Home / Browse projects / Bengaluru Rural, Karnataka / Sapthagiri Sampadha

Registration approved No litigation declared Residential/Group Housing project

Sapthagiri Sampadha

By Sapthagiri Constructions

RG-KA-40229 · RERA PRM/KA/RERA/1250/304/PR/190123/005629 · Last updated on RERA Karnataka portal: 20 Feb 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2025Possession promisedno revision filed
19 of 19Construction stages doneevery applicable stage filed complete
54 of 96Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 127 documents Report an error

Sapthagiri Sampadha is a Residential/Group Housing project by Sapthagiri Constructions in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/190123/005629 on 19 Jan 2023. Possession is promised by 31 Dec 2025. 42 of the 96 units on this registration are recorded sold or booked, and 19 of 19 construction stages are filed complete.

At a glance

Project

  • NameSapthagiri Sampadha
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
    • 560089
  • Pincode560089
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/190123/005629
  • ReraGenie IDRG-KA-40229

Builder

  • NameSapthagiri Constructions
  • Entity typePartnership Firm
  • Authorized SignatorySuman Kumar Yadam
  • Other registrations2 more →

Key dates

this monthRegisteredJan 2023PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Jan 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed127 files

Current status

44%42 of 96 units booked
106.0%Of the estimated cost spent so far

Figures as on 20 Feb 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sapthagiri Sampada---96096

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 20 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 19 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja work100%
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 20 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsNoNot applicable
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes100%
Common storage spacesYes100%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,844 sq m
Named landowners2
LandownerVillageDistrict
Venkatamma--
Chikka Sithappa--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 21.75 cr
Cost incurredRs 23.05 cr
Spent of the estimate105.98%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 20.00 crRs 18.36 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 1.50 crRs 3.62 cr
On-site expenditure-Consultants FeesRs 25.00 lakhRs 21.38 lakh
On-site expenditure-Salaries of workers-Rs 53.46 lakh
On-site expenditure-Site Overhead-Rs 32.08 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTata Vittala Srinivas
EngineerMANDHADI VENKAT RAMANA REDDY
Chartered AccountantANIMIREDDY RAMAKRISHNA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed127

As listed on the registration, under the names the promoter filed them with; the newest 80 of 127 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/190123/005629 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q3 FY2025-26_0001.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Q3.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q3.pdf20 Feb 2026
Q3 2025-26 Water supply and sewage board20 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)20 Feb 2026
Q3 2025-26 KPTCL- BESCOM20 Feb 2026
CA Certificate Form_1 SapthagiriFile: CA Certificate Form_1 Sapthagiri.pdf13 Jan 2023
Clarification for title transfer deed documents from chikkasethappa to venkatamma wo chikkaseethappaFile: Clarification for title transfer deed documents from chikkasethappa to venkatamma wo chikk9 Jan 2023
JDA GPA Land owners khathaFile: JDA GPA Land owners khatha.pdf9 Jan 2023
Affidavit cum DeclarationFile: Affidavit cum Declaration.pdf9 Jan 2023
AffidavitFile: Affidavit.pdf9 Jan 2023
Non-LitigationFile: No litigation.pdf9 Jan 2023
Form - 1 CA CertificatreFile: Form One.pdf9 Jan 2023
Membership certificate of CAFile: Membership certificate.jpeg19 Dec 2022
Form 1 CA CertificateFile: Form one Chartered Accountant Signed.pdf19 Dec 2022
Bank Account detailsFile: Bank.jpg19 Dec 2022
RTCFile: Latest RTC.pdf19 Dec 2022
Partition deed and IHR MR in the name of munikadarappa and chikkaseethappaFile: Partition deed and IHR MR in the name of munikadarappa and chikkaseethappa.pdf19 Dec 2022
local authorithy katha in the name of jda and gpa land ownersFile: local authorithy katha in the name of jda and gpa land owners.pdf19 Dec 2022
local authorithy katha in the name of jda and gpa land ownersFile: Title transfer deed documents from chikkasethappa to venkatamma wo chikkaseethappa and his19 Dec 2022
clarifications that chikka seethappa not signed to supplementary jdaFile: clarifications that chikka seethappa not signed to supplementary jda.pdf19 Dec 2022
EC till earlier to fifteen daysFile: EC till earlier to fifteen days.pdf19 Dec 2022
Advocate search reportFile: Advocate search report.pdf19 Dec 2022
Affidavit Cum Declaration Form-BFile: Affidavit Cum Declaration Form B.pdf19 Dec 2022
Affidavit Non LitigationFile: Affidavit Non Litigation.pdf19 Dec 2022
Sub registrar Guidance valueFile: Sub registrar Guidance value.pdf19 Dec 2022
Carpet area calculationFile: Carpet area calculation.pdf19 Dec 2022
commencement certificate clarificationFile: commencement certificate clarification.pdf19 Dec 2022
Building LicenceFile: Building Licence.pdf19 Dec 2022
Clarification for parkingFile: Clarification for parking.pdf19 Dec 2022
CDP PlanFile: CDP Plan.pdf19 Dec 2022
Water NOCFile: Water NOC.pdf19 Dec 2022
Structural SaftyFile: Structural Safty.pdf19 Dec 2022
Agreemet for saleFile: Agreemet for sale.pdf19 Dec 2022
AffidavitFile: Affidavit.pdf19 Dec 2022
STP DrawingFile: STP Drawing.pdf19 Dec 2022
Height of the projectFile: Project Height.pdf19 Dec 2022
Clarification that chikka seethappa not signed to supplementary jdaFile: Clarification for Chikka Sithappa not signing the documents.pdf23 Nov 2022
Certified copy obtained by the concerned Sub-registrar regarding value of the property on the basisFile: Sub-registrar Guidance value.pdf23 Nov 2022
Single plot layoutFile: single site.pdf23 Nov 2022
Single plot layout OrderFile: single site Order.pdf23 Nov 2022
KSPCB CFEFile: Sapthagiri Constructions KSPCB CFE.pdf23 Nov 2022
Building LicenseFile: building licence.pdf23 Nov 2022
Otehr Building LicenceFile: building licence Other.pdf23 Nov 2022
Architects certificate with valid Name and signatureFile: Architect Certificate.pdf23 Nov 2022
CDP map showing the proposed siteFile: PLAN.jpg23 Nov 2022
Village map showing the proposed siteFile: VILLAGE MAP.pdf23 Nov 2022
Relinquishment deedFile: relinquish deed.pdf23 Nov 2022
Copy of fee receipt paid towards water supply NOC and BESCOM NOCFile: BESOCM NOC.pdf23 Nov 2022
Certificate from Registered Engineer indicating the structural safety for the proposed buildingFile: Engineer Certificate.pdf23 Nov 2022
Provision of STP in the project is to be clarified by the promoter along with the copy of supportingFile: Sapthagiri Constructions KSPCB CFE.pdf23 Nov 2022
RTC, survey 3/3-
Mutation, survey 3/3-
Encumbrance Certificate, survey 3/3-
Conversion/Alienation Order, survey 3/3-
JDA, survey 3/3-
Khatha, survey 3/3-
RTC, survey 3/5-
Mutation, survey 3/5-
Encumbrance Certificate, survey 3/5-
Conversion/Alienation Order, survey 3/5-
JDA, survey 3/5-
Khatha, survey 3/5-
Registration CertificateFile: Firm Registration Certificate.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA Certificate Form_1 Sapthagiri_compressed.pdf-
Certificate issued by Architect Form 2File: Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No litigation.pdf-
Certificate from Chartered AccountFile: Chartered Accountant Certificate.pdf-
Balance Sheet 2021 - 2022File: Financials.pdf-
Balance Sheet 2020 - 2021File: Financials.pdf-
Balance Sheet 2019 - 2020File: Financials.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Financials.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Financials.pdf-

How this compares with Bengaluru Rural

44%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Sapthagiri Sampadha on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

Builder: Sapthagiri Constructions

SAPTHAGIRI CONSTRUCTIONS has 3 registrations on RERA Karnataka, including Sapthagiri Sampada B Block and Sapthagiri Sampadha. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Sapthagiri Sampadha is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sapthagiri Sampadha?

The registered promoter entity is Sapthagiri Constructions, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sapthagiri Sampadha?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Sapthagiri Sampadha?

The professionals named in the filing: Architect: Tata Vittala Srinivas; Engineer: MANDHADI VENKAT RAMANA REDDY; Chartered Accountant: ANIMIREDDY RAMAKRISHNA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sapthagiri Sampadha?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sapthagiri Sampadha. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sapthagiri Sampadha to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.