Home / Browse projects / Gandhinagar, Gujarat / SAHJANAND SENTOSSA

Valid until 31 Jul 2027 Mixed Development project

SAHJANAND SENTOSSA

By AKSHAR REALITY

RG-GJ-14301 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11000/031222 · Last updated on GujRERA portal: 4 Jul 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2027Possession promisedno revision filed
30 of 81Construction stages doneacross 9 buildings; furthest along: Sanitary fittings within the flats, 89%
195 of 325Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SAHJANAND SENTOSSA is a Mixed Development project by AKSHAR REALITY in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11000/031222 on 3 Dec 2022. Possession is promised by 31 Jul 2027. 130 of the 325 units on this registration are recorded sold or booked, and 30 of 81 construction stages are filed complete.

At a glance

Project

  • NameSAHJANAND SENTOSSA
  • TypeMixed Development
  • Location
    • SURVEY NO 448
    • F P NO 191
    • TP SCHEME NO 16 (PETHAPUR)
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11000/031222
  • ReraGenie IDRG-GJ-14301

Builder

  • NameAKSHAR REALITY
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2022PromisedJul 2027

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2027
  • Registered on3 Dec 2022
  • Promised completion31 Jul 2027
  • Revised completionNone
  • Buildings9 building records
  • Documents filed38 files

Current status

40%130 of 325 units booked
25.1%Of the estimated cost spent so far

Figures as on 4 Jul 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK E---28028
BLOCK F---28028
BLOCK G---28028
BLOCK H---44044
BLOCK I---44044
BLOCK A---284169
BLOCK B---28028
BLOCK C---28028
BLOCK D---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building9

As on 4 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 81 construction stages are filed complete across 9 buildings. The stage furthest along is Sanitary fittings within the flats, at 89%.

BLOCK E74%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor86%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats29%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing18%
BLOCK F81%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats89%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing18%
BLOCK G56%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats88%
Sanitary fittings within the flats18%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing11%
BLOCK H25%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure27%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK I39%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats45%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks9%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK A43%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats62%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK B42%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
BLOCK C49%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats88%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks38%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing18%
BLOCK D52%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing21%

Progress on shared amenities23

As on 4 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes0%
Compound wallYes0%
Plinth protectionYes0%
Water tankYes0%
Other requirementsYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,746 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 54.19 cr
Cost incurredRs 13.60 cr
Spent of the estimate25.1%
BuildingWingEstimatedIncurred
BLOCK HNARs 9.26 crRs 92.58 lakh
BLOCK INARs 9.26 crRs 92.58 lakh
BLOCK GNARs 6.17 crRs 2.16 cr
BLOCK ANARs 4.92 crRs 1.23 cr
BLOCK BNARs 4.92 crRs 1.23 cr
BLOCK CNARs 4.92 crRs 1.48 cr
BLOCK DNARs 4.92 crRs 1.48 cr
BLOCK ENARs 4.92 crRs 2.46 cr
BLOCK FNARs 4.92 crRs 1.72 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTHE GRID-Vishwajeet Hada
EngineerUmang J Patel

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA11000/031222 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)4 Jul 2024
Engineer's certificate annexure4 Jul 2024
RERA registration certificate3 Dec 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Architect's certificate (Form 1)-

How this compares with Gandhinagar

40%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SAHJANAND SENTOSSA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmSAHJANAND SENTOSSAOther 62Dot size: filed unitsN

Filed coordinates, straight-line distance. 62 registered projects within 2 km.

Builder: AKSHAR REALITY

AKSHAR REALITY has 1 registration on GujRERA, including SAHJANAND SENTOSSA. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SAHJANAND SENTOSSA is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SAHJANAND SENTOSSA?

The registered promoter entity is AKSHAR REALITY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SAHJANAND SENTOSSA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAHJANAND SENTOSSA?

The professionals named in the filing: Architect: THE GRID-Vishwajeet Hada; Engineer: Umang J Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAHJANAND SENTOSSA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAHJANAND SENTOSSA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAHJANAND SENTOSSA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.