SHEETAL HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHEETAL SHREE KAILASH is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHEETAL SHREE KAILASH?

The registered promoter entity is TOUGHCONS REALTORS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHEETAL SHREE KAILASH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHEETAL SHREE KAILASH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHEETAL SHREE KAILASH?

The professionals named in the filing: Architect: ABHIJIT UDANI; Engineer: UNISTEPS CONSULTANT PVT LTD; Chartered Accountant: RAJPUROHIT & TIWARI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHEETAL SHREE KAILASH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHEETAL SHREE KAILASH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHEETAL SHREE KAILASH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.