Home / Browse projects / Sangli, Maharashtra / SHALINEE HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

SHALINEE HEIGHTS

By M S BUILDERS AND DEVELOPERS

RG-MH-51682 · RERA P53100051974 · Last updated on MahaRERA portal: 18 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 6 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Apr 2026Possession promised6 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
9 of 24Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

SHALINEE HEIGHTS is a Residential / Group Housing project by M S BUILDERS AND DEVELOPERS in Sangli, Maharashtra, registered with MahaRERA as P53100051974 on 13 Jul 2023. Possession was promised by 30 Apr 2026 and is now 6 months past that date. 15 of the 24 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHALINEE HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • NEW KUPWAD
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416415
  • Pincode416415
  • RERA no.P53100051974
  • ReraGenie IDRG-MH-51682

Builder

  • NameM S BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersDILIP APPASAHEB MOLE, DILIP APPASAHEB MOLE HUF, PADAMSHREE DILIP MOLE, DHIRAJ VIKAS SHAH
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

6 months past promisethis monthRegisteredJul 2023PromisedApr 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on13 Jul 2023
  • Promised completion30 Apr 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed61 files

Current status

62%15 of 24 units booked
99.0%Work done, per cost certificate

Figures as on 18 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHALINEE HEIGHTSNA6624024

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

SHALINEE HEIGHTS: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area509 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Sep 2025

Approvals and building plan

Sanctioning authoritySMKC
Permissible FSI1298.9
Proposed, not sanctioned1,299 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSANGLI
Estimated costRs 2.64 cr
Cost incurredRs 2.61 cr
Work done98.95%
BuildingWingEstimatedIncurred
SHALINEE HEIGHTSNARs 2.57 crRs 2.61 cr
-NARs 6.79 lakh-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMIT PANDIT MOHAN PANDIT
EngineerVIKAS M SHAH MANGALBHAI SHAH
Chartered AccountantKEDAR S SABANE A SABANE
PartnerRole in project
M S BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf18 May 2026
Withdrawal Update Form 2File: Form 2.pdf18 May 2026
Withdrawal Update Form 3File: CA Certificate.pdf18 May 2026
Withdrawal Update Form 1File: Form 1 Up to Sep 2025.pdf18 Apr 2026
Withdrawal Update Form 1File: Form 1 Up to Dec 2025.pdf18 Apr 2026
Withdrawal Update Form 2File: Form 2 Up to Sep 2025.pdf18 Apr 2026
Withdrawal Update Form 2File: Form 2 Up to Dec 2025.pdf18 Apr 2026
Withdrawal Update Form 3File: Form 3 Up to Sep 2025.pdf18 Apr 2026
Withdrawal Update Form 3File: Form 3 Up to Dec 2025.pdf18 Apr 2026
Withdrawal Update Form 1File: Architect Letter (1).pdf26 Sep 2025
Withdrawal Update Form 2File: Engineers Letter (1).pdf26 Sep 2025
Withdrawal Update Form 3File: C A Certificate (2).pdf26 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 up to Mar 2025.pdf7 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 up to Mar 2025.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 up to Mar 2025.pdf7 May 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory up to Mar 2025.pdf7 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf3 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf3 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf3 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf2 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf2 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf2 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf2 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (1).pdf17 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engeineer Certificate.pdf17 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory (1).pdf17 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate.pdf17 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf10 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf10 May 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory (1).pdf10 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf10 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf24 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory (1).pdf24 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate.pdf24 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate with Sign.pdf26 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf25 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf25 Oct 2023
Other - TechnicalFile: Adobe Scan Jul 06, 2023 (5).pdf6 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT.pdf30 Jun 2023
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development (2).pdf20 Jun 2023
Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf20 Jun 2023
PAN CardFile: 1 PAN Card.pdf20 Jun 2023
Copy of the legal title reportFile: 1 Copy of the legal title report (1).pdf20 Jun 2023
Details of encumbrances concerned to FinanceFile: FINANCE.pdf20 Jun 2023
Details of encumbrances concerned to FinanceFile: LEGAL.pdf20 Jun 2023
Details of encumbrances concerned to LegalFile: FINANCE.pdf20 Jun 2023
Details of encumbrances concerned to LegalFile: LEGAL.pdf20 Jun 2023
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf20 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development (2).pdf20 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development (1).pdf20 Jun 2023
Declaration about Commencement CertificateFile: DECLARATION ANOUT.pdf20 Jun 2023
Declaration in FORM BFile: Adobe Scan Jun 20, 2023 (8)_compressed.pdf20 Jun 2023
CERSAI detailsFile: CERSAI DEC.pdf20 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf20 Jun 2023
Proforma of Allotment letterFile: Adobe Scan Jun 20, 2023 (7)_compressed.pdf20 Jun 2023
Proforma of Agreement for saleFile: AGRE FORMAT.pdf20 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPRATE BANK ACCOUNT.pdf20 Jun 2023
Deviation Report with respect to Allotment letterFile: ALLOT DEVIATION.pdf20 Jun 2023
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement.pdf20 Jun 2023

How this compares with Sangli

62%of this project is bookeddistrict median 16%
11%of Sangli projects moved their completion datethis one has not
29%of Sangli registrations have lapsed or been cancelledthis one is among them

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep SHALINEE HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEW KUPWAD790+ in Sangli

Builder: M S BUILDERS AND DEVELOPERS

M S BUILDERS AND DEVELOPERS has 2 registrations on MahaRERA, including M S PLAZA and SHALINEE HEIGHTS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What does it mean that SHALINEE HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHALINEE HEIGHTS is delayed beyond 30 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHALINEE HEIGHTS?

The registered promoter entity is M S BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHALINEE HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHALINEE HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHALINEE HEIGHTS?

The professionals named in the filing: Architect: AMIT PANDIT MOHAN PANDIT; Engineer: VIKAS M SHAH MANGALBHAI SHAH; Chartered Accountant: KEDAR S SABANE A SABANE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHALINEE HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHALINEE HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHALINEE HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.