ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Sai Paradise

Registration lapsed No litigation declared Residential / Group Housing project

Sai Paradise

By SJ Construction

RG-MH-63184 · RERA P52100018848 · Last updated on MahaRERA portal: 4 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
18 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 119 documents Report an error

Sai Paradise is a Residential / Group Housing project by SJ Construction in Pune, Maharashtra, registered with MahaRERA as P52100018848 on 6 Dec 2018. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSai Paradise
  • TypeResidential / Group Housing
  • Location
    • Lingali
    • Daund
    • Pune
    • 413801
  • Pincode413801
  • RERA no.P52100018848
  • ReraGenie IDRG-MH-63184

Builder

  • NameSJ Construction
  • Entity typePartnership
  • PartnersSushant Jawak, Shrikant Jawak

Key dates

10 months past promisethis monthRegisteredDec 2018First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Dec 2018
  • Promised completion30 Dec 2025
  • Revised completionRevised to 30 Dec 2025 (originally 30 Dec 2024)
  • Buildings2 building records
  • Documents filed119 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sai Paradise ANA40000
Sai Paradise BNA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

Sai Paradise A82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Sai Paradise B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,500 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Harishchandra Malhari JagdaleLingaliPune

Approvals and building plan

Permissible FSI1405.48
Proposed, not sanctioned1,405 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAhmednagar

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
SJ Construction-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025915Dec 2024 → Dec 2025

Reason as filed by the promoterThe plan will be revised in the future, so we need more time. Therefore, we request an extension until 30th December 2025.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Dec 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 May 2025

Documents filed119

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: daund compilation certificate .pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 060425.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 060425.pdf15 Apr 2025
Certificates of CA (Form 3)File: Form3 220125_compressed.pdf15 Apr 2025
Certificates of CA (Form 3)File: Form 3 100425_compressed.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 040425.pdf15 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure_March 25.pdf15 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4 Form 2A_22-23.pdf15 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 4 Form 2A_23-24.pdf15 Apr 2025
Declaration in FORM BFile: Form B_.pdf28 Mar 2025
Declaration about Commencement CertificateFile: Form D.pdf28 Mar 2025
CERSAI detailsFile: CERSEI Report.pdf28 Mar 2025
Other - TechnicalFile: Certificate of work progress.pdf28 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf28 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured unsecured.pdf28 Mar 2025
Disclosure of sold/ booked inventoryFile: A,b,c sold inventory .pdf12 Mar 2025
Declaration about Commencement CertificateFile: Format D.pdf12 Mar 2025
Form 2AFile: Form 2 A 2023.pdf27 Dec 2024
Form 2AFile: Form 2A 2024.pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-4-19.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-1-19.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Oct 2024.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: July 2024.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A 7jan24.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A 6apr24.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-10-23.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-7-23.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-4-23.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-1-23.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-10-22.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-7-22.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4-4-22.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-1-21.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4-10-21.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4-7-21.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4-4-21.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-10-20.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-7-20.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-4-20.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-1-20.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-10-19.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7-7-19.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4-1-22.pdf25 Dec 2024
Certificates of CA (Form 3)File: Form3_30092024.pdf25 Dec 2024
Certificates of CA (Form 3)File: Form3_30062024.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E 41024.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E 5124.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E 4724.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: E 4424.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 51023.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 050723.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 050423.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 050123.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2012022.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 050122.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 020722.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 020422.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 030121.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 03721.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02121.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05oct20.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05jul20.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05jan20.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05apr2020.pdf25 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: plinth completions certificate.pdf25 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: daund compilation certificate .pdf25 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-FY 23-24.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05 apr 19.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 05 oct19.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5july19.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 Jan 2019.pdf19 Dec 2024
Certificates of CA (Form 3)File: Form3_30062023.pdf1 Jul 2024
Certificates of CA (Form 3)File: Form3_30092023.pdf1 Jul 2024
Certificates of CA (Form 3)File: Form3_31122023.pdf1 Jul 2024
Certificates of CA (Form 3)File: Form3_31032024.pdf1 Jul 2024
Certificates of CA (Form 3)File: form 3 July 2022.pdf13 Dec 2023
Certificates of CA (Form 3)File: form 3 - Oct 2022.pdf13 Dec 2023
Certificates of CA (Form 3)File: form 3 -Jan 2023_compressed.pdf13 Dec 2023
Certificates of CA (Form 3)File: form 3 -April 2023_compressed.pdf13 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 2023.pdf13 Dec 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sai Paradise on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lingali13,700+ in Pune

Builder: SJ Construction

SJ Construction has 1 registration on MahaRERA, including Sai Paradise. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Sai Paradise shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sai Paradise is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sai Paradise?

The registered promoter entity is SJ Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sai Paradise?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sai Paradise?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Sai Paradise?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sai Paradise. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sai Paradise to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.