ReraGenieLog inGet a buyer report

Home / Browse projects / Ahmednagar, Maharashtra / SAIKRUPA ROW BUNGLOW PHASE 3

Completed No litigation declared Residential / Group Housing project

SAIKRUPA ROW BUNGLOW PHASE 3

By PUSHPA JAYSING MHASKE

RG-MH-08827 · RERA P52200011932 · Last updated on MahaRERA portal: 6 Aug 2018

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.
Aug 2018Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 60%
0Complaints at MahaRERAon this registration
Jump to the 19 documents Report an error

SAIKRUPA ROW BUNGLOW PHASE 3 is a Residential / Group Housing project by PUSHPA JAYSING MHASKE in Ahmednagar, Maharashtra, registered with MahaRERA as P52200011932 on 1 Sep 2017. The registration is recorded completed; possession was promised by 31 Aug 2018.

At a glance

Project

  • NameSAIKRUPA ROW BUNGLOW PHASE 3
  • TypeResidential / Group Housing
  • Location
    • NEAR NEPTI ROAD
    • RADHA KRISHNA COLONY
    • KEDGAON
    • Ahmadnagar (M Corp.)
    • Nagar
    • Ahmednagar
    • 414005
  • Pincode414005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52200011932
  • ReraGenie IDRG-MH-08827

Builder

  • NamePUSHPA JAYSING MHASKE
  • Entity typeIndividual

Key dates

this monthRegisteredSep 2017PromisedAug 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Sep 2017
  • Promised completion31 Aug 2018
  • Revised completionNone
  • Buildings1 building record
  • Documents filed19 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAIKRUPA ROW BUNGLOW PHASE 3NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Aug 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 60%.

SAIKRUPA ROW BUNGLOW PHASE 3: 49% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Aug 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Open Space12

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area770 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI811.04
Proposed, not sanctioned811 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAMBAR PLAZA, STATION ROAD AHMEDNAGAR

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHWINI B HATWAKAR
EngineerUTTARESHWAR KALE
PartnerRole in project
PUSHPA JAYSING MHASKE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Aug 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed19

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificates / NA Order for plotted developmentFile: SaiKrupa Plan.pdf6 Aug 2018
Certificates of CA (Form 3)File: FORM 3 NEW.pdf6 Aug 2018
Certificates of CA (Form 3)File: FORM 3 NEW.pdf6 Aug 2018
Certificates of CA (Form 5)File: form 5.pdf6 Aug 2018
Certificates of Architect (Form 4)File: ARCHITECTS CERT.pdf6 Aug 2018
Certificates of Architect (Form 4)File: FORM 4.pdf6 Aug 2018
OtherFile: SAIKRUPA COMPLETION.pdf6 Aug 2018
Layout approvalFile: LAYOUT.PDF30 Aug 2017
Building plan approvalFile: SaiKrupa Plan.pdf30 Aug 2017
PAN CardFile: pan_pushpa mahske.pdf30 Aug 2017
Copy of the legal title reportFile: Serch Report.pdf30 Aug 2017
Details of encumbrancesFile: ENCUMBRANCES.pdf30 Aug 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.PDF30 Aug 2017
Building Plan Approval (IOD)File: SaiKrupa Plan.pdf30 Aug 2017
Declaration in FORM BFile: FORM B.pdf30 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architects ceritificate sai krupa.pdf30 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg ceritificate sai krupa.pdf30 Aug 2017
Certificates of CA (Form 3)File: form3 sai krupa007.pdf30 Aug 2017
Proforma of Allotment letterFile: agreement for sale.pdf30 Aug 2017

How this compares with Ahmednagar

7%of Ahmednagar projects moved their completion datethis one has not
28%of Ahmednagar registrations have lapsed or been cancelledthis one is completed

Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.

Keep SAIKRUPA ROW BUNGLOW PHASE 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KEDGAON490+ in Ahmednagar

Builder: PUSHPA JAYSING MHASKE

PUSHPA JAYSING MHASKE has 1 registration on MahaRERA, including SAIKRUPA ROW BUNGLOW PHASE 3. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ahmednagar district page.

Frequently asked questions

What are my rights if SAIKRUPA ROW BUNGLOW PHASE 3 is delayed beyond 31 Aug 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAIKRUPA ROW BUNGLOW PHASE 3?

The registered promoter entity is PUSHPA JAYSING MHASKE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAIKRUPA ROW BUNGLOW PHASE 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAIKRUPA ROW BUNGLOW PHASE 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAIKRUPA ROW BUNGLOW PHASE 3?

The professionals named in the filing: Architect: ASHWINI B HATWAKAR; Engineer: UTTARESHWAR KALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAIKRUPA ROW BUNGLOW PHASE 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAIKRUPA ROW BUNGLOW PHASE 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAIKRUPA ROW BUNGLOW PHASE 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.