ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / SHAGUN 14

Valid until 30 Dec 2025 Residential/Group Housing project

SHAGUN 14

By RIDDHI SIDDHI DEVELOPERS

RG-GJ-96419 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07562/191020 · Last updated on GujRERA portal: 28 May 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months

Clear

  • Nothing verified clear yet
Dec 2025Possession promisedmoved 12 months from the original
8 of 9Construction stages donefurthest along: Plinth, 0%
1 of 14Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

SHAGUN 14 is a Residential/Group Housing project by RIDDHI SIDDHI DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07562/191020 on 19 Oct 2020. Possession is promised by 30 Dec 2025. The completion date has moved by 12 months from the original filing. 13 of the 14 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHAGUN 14
  • TypeResidential/Group Housing
  • Location
    • 206/2
    • TP 19
    • RAYSAN-RANDESAN-KOBA
    • Raysan
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07562/191020
  • ReraGenie IDRG-GJ-96419

Builder

  • NameRIDDHI SIDDHI DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →
  • Past their filed date3

Key dates

this monthRegisteredOct 2020First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusValid until 30 Dec 2025
  • Registered on19 Oct 2020
  • Promised completion30 Dec 2025
  • Revised completionRevised to 30 Dec 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed41 files

Current status

93%13 of 14 units booked
86.1%Of the estimated cost spent so far

Figures as on 28 May 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shagun 14---14014

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 28 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Plinth, at 0%.

Shagun 14: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 28 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,370 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 4.50 cr
Cost incurredRs 3.88 cr
Spent of the estimate86.11%
BuildingWingEstimatedIncurred
Shagun 14NARs 4.50 crRs 3.88 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARPIT SHAH
EngineerVASANT SONI

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07562/191020 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)28 May 2025
Accountant's certificate (Form 3)28 May 2025
Site photograph, Shagun 1428 May 2025
Engineer's certificate (Form 2)17 Apr 2024
Engineer's certificate annexure17 Apr 2024
RERA registration certificate19 Oct 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

93%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 12 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SHAGUN 14 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Raysan1,600+ in Gandhinagar

2 kmSHAGUN 14Other 167Dot size: filed unitsN

Filed coordinates, straight-line distance. 167 registered projects within 2 km.

Builder: RIDDHI SIDDHI DEVELOPERS

RIDDHI SIDDHI DEVELOPERS has 3 registrations on GujRERA, including Shagun 15 and Shagun 12. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SHAGUN 14 is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHAGUN 14?

The registered promoter entity is RIDDHI SIDDHI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHAGUN 14?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHAGUN 14?

The professionals named in the filing: Architect: ARPIT SHAH; Engineer: VASANT SONI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHAGUN 14?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHAGUN 14. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHAGUN 14 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.