ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / SAHAJANAND SKY

Valid until 30 Sep 2023 Mixed Development project

SAHAJANAND SKY

By Akshar Corporation

RG-GJ-58264 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05552/EX1/020323 · Last updated on GujRERA portal: 30 Sep 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2023Possession promisedmoved 11 months from the original
24 of 24Construction stages doneacross 4 buildings; every applicable stage filed complete
4 of 119Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

SAHAJANAND SKY is a Mixed Development project by Akshar Corporation in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05552/EX1/020323 on 13 Jun 2019. Possession is promised by 30 Sep 2023. The completion date has moved by 11 months from the original filing. 115 of the 119 units on this registration are recorded sold or booked, and 24 of 24 construction stages are filed complete.

At a glance

Project

  • NameSAHAJANAND SKY
  • TypeMixed Development
  • Location
    • Survey No. 845/1 and 846
    • NR.SHIV ADESH
    • VAVOL
    • VAVOL
    • Gandhinagar
    • 382016
  • Pincode382016
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05552/EX1/020323
  • ReraGenie IDRG-GJ-58264

Builder

  • NameAkshar Corporation
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →
  • Past their filed date2

Key dates

this monthRegisteredJun 2019First promiseOct 2022Revised toSep 2023

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2023
  • Registered on13 Jun 2019
  • Promised completion30 Sep 2023
  • Revised completionRevised to 30 Sep 2023 (originally 1 Oct 2022)
  • Buildings4 building records
  • Documents filed44 files

Current status

97%115 of 119 units booked
100.0%Of the estimated cost spent so far

Figures as on 30 Sep 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block-A---26733
Block-B---26632
Block-C---27027
Block-D---27027

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 30 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 24 construction stages are filed complete across 4 buildings.

Block-A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block-B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block-C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block-D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,371 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 11.88 cr
Cost incurredRs 11.88 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Block-ANARs 2.97 crRs 2.97 cr
Block-BNARs 2.97 crRs 2.97 cr
Block-CNARs 2.97 crRs 2.97 cr
Block-DNARs 2.97 crRs 2.97 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectThe Grid Architrecs- Snehal Suthar
EngineerUMANG J. PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05552/EX1/020323Applied Dec 2022; approved Mar 2023

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05552/EX1/020323 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)30 Sep 2023
Engineer's certificate (Form 2)30 Sep 2023
Engineer's certificate annexure30 Sep 2023
Accountant's certificate (Form 3)30 Sep 2023
Site photograph, Block-A30 Sep 2023
Site photograph, Block-B30 Sep 2023
Site photograph, Block-C30 Sep 2023
Site photograph, Block-D30 Sep 2023
RERA registration certificate13 Jun 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

97%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 11 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SAHAJANAND SKY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near VAVOL1,600+ in Gandhinagar

2 kmSAHAJANAND SKYOther 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: Akshar Corporation

AKSHAR CORPORATION has 2 registrations on GujRERA, including AKSHAR PLATINIUM and SAHAJANAND SKY. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SAHAJANAND SKY is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SAHAJANAND SKY?

The registered promoter entity is Akshar Corporation, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SAHAJANAND SKY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAHAJANAND SKY?

The professionals named in the filing: Architect: The Grid Architrecs- Snehal Suthar; Engineer: UMANG J. PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAHAJANAND SKY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAHAJANAND SKY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAHAJANAND SKY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.