Sai Empire - Plot B
RG-MH-23661 · RERA P52100078973 · Last updated on MahaRERA portal: 2 Nov 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sai Empire - Plot B is a Plotted project by M/s Sai Angan Projects LLP in Pune, Maharashtra, registered with MahaRERA as P52100078973 on 24 Jan 2025. Possession was promised by 31 Dec 2025 and is now 10 months past that date.
At a glance
Project
- NameSai Empire - Plot B
- TypePlotted
- Location
- Wadmukhwadi
- Haveli
- Pune
- 412105
- Pincode412105
- RERA no.P52100078973
- ReraGenie IDRG-MH-23661
Builder
- NameM/s Sai Angan Projects LLP
- Entity typeOthers
- Named personsASHOK MADHUBHAI MALVIYA, MUKESH SOHANRAJ JAIN, MARUTI GULAB SHINDE, NILESH HIRAMAN BARNE, SOMNATH MAKARDHWAJ DOUNDKAR
- Other registrations3 more →
- Completed2 of 4
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 Jan 2025
- Promised completion31 Dec 2025
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed46 files
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Progress on shared amenities15
As on 2 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | M s Patil and Bugade Associates |
| Engineer | Rutuja Jagdale |
| Chartered Accountant | CA Shakti Soni and Associates |
| Partner | Role in project |
|---|---|
| M/s Sai Angan Projects LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Nov 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Nov 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed46
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Empire B.pdf | 2 Nov 2025 |
| Form 2File: Form 2-B.pdf | 2 Nov 2025 |
| Form 3File: CA certificate-Empire B.pdf | 2 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold- Empire B.pdf | 2 Nov 2025 |
| Form 1File: Empire B.pdf | 23 Jul 2025 |
| Form 2File: Form 2- Sai Empire Plot B.pdf | 23 Jul 2025 |
| Form 3File: Sai Angan Project Plot B.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold- Empire B.pdf | 23 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf | 21 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sai Angan Projects (Plot B)_rotated (1)_compressed.pdf | 21 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Sai EMpire B.pdf | 21 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold -B.pdf | 21 Apr 2025 |
| Other - FinanceFile: 2 Commencement Certificates _ NA Order for plotted development (7).pdf | 2 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Mail-Plot B.pdf | 25 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 2 Disclosure of Interest in Other Real Estate Organizations (4) (1).pdf | 25 Nov 2024 |
| Building plan approval or NA orderFile: SAI EMPIRE - B-2_compressed.pdf | 12 Nov 2024 |
| Layout approvalFile: SAI EMPIRE - B-2_compressed.pdf | 12 Nov 2024 |
| PAN CardFile: 1 PAN Card (5).pdf | 12 Nov 2024 |
| Copy of the legal title reportFile: 1 Copy of the legal title report (25)-1-3 (1).pdf | 12 Nov 2024 |
| Copy of the legal title reportFile: SEARCH - SAI EMPIRE - B_compressed.pdf | 12 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCES (2).pdf | 12 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: SAI EMPIRE - B-2_compressed.pdf | 12 Nov 2024 |
| Proforma of Allotment letterFile: Model form of AL-Plot B.pdf | 12 Nov 2024 |
| Declaration in FORM BFile: Form B, Sai Empire - B_compressed.pdf | 12 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf | 12 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost Fund withdrawal (Form 3) (50) (1).pdf | 12 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Plot B.pdf | 12 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: साई आंगण प्रोजेक्ट एल एल पी NA Order (1).pdf | 12 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: SAI EMPIRE - B-2_compressed.pdf | 12 Nov 2024 |
| Other - LegalFile: 16829- Project - B_compressed-35-54.pdf | 12 Nov 2024 |
| Other - LegalFile: 16829- Project - B_compressed-1-17.pdf | 12 Nov 2024 |
| Other - LegalFile: 16829- Project - B_compressed-18-34.pdf | 12 Nov 2024 |
| Declaration about Commencement CertificateFile: Format D-Plot B-1.pdf | 12 Nov 2024 |
| CERSAI detailsFile: DECLARATION - CERSAI.pdf | 12 Nov 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT - A .pdf | 12 Nov 2024 |
| Deviation Report with respect to Allotment letterFile: DEVIATION ALLOTMENT.pdf | 12 Nov 2024 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCES (2).pdf | 12 Nov 2024 |
| Other - TechnicalFile: ANNEXURE - A.pdf | 12 Nov 2024 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION - Agreement to sale.pdf | 12 Nov 2024 |
| Proforma of Agreement for saleFile: AFS- Plot B.pdf | 12 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations (8) (1).pdf | 12 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 2 Disclosure of Interest in Other Real Estate Organizations (4) (1).pdf | 12 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 3 Disclosure of Interest in Other Real Estate Organizations (4) (1).pdf | 12 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 4 Disclosure of Interest in Other Real Estate Organizations (3) (1).pdf | 12 Nov 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B- Bank- Plot B.pdf | 12 Nov 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Secured loan-Plot B.pdf | 12 Nov 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations, which the RERA portal never shows together
- All 46 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Sai Empire - Plot B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Wadmukhwadi13,700+ in Pune
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: M/s Sai Angan Projects LLP
M/s Sai Angan Projects LLP has 4 registrations on MahaRERA, including Sai Empire G and Sai Empire J. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Sai Empire - Plot B shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Sai Empire - Plot B is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sai Empire - Plot B?
The registered promoter entity is M/s Sai Angan Projects LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sai Empire - Plot B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Sai Empire - Plot B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sai Empire - Plot B?
The professionals named in the filing: Architect: M s Patil and Bugade Associates; Engineer: Rutuja Jagdale; Chartered Accountant: CA Shakti Soni and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sai Empire - Plot B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.