Home / Browse projects / Raigarh, Maharashtra / SAGAR SARGAM RESIDENCY
SAGAR SARGAM RESIDENCY
RG-MH-39383 · RERA P52000009713 · Last updated on MahaRERA portal: 16 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 27 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAGAR SARGAM RESIDENCY is a Residential / Group Housing project by Shree Tulsi Developes in Raigarh, Maharashtra, registered with MahaRERA as P52000009713 on 22 Aug 2017. Possession is promised by 31 Mar 2027. The completion date has moved by 27 months from the original filing. 48 of the 127 units on this registration are recorded sold or booked, and 33 of 55 construction stages are filed complete.
At a glance
Project
- NameSAGAR SARGAM RESIDENCY
- TypeResidential / Group Housing
- Location
- Survey No-6 and H No-5
- Halivali Karjat
- Haliwali
- Karjat
- Raigarh
- 410201
- Pincode410201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000009713
- ReraGenie IDRG-MH-39383
Builder
- NameShree Tulsi Developes
- Entity typePartnership
- PartnersDevendrakumar Shivlal Patel, Daivik Jayantibhai Patel, Chintankumar Premjibhai Patel, Suresh Natwarbhai Patel, Ashesh Jethalal Patel
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Aug 2017
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 30 Dec 2024)
- Buildings5 building records
- Documents filed118 files
Current status
Figures as on 16 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building No 1 Wing A | NA | 8 | 4 | 49 | 4 | 53 |
| Building No 2 Wing B | NA | 6 | 5 | 28 | 0 | 28 |
| Building No 3 Wing C | NA | 6 | 4 | 18 | 0 | 18 |
| Building No 4 Wing D | NA | 5 | 0 | 26 | 0 | 26 |
| Building No 5 Wing E | NA | 2 | 0 | 2 | 0 | 2 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 16 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
33 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Staircases, at 90%.
Building No 1 Wing A46%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 2 Wing B77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Building No 3 Wing C77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Building No 4 Wing D77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Building No 5 Wing E80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 16 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 75% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 75% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Tawale Builders | ambhiwali bk | Raigarh |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building No 1 Wing A | NA | Rs 4.75 cr | Rs 2.81 cr |
| Building No 4 Wing D | NA | Rs 2.04 cr | Rs 2.00 cr |
| Building No 2 Wing B | NA | Rs 1.50 cr | Rs 1.48 cr |
| Building No 3 Wing C | NA | Rs 1.11 cr | Rs 1.09 cr |
| - | NA | Rs 40.50 lakh | Rs 22.50 lakh |
| Building No 5 Wing E | NA | Rs 14.50 lakh | Rs 14.20 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | STRUCTILIS CONSULTANTS PVT LTD GIRISH THAKARE |
| Engineer | K R PATEL & ASSOCIATES Kamlesh R Patel |
| Chartered Accountant | BHAVIK JAYANTILAL VELANI |
| Chartered Accountant | SWATI SUDHENDU PATEL |
| Chartered Accountant | Sudhir Patel & Associates |
| Partner | Role in project |
|---|---|
| Shree Tulsi Developes | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe date of completion of our project is 30-12-2024 but considering the following reasons we request your honor to grant us one year of extension to complete the entire process of obtaining Occupation Certificate1) 1) Revised Building Plan: The original construction was approved for a G+4 structure in, A-Wing (Building No-1). Under the new UDCPR-2020 regulations, we applied for and successfully obtained additional FSI, which allowed us to revise the plan to a G+7 structure. This revised plan was approved, and a new Commencement Certificate (CC) was issued on 9th May 2023. 2) Additional Constru
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Feb 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2027
Documents filed118
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: Form 5_FY 25-26.pdf | 16 Jun 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 2 May 2026 |
| Withdrawal Update Form 1File: RERA FORM 1 March-2026.pdf | 2 May 2026 |
| Withdrawal Update Form 1File: RERA FORM 1 March-2026.pdf | 2 May 2026 |
| Withdrawal Update Form 2File: RERA FORM 2 March-2026.pdf | 2 May 2026 |
| Withdrawal Update Form 2File: RERA FORM 2 March-2026.pdf | 2 May 2026 |
| Withdrawal Update Form 2File: RERA FORM 2 March-2026.pdf | 2 May 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.pdf | 2 May 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.pdf | 2 May 2026 |
| Withdrawal Update Form 3File: FORM-3.pdf | 2 May 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Withdrawal Application.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form3 Withdrawal Application.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form3 Withdrawal Application.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Withdrawal Application.pdf | 27 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Withdrawal Application.pdf | 27 Mar 2026 |
| Withdrawal Update Form 3File: Form3 Withdrawal Application.pdf | 27 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Withdrawal Application.pdf | 23 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Withdrawal Application.pdf | 23 Mar 2026 |
| Withdrawal Update Form 2File: Form2-Withdrawal Application Q1.pdf | 23 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Withdrawal Application.pdf | 23 Mar 2026 |
| Withdrawal Update Form 3File: Form3-Withdrawal Application Q1.pdf | 23 Mar 2026 |
| Withdrawal Update Form 3File: Form3-Withdrawal Application Q1.pdf | 23 Mar 2026 |
| Withdrawal Update Form 1File: Form1-Withdrawal Application Q1.pdf | 13 Mar 2026 |
| Withdrawal Update Form 1File: Form1-Withdrawal Application Q1.pdf | 13 Mar 2026 |
| Withdrawal Update Form 1File: Form1-Withdrawal Application Q1.pdf | 13 Mar 2026 |
| Withdrawal Update Form 2File: FORM-2.pdf | 13 Mar 2026 |
| Withdrawal Update Form 2File: Form2-Withdrawal Application Q1.pdf | 13 Mar 2026 |
| Withdrawal Update Form 2File: Form2-Withdrawal Application Q1.pdf | 13 Mar 2026 |
| Withdrawal Update Form 3File: FORM 3 CA Certi STD (1).pdf | 13 Mar 2026 |
| Withdrawal Update Form 3File: FORM 3 CA Certi STD (1).pdf | 13 Mar 2026 |
| Withdrawal Update Form 3File: Form3-Withdrawal Application Q1.pdf | 13 Mar 2026 |
| Form 5 (FY 2024-2025)File: Uploded Form-5.pdf | 7 Oct 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: TULSI RERA FORM 1.pdf | 26 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Form-1.pdf | 25 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Form-1.pdf | 25 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 Form-1.pdf | 25 Mar 2025 |
| Certificates of CA (Form 3)File: 1 Form-3.pdf | 25 Mar 2025 |
| Certificates of CA (Form 3)File: 2 Form-3.pdf | 25 Mar 2025 |
| Certificates of CA (Form 3)File: 3 Form-3.pdf | 25 Mar 2025 |
| Certificates of CA (Form 3)File: 4 Form-3.pdf | 25 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Form-2.pdf | 25 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form-2.pdf | 25 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Form-2.pdf | 25 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Form-2.pdf | 25 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 22 Mar 2025 |
| Declaration in FORM BFile: Form B RERA Promoter.pdf | 20 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold and Unsold Q3 FY-24-25.pdf | 12 Feb 2025 |
| Proforma of Allotment letterFile: Draff of Allotment Letter.pdf | 26 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Letter -Finance.pdf | 24 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Letter -Legal.pdf | 24 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 24 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 24 Dec 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: No Escrow on RERA Bank Act Format-A.pdf | 24 Dec 2024 |
| Deviation Report with respect to Allotment letterFile: No Deviation in LoA Declaration.pdf | 24 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance Letter -Legal.pdf | 24 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance Letter -Finance.pdf | 24 Dec 2024 |
| Deviation Report with respect to model copy of AgreementFile: No Deviation in AFS Declaration.pdf | 24 Dec 2024 |
| Proforma of Agreement for saleFile: Agreement for sale.pdf | 24 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 Partner Interest declaration.pdf | 24 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 17 Dec 2024 |
| Certificates of CA (Form 3)File: Form-3.pdf | 17 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 RERA 02042024.pdf | 17 Dec 2024 |
| Certificates of CA (Form 3)File: Sold Unsold Inventory Q1 FY 24-25.pdf | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Q1 FY 24-25.pdf | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Q2 FY 24-25.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SCAN Form 5_FY 23-24.pdf | 10 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A- FY 21-22.pdf | 10 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- FY 22-23.pdf | 10 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- FY 23-24.pdf | 10 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Q4 FY 23-24 DISCLOSURE OF SOLD - BOOKED INVENTORY.pdf | 3 May 2024 |
| Disclosure of sold/ booked inventoryFile: Q1 DISCLOSURE OF SOLD - BOOKED INVENTORY-1.pdf | 18 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Q2 DISCLOSURE OF SOLD - BOOKED INVENTORY.pdf | 18 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Q3 DISCLOSURE OF SOLD - BOOKED INVENTORY.pdf | 18 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Tawle Builders.pdf | 18 Mar 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 118 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAGAR SARGAM RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Halivali Karjat5,900+ in Raigarh
Filed coordinates, straight-line distance. 87 registered projects within 2 km.
Bellezza Woods
DOTOM BUILD SQUARE
Winds of Calm
Eiffel Lifespaces Pvt Ltd
PURANIK CITY SECTOR 2
Puranik Builders Limited
Foothills of Matheran P - 2
HOABL Impactum Land Private Limited
FLORENCE TOWN
BRIGHT DEVELOPERS
The Destination
DOVE BUILDMART PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: Shree Tulsi Developes
Shree Tulsi Developes has 1 registration on MahaRERA, including SAGAR SARGAM RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if SAGAR SARGAM RESIDENCY is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAGAR SARGAM RESIDENCY?
The registered promoter entity is Shree Tulsi Developes, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAGAR SARGAM RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAGAR SARGAM RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAGAR SARGAM RESIDENCY?
The professionals named in the filing: Architect: STRUCTILIS CONSULTANTS PVT LTD GIRISH THAKARE; Engineer: K R PATEL & ASSOCIATES Kamlesh R Patel; Chartered Accountant: BHAVIK JAYANTILAL VELANI; Chartered Accountant: SWATI SUDHENDU PATEL; Chartered Accountant: Sudhir Patel & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAGAR SARGAM RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.