ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / SHAH S MANGALAM

Registration lapsed No litigation declared Residential / Group Housing project

SHAH S MANGALAM

By SHAH BUILDERS AND DEVELOPERS

RG-MH-90546 · RERA P51600051988 · Last updated on MahaRERA portal: 10 Nov 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
19 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
8 of 18Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

SHAH S MANGALAM is a Residential / Group Housing project by SHAH BUILDERS AND DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600051988 on 13 Jul 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 10 of the 18 units on this registration are recorded sold or booked, and 19 of 33 construction stages are filed complete.

At a glance

Project

  • NameSHAH S MANGALAM
  • TypeResidential / Group Housing
  • Location
    • LAM ROAD
    • DEOLALI CAMP
    • Deolali (CB)
    • Nashik
    • 422402
  • Pincode422402
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600051988
  • ReraGenie IDRG-MH-90546

Builder

  • NameSHAH BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersMAHENDRA KANKUCHAND SHAH, SHRUTI ATISH SHAH
  • Other registrations11 more →
  • Completed10 of 12
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

10 months past promisethis monthRegisteredJul 2023PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on13 Jul 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed70 files

Current status

56%10 of 18 units booked
100.0%Work done, per cost certificate

Figures as on 10 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA44606
B WINGNA44606
C WINGNA44606

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 10 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

A WING64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING55%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C WING55%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Closed/Covered3
Open Space6
BuildingClosed/CoveredOpen SpaceTotal
A WING123
B WING123
C WING123

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,660 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Jun 2025
LandownerVillageDistrict
BAPU LAXMAN SHINDEDeolali (CB)Nashik
RAMDAS LAXMAN SHINDEDeolali (CB)Nashik
SHANKAR LAXMAN SHINDEDeolali (CB)Nashik
SHINDUBAI LAXMAN SHINDEDeolali (CB)Nashik
SANDEEP JAGANATH SHINDEDeolali (CB)Nashik

Approvals and building plan

Sanctioning authorityCantonment Board Deolali
Permissible FSI850.0
Proposed, not sanctioned850 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDEOLALI CAMP DEOLALI
Estimated costRs 4.00 cr
Cost incurredRs 4.00 cr
Work done100.0%
BuildingWingEstimatedIncurred
C WINGNARs 1.34 crRs 1.34 cr
A WINGNARs 1.33 crRs 1.33 cr
B WINGNARs 1.33 crRs 1.33 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNITIN SALAVE K SALAVE
EngineerACHAL RAJE RAJE
Chartered AccountantCA KARAN MAHALE
Chartered AccountantSANKET SANGALE S SANGALE
Chartered AccountantMAHESH PUNAMCHAND SHAH
PartnerRole in project
SHAH BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate.pdf10 Nov 2025
Withdrawal Update Form 2File: Engineer Certificate.pdf10 Nov 2025
Withdrawal Update Form 3File: From 3.pdf10 Nov 2025
Withdrawal Update Form 1File: Architect Certificate.pdf6 Nov 2025
Withdrawal Update Form 2File: Engineer Certificate.pdf6 Nov 2025
Withdrawal Update Form 3File: From 3.pdf6 Nov 2025
Form 2A (FY 2024-2025)File: From 2 A.pdf16 Oct 2025
Form 5 (FY 2024-2025)File: From 5.pdf1 Oct 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate .pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From No 3_compressed.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Rera Audit From 5.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginer Certificate.pdf17 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate_compressed.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate Final.pdf16 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: From 2 AA.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate Shah's Mangalam site.pdf1 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf25 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2 AA.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Mangalm.pdf22 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate.pdf22 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf29 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate_compressed.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginer Certificate.pdf30 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf23 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf23 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate_compressed.pdf23 Oct 2023
Building plan approvalFile: New Plan_compressed.pdf28 Jun 2023
Building plan approvalFile: Declration of plan.pdf28 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: New Plan_compressed.pdf28 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Declration of plan.pdf28 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a Certificate_compressed.pdf21 Jun 2023
Building plan approvalFile: STAMP.pdf7 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: STAMP.pdf7 Jun 2023
Copy of the legal title reportFile: Titile Report_compressed-1.pdf1 Jun 2023
Copy of the legal title reportFile: Titile Report_compressed-2.pdf1 Jun 2023
Copy of the legal title reportFile: Titile Report_compressed-3.pdf1 Jun 2023
Details of encumbrances concerned to FinanceFile: Encubrance31052023.pdf1 Jun 2023
Details of encumbrances concerned to LegalFile: Encubrance31052023.pdf1 Jun 2023
CERSAI detailsFile: CERSAI31052023.pdf1 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: interst31052023_compressed.pdf1 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration31052023.pdf1 Jun 2023
Layout approvalFile: Lay Out.pdf17 May 2023
Copy of Layout Approval (in case of layout)File: Lay Out.pdf17 May 2023
PAN CardFile: 1 PAN Card.pdf11 May 2023
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate legal.pdf11 May 2023
Details of encumbrances concerned to LegalFile: Encumbrance Certificate legal.pdf11 May 2023
Commencement Certificates / NA Order for plotted developmentFile: N A orders_compressed.pdf11 May 2023
Declaration about Commencement CertificateFile: Declration Commencement Certificate.pdf11 May 2023
Declaration in FORM BFile: From B Atish Shah_compressed.pdf11 May 2023
Proforma of Agreement for saleFile: RERA AGREEMENT DRAFT.pdf11 May 2023
Proforma of Allotment letterFile: allotment letters.pdf11 May 2023
Deviation Report with respect to Allotment letterFile: Deviation for allotement letters_compressed.pdf11 May 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Agrrement draft_compressed-1-9.pdf11 May 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Agrrement draft_compressed-10-18.pdf11 May 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Agrrement draft_compressed-19-27.pdf11 May 2023

How this compares with Nashik

56%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHAH S MANGALAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DEOLALI CAMP4,100+ in Nashik

2 kmSHAH S MANGALAMCompleted 7Lapsed / revoked 5Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: SHAH BUILDERS AND DEVELOPERS

SHAH BUILDERS AND DEVELOPERS has 12 registrations on MahaRERA, including SHAHS GARDEN RESIDENCY PHASE II and SHAH GOVIND APARTMENT PHASE II. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that SHAH S MANGALAM shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHAH S MANGALAM is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHAH S MANGALAM?

The registered promoter entity is SHAH BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHAH S MANGALAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHAH S MANGALAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHAH S MANGALAM?

The professionals named in the filing: Architect: NITIN SALAVE K SALAVE; Engineer: ACHAL RAJE RAJE; Chartered Accountant: CA KARAN MAHALE; Chartered Accountant: SANKET SANGALE S SANGALE; Chartered Accountant: MAHESH PUNAMCHAND SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHAH S MANGALAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHAH S MANGALAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHAH S MANGALAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.