Home / Browse projects / Pune, Maharashtra / SAIPLAZA

Registration lapsed No litigation declared Commercial project

SAIPLAZA

By AGASTI DEVELOPERS

RG-MH-62955 · RERA P52100018259 · Last updated on MahaRERA portal: 18 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 69 months
  • 5 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

SAIPLAZA is a Commercial project by AGASTI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100018259 on 22 Oct 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 69 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSAIPLAZA
  • TypeCommercial
  • Location
    • Pune Nashik Highway
    • Rajgurunagar
    • Rajgurunagar (CT)
    • Khed
    • Pune
    • 410505
  • Pincode410505
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018259
  • ReraGenie IDRG-MH-62955

Builder

  • NameAGASTI DEVELOPERS
  • Entity typePartnership
  • GSTIN27ABEFA1859L1Z6
  • PartnersLAXMIKANT AMBADAS NAIKWADI, SONALI LAXMIKANT NAIKWADI, ATUL GULABRAO TAMBE

Key dates

10 months past promisethis monthRegisteredOct 2018First promiseMar 2020Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Oct 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Mar 2020)
  • Buildings1 building record
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAIPLAZANA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

SAIPLAZA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed144

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots144
Closed/Covered1
Open Space143

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
AGASTI DEVELOPERSAkolaAhmednagar

Approvals and building plan

Permissible FSI3456.0
Proposed, not sanctioned3,014 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAKOLE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLAXMIKANT NAIKWADI
EngineerVijay Ranade
Chartered AccountantVikas Naikwadi
PartnerRole in project
AGASTI DEVELOPERS-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011631Mar 2020 → Mar 2024

Reason as filed by the promoterConstruction of the project is almost completed and we have already applied for part completion certificate but due to some RTI applications and transfer of concerns officials , completion certificate is getting delayed. As we do not want to apply for further extension we are applying for one time for 10 months extension for the last time. Reasons of the same are explained in detail in the attachment uploaded in Other Tab.

EXT52100019604Mar 2020 → Dec 2024

Reason as filed by the promoterDear Authority, We have already completed the construction part and have applied for occupancy certificate but same is pending due to "Mojani Notice" from Bhumi Abhilesh Vibhag, Maharashtra Shasan. One of the citizen had made a complain and had demanded the Mojani, There were multiple applications made under RTI act and this resulted into to delay in processing of application of completion certificate. We request authority to check the details submitted in our last extension request, and we humbly state that the construction part is already done. We are requesting respective authorities to pro

EXT52100006017Mar 2020 → Mar 2021

Reason as filed by the promoterNo of days Mansoon stayed in West Maharasthra in FY 2019-20 were quite large as compared to average days. This resulted into delay in construction progress. No of permissions and sanctions were required to be obtained at different stages of construction from different Government authorities. But as there were Central and State Elections in last year, sanctioning authorities were occupied with other responsibilities also. We started our project activities with faster pace but due to unfortunate Corona Virus (nCOVID 9) epidemic number of contractors went to their native places. As we are not sur

EXT52100025920Mar 2020 → Mar 2025

Reason as filed by the promoterWe hereby submit this request to kindly grant an extension of three months for the completion timeline of our project [Project Name] registered under RERA with Registration No. P52100018259 Reason for Extension Request: 1. Engagement in Maharashtra State Elections: o Our CEO and key team members were actively engaged and occupied during the Maharashtra State Elections. This included responsibilities that limited their ability to oversee the timely completion of the documentation process. o Additionally, the implementation of the Model Code of Conduct (Acharsanhita) during this period further r

EXT52100027816Mar 2020 → Dec 2025

Reason as filed by the promoterWe had applied for extension up to 31/12/2025 in previous application in FORM B but at the time of filing the online application we had selected 31/03/2025 as the extension date by mistake. We hereby request the authority to consider the application once again and grant the extension up to 31/12/2025. Thank you.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000340734Mr. Mahesh Kashinath DeshmukhM/s. Agasti Developers Through its partner Mr. Lakshmikant Ambadas Naikwadi07/04/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Jan 2023

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Declaration in Form B Format - Promoter.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-D.pdf18 Mar 2025
Certificates of CA (Form 3)File: FORM 3_CA.pdf18 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_D.pdf18 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory_D.pdf18 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_D.pdf18 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_D.pdf18 Mar 2025
Declaration in FORM BFile: FORM B.pdf27 Feb 2025
Declaration in FORM BFile: Declaration in Form B Format - Promoter.pdf27 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf27 Feb 2025
Certificates of CA (Form 3)File: FORM 3_CA.pdf27 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf27 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf27 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf27 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf27 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf27 Feb 2025
Declaration in FORM BFile: FORM B.pdf31 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3_CA_.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2A.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold_Booked_Unsold Inventory.pdf31 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf31 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_CA.pdf31 Jan 2025
Declaration in FORM BFile: FORMAT-B.pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold_Booked_Unsold Inventory.pdf16 Jan 2025
Declaration in FORM BFile: Declaration in Form B Format - Promoter.pdf1 Jun 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf1 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf24 May 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY.pdf24 May 2023
Certificates of CA (Form 3)File: Form 3.pdf24 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf24 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest Declaration.pdf12 Jan 2023
Proforma of Agreement for saleFile: Proforma Agrrement of Sale.pdf12 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate by Architect.pdf12 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Details.pdf12 Jan 2023
Deviation Report with respect to Allotment letterFile: Deviation Statement.pdf12 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Statement.pdf12 Jan 2023
Details of encumbrances concerned to FinanceFile: 1 Commencement Certificates _ NA Order for plotted development.pdf5 Jan 2023
Details of encumbrances concerned to LegalFile: 1 Commencement Certificates _ NA Order for plotted development.pdf5 Jan 2023
Declaration about Commencement CertificateFile: 1 Commencement Certificates _ NA Order for plotted development.pdf5 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Commencement Certificate.pdf5 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate.pdf5 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Eng Certificate Quality.pdf5 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Eng Certificate Quality.pdf5 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Eng Certificate Quality.pdf5 Jan 2023
Disclosure of sold/ booked inventoryFile: Booked Inventory.pdf5 Jan 2023
CERSAI detailsFile: CERSAI Declaration.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 Annual Statement of Accountant.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Annual Statement of Accountant.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Annual Statement of Accountant.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Annual Statement of Accountant.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Annual Statement of Accountant.pdf5 Jan 2023
Building plan approvalFile: PLAN-1.pdf13 Oct 2018
Building plan approvalFile: PLAN-2.pdf13 Oct 2018
Layout approvalFile: PLAN-1.pdf13 Oct 2018
Layout approvalFile: PLAN-2.pdf13 Oct 2018
PAN CardFile: PAN CARD PDF.pdf13 Oct 2018
Copy of the legal title reportFile: SEARCH AND TITLE REPORT.pdf13 Oct 2018
Details of encumbrancesFile: ENCUMBEREANCE CERTFICATE.pdf13 Oct 2018
Copy of Layout Approval (in case of layout)File: PLAN-1.pdf13 Oct 2018
Copy of Layout Approval (in case of layout)File: PLAN-2.pdf13 Oct 2018
Building Plan Approval (IOD)File: PLAN-1.pdf13 Oct 2018
Building Plan Approval (IOD)File: PLAN-2.pdf13 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CUM SANCTION LETTER.pdf13 Oct 2018
Declaration in FORM BFile: FORM B ARCHITECT CERTFICATE.pdf13 Oct 2018
Certificates of CA (Form 3)File: CA CERTIFICATE FORM 3.pdf13 Oct 2018
Proforma of Allotment letterFile: AGREEMENT TO SALE.pdf13 Oct 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 69 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAIPLAZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rajgurunagar13,700+ in Pune

2 kmSAIPLAZACompleted 163Lapsed / revoked 118Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: AGASTI DEVELOPERS

AGASTI DEVELOPERS has 1 registration on MahaRERA, including SAIPLAZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SAIPLAZA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAIPLAZA is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAIPLAZA?

The registered promoter entity is AGASTI DEVELOPERS, a partnership as per the filing. Its GSTIN 27ABEFA1859L1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAIPLAZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAIPLAZA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAIPLAZA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAIPLAZA?

The professionals named in the filing: Architect: LAXMIKANT NAIKWADI; Engineer: Vijay Ranade; Chartered Accountant: Vikas Naikwadi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAIPLAZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAIPLAZA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAIPLAZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.