Home / Browse projects / Aurangabad, Maharashtra / Samarth Pride
Samarth Pride
RG-MH-02727 · RERA P51500045981 · Last updated on MahaRERA portal: 3 Sep 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 11 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Samarth Pride is a Residential / Group Housing project by Samarth Pride in Aurangabad, Maharashtra, registered with MahaRERA as P51500045981 on 15 Jun 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 11 months from the original filing.
At a glance
Project
- NameSamarth Pride
- TypeResidential / Group Housing
- Location
- Jalgaon Road
- Near Visawa Hotel
- Aurangabad (M Corp.)
- Aurangabad
- 431008
- Pincode431008
- RERA no.P51500045981
- ReraGenie IDRG-MH-02727
Builder
- NameSamarth Pride
- Entity typePartnership
- PartnerRaghunath Eknath Autade
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on15 Jun 2022
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Jan 2025)
- Buildings4 building records
- Documents filed59 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 2 | 2 | 0 | 0 | 0 |
| Building B | NA | 2 | 2 | 0 | 0 | 0 |
| Building C | NA | 2 | 2 | 0 | 0 | 0 |
| Building D | NA | 2 | 2 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 3 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 40%.
Building A40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building B40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building C35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 40% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building D37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 3 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Kiran Sunil Dahihande | Sawangi | Aurangabad |
| Jayshree Santosh Dahihande | Sawangi | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DHANANJAY B DOIFODE |
| Engineer | ABHAY S PATIL |
| Chartered Accountant | SHYAMKANT MAHADEVRAO BORDE |
| Chartered Accountant | SUDHAKAR NANA AHER |
| Partner | Role in project |
|---|---|
| Samarth Pride | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) We are facing problem of no booking and delay in collection from customer's. If we force for payment the customers were cancelling bookings. We have applied for bankers but no banker is ready to finance. But with our own capital we have completed at most 80 pct of work as you can confirm from Form 1, 3 uploaded on portal. Now only 20 pct work is balance and in next 8/10 months we will defiantly finish the same. You are kindly requested to extend completion date up to 31/12/2025
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed59
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Arch Form 01 SP38.pdf | 3 Sep 2025 |
| Form 2File: Form02 Eng SP38.pdf | 3 Sep 2025 |
| Form 3File: Form 3 CA SP38.pdf | 3 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Pride Sold unsold.pdf | 3 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch.pdf | 16 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4.pdf | 16 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Samarth Pride.pdf | 16 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCH June 2024.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch June 22.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCH Dec 2024.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCH Sep 2024.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCH March 2024.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch DT Dec 2023.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 01 Arch Sep 2023.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCH June 2023.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCH March 2023.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCH DT Dec 2022.pdf | 3 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCH Sep 2022.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Sep 2023.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Dec 2024.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Sept 2024.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA DT June 2024.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA March 2024.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 CA Dec 2023.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA June 2023.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA March 2023.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Dec 2022.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Sep 2022.pdf | 3 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA June 2022.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer cert June 2022 samarth pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Cert Sep 2022 Samarth pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer cert Dec 2022 samarth pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 engineer cert March 2023 Samarth pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 engineer cert June 2023 Samarth pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Cert Sept 2023 Samarth pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer cert Dec 2023 Samarth pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer cert March 2024 samarth pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer cert June 2024 Samarth Pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer cert Sept 2024 samarth pride.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 engineer cert Dec 2024 Samarth pride.pdf | 3 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Samarth Pride.pdf | 15 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Form 3pdf (1).pdf | 4 Jun 2022 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER format.pdf | 4 Jun 2022 |
| Copy of the legal title reportFile: NEW SEARCH REPORT.pdf | 18 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order Collector SP38 Sawangi.pdf | 18 May 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200237241540_For_Asset_Based_Search_12_05_2022_19_12_49_853.pdf | 18 May 2022 |
| Layout approvalFile: Final Layout SP38 Sawangi 0.pdf | 12 May 2022 |
| Building plan approvalFile: A AND B BUILDING PLAN.pdf | 12 May 2022 |
| Building plan approvalFile: C TYPE BUILDING PLAN.pdf | 12 May 2022 |
| Building plan approvalFile: D TYPE BUILDING PLAN.pdf | 12 May 2022 |
| PAN CardFile: pan samarth pride.pdf | 12 May 2022 |
| Details of encumbrancesFile: Non-Encumbrance Certificate.pdf | 12 May 2022 |
| Copy of Layout Approval (in case of layout)File: Final Layout SP38 Sawangi 0.pdf | 12 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: A AND B BUILDING PLAN.pdf | 12 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: C TYPE BUILDING PLAN.pdf | 12 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: D TYPE BUILDING PLAN.pdf | 12 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Building Permision.pdf | 12 May 2022 |
| Declaration about Commencement CertificateFile: Format-D.pdf | 12 May 2022 |
| Declaration in FORM BFile: Form B Dinesh Salunkhe Developers 0.pdf | 12 May 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 59 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Samarth Pride on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Visawa Hotel1,400+ in Aurangabad
SARA NIWARA
Sara Infrastructures
Sawangi City Phase-2
Aryaman Infra
JANKI HEIGHTS
SHREE BALAJI BUILDCON
Rajgad- Swaraj Nagar
M S M Infra
Swapna Srushti 1
M/s Nisha Associates
KISAN PARK
KALYANRAO KISANRAO AUTADE
See every Aurangabad project, with the district possession charts
Builder: Samarth Pride
Samarth Pride has 1 registration on MahaRERA, including Samarth Pride. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What does it mean that Samarth Pride shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Samarth Pride is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Samarth Pride?
The registered promoter entity is Samarth Pride, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Samarth Pride?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Samarth Pride?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Samarth Pride?
The professionals named in the filing: Architect: DHANANJAY B DOIFODE; Engineer: ABHAY S PATIL; Chartered Accountant: SHYAMKANT MAHADEVRAO BORDE; Chartered Accountant: SUDHAKAR NANA AHER. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Samarth Pride?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback