Home / Browse projects / Raigarh, Maharashtra / SAI KRUPA

Registered Litigation declared Residential / Group Housing project

SAI KRUPA

By K T REALTY

RG-MH-28807 · RERA P52000027073 · Last updated on MahaRERA portal: 3 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 35 months
  • 2 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Sep 2027Possession promisedmoved 35 months from the original
7 of 11Construction stages donefurthest along: Staircases, 99%
1 of 68Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

SAI KRUPA is a Residential / Group Housing project by K T REALTY in Raigarh, Maharashtra, registered with MahaRERA as P52000027073 on 13 Nov 2020. Possession is promised by 30 Sep 2027. The completion date has moved by 35 months from the original filing. 67 of the 68 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSAI KRUPA
  • TypeResidential / Group Housing
  • Location
    • PLOT NO 3 SECTOR 6
    • NAVIMUMBAI
    • Kamothe
    • Panvel
    • Raigarh
    • 410209
  • Pincode410209
  • RERA no.P52000027073
  • ReraGenie IDRG-MH-28807

Builder

  • NameK T REALTY
  • Entity typePartnership
  • PartnersDHIARJ VIJAYKUMAR CHAWLA, RAJESHKUMAR MULCHAND CHAVALA, HITESH DILIPBHAI VADHVANI, RONAK ASHOKKUMAR CHAWLA, VINODKUMAR MULCHAND CHAVALA
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2020First promiseOct 2024Revised toSep 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on13 Nov 2020
  • Promised completion30 Sep 2027
  • Revised completionRevised to 30 Sep 2027 (originally 1 Oct 2024)
  • Buildings1 building record
  • Documents filed69 files

Current status

99%67 of 68 units booked
100.0%Work done, per cost certificate

Figures as on 3 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI KRUPANA9763568

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 99%.

SAI KRUPA: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered8
Open Space10

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,073 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Aug 2025

Approvals and building plan

Sanctioning authoritykalyan dombivali municipal corporation
Permissible FSI1607.91
Proposed, not sanctioned1,608 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP 38 AND 39 PATEL HERITAGE PLOT NO 15 TO 17,SECTOR 07,KHARGHAR 410210
Estimated costRs 5.90 cr
Cost incurredRs 5.90 cr
Work done100.0%
BuildingWingEstimatedIncurred
SAI KRUPANARs 5.43 crRs 5.43 cr
-NARs 47.20 lakhRs 47.20 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATUL PATEL ARCHITECTS
EngineerS R CONSULTANTS
EngineerBIPIN MAURYA
Chartered AccountantSWATI SUDHENDU PATEL
Chartered AccountantBHAVIK JAYANTILAL VELANI
Chartered AccountantPIYUSH GHATLIYA & COMPANY
PartnerRole in project
K T REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000024727Oct 2024 → Sep 2025

Reason as filed by the promoterExplanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of SAI KRUPA’ - As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 01/10/2024 as the project completion date, we will not be able to complete the project due to various unavoidable reasons. Such as 1) After the impact of the pandemic, the increasing prices of the con

EA25082502434Oct 2024 → Sep 2027

Reason as filed by the promoterShortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized trades. The COVID-19 pandemic has resulted in the migration of a large proportion of the labor force, particularly migrant workers, back to their native regions due to lockdowns, health concerns, and other social and economic factors. As a consequence, a substantial number of workers previously engaged on-site have been unable to return, thereby halting criti

Litigation declared2

CaseCourtStatus
156/2022/2022Civil court senior divi PanvelAwaiting Notice
MHRG170010802023/2023DISTRICT COURT RAIGARHClosed

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000231216VINOD KRISHNA SHELKEk t realty27/05/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2027

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A_ MAR 25_KT REALTY.pdf3 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A_ MAR 26_KT REALTY.pdf3 Aug 2026
Withdrawal Update Form 1File: FORM 1_ MARCH 26_ SAI KRUPA.pdf24 Apr 2026
Withdrawal Update Form 2File: FORM 2_ MARCH 26_ SAI KRUPA.pdf24 Apr 2026
Withdrawal Update Form 3File: FORM 3_ MARCH 26_ SAI KRUPA.pdf24 Apr 2026
Withdrawal Update Form 1File: FORM 1_SEP 25_SAI KRUPA.pdf19 Jan 2026
Withdrawal Update Form 1File: FORM 1_DEC 25_SAI KRUPA.pdf19 Jan 2026
Withdrawal Update Form 2File: FORM 2_SEP 25_SAI KRUPA.pdf19 Jan 2026
Withdrawal Update Form 2File: FORM 2_DEC 25_SAI KRUPA.pdf19 Jan 2026
Withdrawal Update Form 3File: FORM 3_SEP 25_SAI KRUPA.pdf19 Jan 2026
Withdrawal Update Form 3File: FORM 3_DEC 25_SAI KRUPA.pdf19 Jan 2026
Building plan approvalFile: BUILDING PLAN.pdf25 Nov 2025
Form 5 (FY 2024-2025)File: Scan Form-5 Uploded.pdf13 Nov 2025
Form 1File: FORM 1_ SEP & DEC 24_ SAI KRUPA.pdf21 Aug 2025
Form 2File: FORM 2_ SEP & DEC 24_ SAI KRUPA.pdf21 Aug 2025
Form 3File: FORM 3_ SEP & DEC 24_ SAI KRUPA.pdf21 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ SEP & DEC 24_SAI KRUPA.pdf21 Aug 2025
Form 1File: FORM 1_ MARCH 25_ SAI KRUPA_ KT GROUP.pdf21 Aug 2025
Form 2File: FORM 2_ MARCH 25_ SAI KRUPA_ KT GROUP.pdf21 Aug 2025
Form 3File: FORM 3_ MARCH 25_ SAI KRUPA_ KT GROUP.pdf21 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ MARCH 25_ SAI KRUPA_ KT GROUP.pdf21 Aug 2025
Withdrawal Update Form 1File: FORM 1_ JUNE 25_ SAI KRUPA_ KT GROUP.pdf21 Aug 2025
Withdrawal Update Form 2File: FORM 2_ JUNE 25_ SAI KRUPA_ KT GROUP.pdf21 Aug 2025
Withdrawal Update Form 3File: FORM 3_ JUNE 25_ SAI KRUPA_ KT GROUP.pdf21 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_ DEC 24.pdf19 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_ DEC 24_compressed (2).pdf19 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ DEC 24.pdf19 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ DEC 24.pdf19 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A FY 2021-22.pdf11 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A FY 2022-23.pdf11 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A FY 2023-24.pdf11 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A FY 2021-22.pdf11 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A FY 2022-23.pdf11 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A FY 2023-24.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1_ SEP 24.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2_ SEP 24.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3_ SEP 24.pdf10 Oct 2024
Disclosure of sold/ booked inventoryFile: 4 SOLD UNSOLD_ SEP 24.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 5 FORM 5_ MARCH 24.pdf10 Oct 2024
Declaration in FORM BFile: FORM B .pdf10 Oct 2024
Declaration in FORM BFile: FORM B .pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1_ SEP 24.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3_ SEP 24.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2_ SEP 24.pdf10 Oct 2024
Disclosure of sold/ booked inventoryFile: 4 SOLD UNSOLD_ SEP 24.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 5 FORM 5_ MARCH 24.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: KT REALTY 3 -SAI KRUPA FROM 5.pdf11 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SAI KRUPA PLOT 03.pdf14 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 9 K T R Pro-Sai Krupa F-5.pdf26 Apr 2022
Declaration about Commencement CertificateFile: SELF DEC 3 6 KAMOTHE.pdf17 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: sai krupa 14 06 21 F Y 20 21.pdf17 Aug 2021
PAN CardFile: K T REALTY PAN.pdf11 Nov 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA form 1.pdf11 Nov 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINER CERTIFICATE FORM 2.pdf10 Nov 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINER CERTIFICATE TABLE A.pdf10 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca patel form 3.pdf10 Nov 2020
Proforma of Allotment letterFile: Sai Krupa alootment.pdf10 Nov 2020
Copy of the legal title reportFile: TITLE CLERANCE CERTIFICATE (2).pdf7 Nov 2020
Copy of the legal title reportFile: SERCH REPORT.pdf7 Nov 2020
Details of encumbrancesFile: Image (19).pdf7 Nov 2020
Declaration in FORM BFile: PAGE 1-converted.pdf7 Nov 2020
Proforma of Allotment letterFile: KT REALTY 2.pdf7 Nov 2020
Building plan approvalFile: plan 1.pdf3 Nov 2020
Building plan approvalFile: plan 2.pdf3 Nov 2020
Layout approvalFile: plan 3.pdf3 Nov 2020
Copy of Layout Approval (in case of layout)File: plan 3.pdf3 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: plan 1.pdf3 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: plan 2.pdf3 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf3 Nov 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SAI VRINDAVANPLOT 33 SECTOR 9 KOPERKHAIRANE NAVIMUMBAI50CompletedOct 2022Oct 2022

How this compares with Raigarh

99%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 35 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI KRUPA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NAVIMUMBAI5,900+ in Raigarh

Builder: K T REALTY

K T REALTY has 3 registrations on MahaRERA, including SAI VRINDAVAN and SAI KUTIR. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SAI KRUPA is delayed beyond 30 Sep 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI KRUPA?

The registered promoter entity is K T REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI KRUPA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAI KRUPA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAI KRUPA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI KRUPA?

The professionals named in the filing: Architect: ATUL PATEL ARCHITECTS; Engineer: S R CONSULTANTS; Engineer: BIPIN MAURYA; Chartered Accountant: SWATI SUDHENDU PATEL; Chartered Accountant: BHAVIK JAYANTILAL VELANI; Chartered Accountant: PIYUSH GHATLIYA & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI KRUPA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI KRUPA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI KRUPA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.