Home / Browse projects / Mumbai Suburban, Maharashtra / SCORPIO

Registered Litigation declared Residential / Group Housing project

SCORPIO

By JASANI REALTY PVT.LTD

RG-MH-59034 · RERA P51800010230 · Last updated on MahaRERA portal: 29 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • Completion date moved by 40 months
  • 3 extensions taken
  • Rs 56.00 crore secured on the land, in favour of JM Financial Credit Solutions Limited

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 40 months from the original
3 of 11Construction stages donefurthest along: Podiums (if any), 90%
96 of 139Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 147 documents Report an error

SCORPIO is a Residential / Group Housing project by JASANI REALTY PVT.LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010230 on 24 Aug 2017. Possession is promised by 30 Apr 2027. The completion date has moved by 40 months from the original filing. 43 of the 139 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameSCORPIO
  • TypeResidential / Group Housing
  • Location
    • Borivali
    • Mumbai Suburban
    • 400095
  • Pincode400095
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800010230
  • ReraGenie IDRG-MH-59034

Builder

  • NameJASANI REALTY PVT.LTD
  • Entity typeCompany
  • Managing DirectorUDAY INDUKUMAR JASANI
  • ChairpersonHANSA INDUKUMAR JASANI
  • DirectorSantosh Pratap Kapse
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Aug 2017
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed147 files

Current status

31%43 of 139 units booked
69.1%Work done, per cost certificate

Figures as on 29 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SCORPIONA232312613139

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 90%.

SCORPIO: 67% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)90%
Plinth100%
Stilt Floor100%
Slabs of Super Structure87%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%

Progress on shared amenities15

As on 29 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed213

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots213
Closed/Covered213

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,260 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofJM Financial Credit Solutions Limited
Secured amountRs 56.00 crore
CERSAI search filedYes
Declared on12 Dec 2025
LandownerVillageDistrict
DARYANANI INDO SAIGON CONSTRUCTIONS PVT.LTDMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityBRIHANMUMBAI MUNICIPAL CORPORATION
Permissible FSI9022.0
Proposed, not sanctioned7,432 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Express Towers, Nariman Point, Mumbai, Maharashtra 400021
Estimated costRs 69.00 cr
Cost incurredRs 47.69 cr
Work done69.11%
BuildingWingEstimatedIncurred
SCORPIONARs 65.55 crRs 47.46 cr
-NARs 3.45 crRs 22.98 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCharudatt Pradhan
ArchitectThe Design Core
EngineerMukesh Tambe
EngineerSK Consultants & Engineers
Chartered AccountantN B Sayed & Associates
Chartered AccountantVikas Abhang & Associates
Chartered AccountantPranav Bhaskaran & Associates
PartnerRole in project
JASANI REALTY PVT.LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P51800010230/WarDec 2023 → Apr 2027

Reason as filed by the promoterNA

EXT51800013035Dec 2023 → Dec 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 60 % allottees for purpose of extension of RERA registration period of the said project.

EA17092502617Dec 2023 → Dec 2026

Reason as filed by the promoterWe are writing to formally request an extension to the project completion timeline. The recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highest standards of quality and deliverables, additional time is essential. We are committed to completing the project efficiently and effectively, and we believe that this extension will enable us to meet all expectations without compromising on quality.

Litigation declared4

CaseCourtStatus
7496/2002BOMBAY HIGH COURTClosed
2684/2014BOMBAY HIGH COURTClosed
7104/2002Bombay High CourtClosed
2684/2014Bombay High CourtClosed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Mar 2024

Documents filed147

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 147 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A-FY 25-26.pdf29 Sep 2026
Form 2A (FY 2022-2023)File: Form 2A 2022-2023.pdf7 Sep 2026
Form 2A (FY 2023-2024)File: Form 2A 2023-2024.pdf7 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A 2024-2025.pdf7 Sep 2026
Withdrawal Update Form 1File: Form 1 - Scorpio as on June 2026.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 - Scorpio as on June 2026.pdf21 Aug 2026
Withdrawal Update Form 3File: Form 3 - Scorpio as on June 2026.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 - Scorpio as on June 2026.pdf17 Jul 2026
Withdrawal Update Form 2File: Form 2 - Scorpio as on June 2026.pdf17 Jul 2026
Withdrawal Update Form 3File: Form 3 - Scorpio as on June 2026.pdf17 Jul 2026
Form 1File: Form 1 - Scorpio as on March 2025 (Signed).pdf16 Jun 2026
Form 2File: Form 2 - Scorpio as on March 2025 (Signed).pdf16 Jun 2026
Form 3File: Form 3 - Scorpio as on March 2025 (Signed).pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: 20 floors cc.pdf16 Jun 2026
Form 5 (FY 2024-2025)File: Form 5 of Scorpio FY 2024-25.pdf8 Jun 2026
Withdrawal Update Form 1File: Form 1 - Scorpio as on March 2026.pdf23 May 2026
Withdrawal Update Form 2File: Form 2 - Scorpio as on March 2026.pdf23 May 2026
Withdrawal Update Form 3File: Form 3 - Scorpio as on March 2026.pdf23 May 2026
Withdrawal Update Form 1File: Form 1 - Scorpio as on Dec 2025.pdf13 May 2026
Withdrawal Update Form 1File: Form 1 - Scorpio as on Dec 2025.pdf13 May 2026
Withdrawal Update Form 2File: Form 2 - Scorpio as on Sep 2025.pdf13 May 2026
Withdrawal Update Form 2File: Form 2 - Scorpio as on Dec 2025.pdf13 May 2026
Withdrawal Update Form 3File: Form 3 - Scorpio as on Dec 2025.pdf13 May 2026
Withdrawal Update Form 3File: Form 3 - Scorpio as on Dec 2025.pdf13 May 2026
Layout approvalFile: Layout.pdf5 Dec 2025
Building plan approvalFile: 2435802Amendletter_signed.pdf5 Dec 2025
Building plan approvalFile: Layout.pdf5 Dec 2025
Building plan approvalFile: First Floor Plan.pdf5 Dec 2025
Building plan approvalFile: 2nd & 3rd Floor Plan.pdf5 Dec 2025
Building plan approvalFile: 4th, 5th, 6th, 8th, 10th, 12th, 14th, 16th, 18th, 20th Floor Plans.pdf5 Dec 2025
Building plan approvalFile: 7th, 9th, 11th, 13th, 15th, 17th, 19th & Terrace.pdf5 Dec 2025
Building plan approvalFile: Ground Floor Plan.pdf5 Dec 2025
Building plan approvalFile: 1st Floor BUA.pdf5 Dec 2025
Building plan approvalFile: 2nd & 3rd Floor BUA.pdf5 Dec 2025
Building plan approvalFile: Area statement.pdf5 Dec 2025
Building plan approvalFile: Elevation.pdf5 Dec 2025
Building plan approvalFile: Parking.pdf5 Dec 2025
Withdrawal Update Form 1File: Form 1 - Scorpio as on Sep 2025 (SIGNED).pdf19 Oct 2025
Withdrawal Update Form 2File: Form 2 - Scorpio as on Sep 2025.pdf19 Oct 2025
Withdrawal Update Form 3File: Form 3 - Scorpio as on Sep 2025.pdf19 Oct 2025
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf27 Sep 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf27 Sep 2025
Withdrawal Update Form 3File: Form 3 Scorpioo.pdf27 Sep 2025
Withdrawal Update Form 1File: 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf25 Sep 2025
Withdrawal Update Form 1File: Form 1 June 2025 Signed.pdf25 Sep 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf25 Sep 2025
Withdrawal Update Form 2File: Form 2 June 2025 Signed.pdf25 Sep 2025
Withdrawal Update Form 3File: Form 3 June 2025 Signed.pdf25 Sep 2025
Withdrawal Update Form 3File: Form 3 June 2025 Signed.pdf25 Sep 2025
Form 1File: Form 1 - Scorpio as on June 2025.pdf17 Sep 2025
Form 2File: Form 2 - Scorpio as on June 2025.pdf17 Sep 2025
Form 3File: Form 3 - Scorpio as on June 2025.pdf17 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Scorpio as on June 2025.pdf17 Sep 2025
Certificates of CA (Form 3)File: Form 3 - Scorpio as on March 2025.pdf10 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Scorpio as on March 2025.pdf10 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Scorpio as on March 2025.pdf8 Apr 2025
Layout approvalFile: Plan 1.pdf11 Feb 2025
Building plan approvalFile: Plan 2.pdf11 Feb 2025
Building plan approvalFile: Plan 3.pdf11 Feb 2025
Building plan approvalFile: Plan 4.pdf11 Feb 2025
Building plan approvalFile: Plan 5.pdf11 Feb 2025
Building plan approvalFile: Plan 6.pdf11 Feb 2025
Building plan approvalFile: Plan 7.pdf11 Feb 2025
Building plan approvalFile: Plan 8.pdf11 Feb 2025
Building plan approvalFile: Plan 9.pdf11 Feb 2025
Building plan approvalFile: Plan 10.pdf11 Feb 2025
Building plan approvalFile: Plan 11.pdf11 Feb 2025
Building plan approvalFile: Plan 12.pdf11 Feb 2025
Copy of Layout Approval (in case of layout)File: Plan 1.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 2.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 3.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 4.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 5.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 6.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 7.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 8.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 9.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 10.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 11.pdf11 Feb 2025
Building Plan Approval (IOD)File: Plan 12.pdf11 Feb 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
LACITADELKANDIVLI MUMBAI 40006714CompletedMar 2010Late, Apr 2013

How this compares with Mumbai Suburban

31%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 40 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SCORPIO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmSCORPIOCompleted 32Lapsed / revoked 19Other 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 99 registered projects within 2 km.

Builder: JASANI REALTY PVT.LTD

JASANI REALTY PVT.LTD has 2 registrations on MahaRERA, including Apollo Heights and SCORPIO. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SCORPIO is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SCORPIO?

The registered promoter entity is JASANI REALTY PVT.LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SCORPIO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SCORPIO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SCORPIO?

The professionals named in the filing: Architect: Charudatt Pradhan; Architect: The Design Core; Engineer: Mukesh Tambe; Engineer: SK Consultants & Engineers; Chartered Accountant: N B Sayed & Associates; Chartered Accountant: Vikas Abhang & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SCORPIO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SCORPIO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SCORPIO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.