ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SAI CHAITANYA RIVERDALE

Registration lapsed No litigation declared Plotted project

SAI CHAITANYA RIVERDALE

By M/s Sai Chaitanya Riverdale llp

RG-MH-18467 · RERA P52100077324 · Last updated on MahaRERA portal: 29 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
13 of 13Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 46 documents Report an error

SAI CHAITANYA RIVERDALE is a Plotted project by M/s Sai Chaitanya Riverdale llp in Pune, Maharashtra, registered with MahaRERA as P52100077324 on 6 Aug 2024. Possession was promised by 30 Jun 2025 and is now 16 months past that date. 0 of the 13 units on this registration are recorded sold or booked.

At a glance

Project

  • NameSAI CHAITANYA RIVERDALE
  • TypePlotted
  • Location
    • Dudulgaon
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100077324
  • ReraGenie IDRG-MH-18467

Builder

  • NameM/s Sai Chaitanya Riverdale llp
  • Entity typeOthers
  • Named personsM/s Trikaya Buildcorp LLP, Mr Atul Nathu Shinde, Mr Sachin Subhash Kadam, ABN Life Spaces LLP
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredAug 2024PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Aug 2024
  • Promised completion30 Jun 2025
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed46 files

Current status

0%0 of 13 units booked
69.5%Work done, per cost certificate

Figures as on 29 Oct 2025, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 29 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,342 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Aug 2025

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Uttam Complex, Plot NoGp 75, GBlock, Midc, Thermax Chowk, Pune, Maharashtra.411019
Estimated costRs 45.89 lakh
Cost incurredRs 31.90 lakh
Work done69.51%
BuildingWingEstimatedIncurred
-NARs 45.89 lakhRs 31.90 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMs Patil and Bugade Associates
EngineerRutuja Jagdale
Chartered AccountantCA J S Desai and Co
PartnerRole in project
M/s Sai Chaitanya Riverdale llp-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jul 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed46

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Cert - Sai Chaitanya - F (1).pdf29 Oct 2025
Withdrawal Update Form 2File: Form 2- Plot F.pdf29 Oct 2025
Withdrawal Update Form 3File: Final Form 3- Plot F_compressed.pdf29 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert - Sai Chaitanya - F (1).pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sai Chaitanya Riverdale LLp (plot F)_rotated (1)_compressed.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Plot F.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold- Plot F Sai Chaiatnya.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert - Sai Chaitanya - F (1).pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SAI CHITANYA RIVERDALE LLP plot (F) (1)_compressed.pdf12 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Plot F Sai Chaitanya.pdf12 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold- Plot F Sai Chaiatnya.pdf12 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert - Sai Chaitanya - F (1).pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sai Chaitanya Plot - F (1).pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Plot F.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold- Plot F.pdf21 Oct 2024
Other - FinanceFile: Format B-New Plot F.pdf31 Jul 2024
Layout approvalFile: scan0287-2_compressed.pdf24 Jul 2024
Building plan approval or NA orderFile: scan0287-2_compressed.pdf24 Jul 2024
PAN CardFile: Sai Chaitanya Riverdale LLP PAN.pdf24 Jul 2024
Copy of the legal title reportFile: 1 Copy of the legal title report (23) (1).pdf24 Jul 2024
Details of encumbrances concerned to FinanceFile: ENCUMBERENCE.pdf24 Jul 2024
Details of encumbrances concerned to LegalFile: ENCUMBERENCE.pdf24 Jul 2024
Copy of Layout Approval (in case of layout)File: scan0287-2_compressed.pdf24 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: scan0287-2_compressed.pdf24 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: scan0287-1 CC.pdf24 Jul 2024
Declaration about Commencement CertificateFile: Declaration Certificate.pdf24 Jul 2024
Declaration in FORM BFile: Form B - Sai Chaitanya - F plot.pdf24 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert - Sai Chaitanya - F (1).pdf24 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2-Plot F.pdf24 Jul 2024
CERSAI detailsFile: Declaration Reg Cersai.pdf24 Jul 2024
Disclosure for secured/unsecured finance availed for the projectFile: Secured Unsecured- Plot F.pdf24 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3- Plot F_compressed.pdf24 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Atul Shinde - DISCLOSURE.pdf24 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Sachin Kadam - DISCLOSURE.pdf24 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Narendrakumar Vishnoi -DISCLOSURE.pdf24 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Zeeshan Sayyed - DISCLOSURE.pdf24 Jul 2024
Proforma of Agreement for saleFile: Plot F-AFS.pdf24 Jul 2024
Proforma of Allotment letterFile: Allotment Letter.pdf24 Jul 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Plot - F, Format - B.pdf24 Jul 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf24 Jul 2024
Deviation Report with respect to Allotment letterFile: Deviation Rep-Allo Letter.pdf24 Jul 2024
Deviation Report with respect to model copy of AgreementFile: Deviation - AGREEMENT TO SALE.pdf24 Jul 2024
Other - LegalFile: SALE DEED SAI CHAITANYA LLP (1)_compressed-1-15.pdf24 Jul 2024
Other - LegalFile: SALE DEED SAI CHAITANYA LLP (1)_compressed-16-30.pdf24 Jul 2024
Other - LegalFile: SALE DEED SAI CHAITANYA LLP (1)_compressed-31-48.pdf24 Jul 2024
Other - TechnicalFile: Declaration Cum Undertaking .pdf24 Jul 2024

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI CHAITANYA RIVERDALE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dudulgaon13,700+ in Pune

2 kmSAI CHAITANYA RIVERDALECompleted 55Lapsed / revoked 25Other 82Dot size: filed unitsN

Filed coordinates, straight-line distance. 162 registered projects within 2 km.

Builder: M/s Sai Chaitanya Riverdale llp

M/s Sai Chaitanya Riverdale llp has 2 registrations on MahaRERA, including Sai Chaitanya Riverdale and SAI CHAITANYA RIVERDALE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SAI CHAITANYA RIVERDALE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAI CHAITANYA RIVERDALE is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI CHAITANYA RIVERDALE?

The registered promoter entity is M/s Sai Chaitanya Riverdale llp, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI CHAITANYA RIVERDALE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAI CHAITANYA RIVERDALE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI CHAITANYA RIVERDALE?

The professionals named in the filing: Architect: Ms Patil and Bugade Associates; Engineer: Rutuja Jagdale; Chartered Accountant: CA J S Desai and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI CHAITANYA RIVERDALE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI CHAITANYA RIVERDALE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI CHAITANYA RIVERDALE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.