Completed No litigation declared Residential / Group Housing project

Sanskruti Building A

By Pushpam Infra LLP

RG-MH-39533 · RERA P52000011794 · Last updated on MahaRERA portal: 5 May 2022

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Stilt Floor, 75%
1Complaints at MahaRERAon this registration
Jump to the 22 documents Report an error

Sanskruti Building A is a Residential / Group Housing project by Pushpam Infra LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000011794 on 31 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2022. The completion date has moved by 42 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSanskruti Building A
  • TypeResidential / Group Housing
  • Location
    • Kashele
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000011794
  • ReraGenie IDRG-MH-39533

Builder

  • NamePushpam Infra LLP
  • Entity typePartnership
  • GSTIN27AAQFP3028F1Z5
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersShrikant Ashok Chopda, Ashok Dagduram Chopda, Sachin Ashok Chopda
  • Other registrations9 more →
  • Completed4 of 10
  • No longer live3 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed22 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sanskruti Building ANA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 75%.

Sanskruti Building A: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor75%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 5 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,860 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Prisha Nova Realty LLPMumbai CityMumbai City

Approvals and building plan

Permissible FSI1860.0
Proposed, not sanctioned1,853 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor 635/1 B New Gajara Society Bibwewadi Pune 411037

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShirish Mulekar
EngineerParag Chopda
PartnerRole in project
Pushpam Infra LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000000870Dec 2018 → Dec 2019

Reason as filed by the promoterNon availability of River Sand...

EXT52000009064Dec 2018 → Dec 2021

Reason as filed by the promoterMany challenges lie ahead for the real estate industry post lockdown and given the situation, it is simpler said than done for many builders. Right from availability of work force, supply of raw material, monitoring workers health at site and more importantly ensuring free flow of funds to execute the work without any hard less are a few issues to name. Even it is impacted on the booking and going very tough to retain the customer during this period. We had facing some cancellation of booked units and due to the block of finance from banking and customer end we are unable to complete the proje

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000199014Pushpam Infra LLPKrishna Mohan Muddu and Radhika M. Muddu12/11/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 May 2022

Documents filed22

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: A Building OC_compressed.pdf5 May 2022
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf14 Jul 2020
Details of Restarting of Construction work post lockdownFile: Scan.pdf20 Jun 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: A Building_compressed.pdf15 Jan 2020
Layout approvalFile: Layout.pdf31 Jul 2017
Building plan approvalFile: A BLDG 1.pdf31 Jul 2017
Building plan approvalFile: A BLDG 2.pdf31 Jul 2017
PAN CardFile: PLLP PAN CARD.pdf31 Jul 2017
Copy of the legal title reportFile: Legal Title report.pdf31 Jul 2017
Details of encumbrancesFile: NO ENCUMBRANCE CERTIFICATE Building A.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf31 Jul 2017
Building Plan Approval (IOD)File: A BLDG 1.pdf31 Jul 2017
Building Plan Approval (IOD)File: A BLDG 2.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: A BLDG NA ORDER 29-6-16.pdf31 Jul 2017
Declaration in FORM BFile: AFFIDAVIT CUM DECLERATION 3 pages-ilovepdf-compressed.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate For A project Final compressed.pdf31 Jul 2017
Certificates of CA (Form 3)File: Building Certificate ca compressed.pdf31 Jul 2017
Proforma of Allotment letterFile: Allotment letter.pdf31 Jul 2017
Proforma of Allotment letterFile: Rera Studio Agreement Copy.pdf31 Jul 2017
Proforma of Allotment letterFile: ANNEXURE 3.pdf31 Jul 2017
Proforma of Allotment letterFile: ANNEXURE 4.pdf31 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 42 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sanskruti Building A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kashele5,900+ in Raigarh

2 kmSanskruti Building ACompleted 2Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Pushpam Infra LLP

Pushpam Infra LLP has 10 registrations on MahaRERA, including Swapna Pushpa and Swapna Pushpa Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Sanskruti Building A is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sanskruti Building A?

The registered promoter entity is Pushpam Infra LLP, a partnership as per the filing. Its GSTIN 27AAQFP3028F1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sanskruti Building A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sanskruti Building A?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sanskruti Building A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sanskruti Building A?

The professionals named in the filing: Architect: Shirish Mulekar; Engineer: Parag Chopda. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sanskruti Building A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sanskruti Building A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sanskruti Building A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.