Home / Browse projects / Mumbai Suburban, Maharashtra / Rustomjee Summit
Rustomjee Summit
RG-MH-11416 · RERA P51800003590 · Last updated on MahaRERA portal: 3 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 7 complaints at MahaRERA
- Completion date moved by 72 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Rustomjee Summit is a Residential / Group Housing project by KEYSTONE REALTORS LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003590 on 5 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 72 months from the original filing. 231 of the 233 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 7 complaints are on record with the regulator.
At a glance
Project
- NameRustomjee Summit
- TypeResidential / Group Housing
- Location
- Dattapada Road
- Rajendra Nagar
- Borivali
- Mumbai Suburban
- 400066
- Pincode400066
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003590
- ReraGenie IDRG-MH-11416
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Aug 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2021)
- Buildings1 building record
- Documents filed127 files
Current status
Figures as on 3 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Summit | NA | 44 | 44 | 233 | 0 | 233 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Summit: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Summit | NA | Rs 338.45 cr | Rs 338.45 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vivek Bhole Architects Pvt Ltd |
| Architect | Miti Design and Planners |
| Architect | Manish D Savant |
| Engineer | J W Consultant LLP |
| Engineer | Nitin Bhaskar |
| Chartered Accountant | V A Shimpi & Associates |
| Partner | Role in project |
|---|---|
| KEYSTONE REALTORS LIMITED | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs there was delay in procuring further permissions required for completing construction of this project, the Promoter needs extension of one years time to complete the said project.
Reason as filed by the promoter1. The said Real Estate Project has received part occupation certificate dated 18th August, 2023 with regards to Basement + Ground + 1st to 38th upper floors. Full Occupation Certificate for all floors of the said Real Estate Project particularly occupation certificate for the 39th and 40th floors is yet to be procured owing to the following pre-requisites for the issuance of full Occupation Certificate for the said Real Estate Project insisted upon by MHADA, which are enumerated in the MHADA Consent letter to Occupation Certificate dated 11th August 2023. A) Execution and registration of Deed
Reason as filed by the promoterThe Project comprises of Basement + Ground + 1st to 40th upper floors. The Occupation Certificate for all the sanctioned floors have been received except Flat No. 3906 on the 39th Floor and Flat No. 4003 on the 40th Floor. The Occupation Certificate for the said two Flats has not been issued owing to the condition imposed by Maharashtra Housing and Area Development Authority (“MHADA”) for the amalgamation of the 2 (two) erstwhile societies, being Rajendra Nagar Co-operative Housing Ltd. and Rajendra Nagar Manjunath Co-operative Housing Society Limited (“said Societies”) who along with their re
Litigation declared8
| Case | Court | Status |
|---|---|---|
| 1009/2015 | City Civil Court Dindoshi | pending for hearing of Notice of Motion |
| 1676/2016 | City Civil Court Dindoshi | INTERNAL DISPUTE BETWEEN MEMBERS OF THE SOCIETY AT THE STAGE FOR TAKING STEPS TO BRING ON RECORD HEI |
| 9687/1999 | City Civil Court Mumbai | INTERNAL DISPUTES BETWEEN MEMBERS OF SOCIETY CHAMBER SUMMONS ALLOWED NOW PENDING FOR TAKING STEPS |
| 119/2014 | Small Causes Court Bandra | INTERSE DIPUTE BETWEEN MEMBERS OF SOCIETY Decree holder has taken out the present applicaiton for ex |
| 34238/2018 | HIGH COURT BOMBAY | INTERNAL DISPUTE BETWEEN MEMBERS OF THE SOCIETY MATTER WILL BE LISTED IN DUE COURSE |
| 347/2019 | City Civil Court at DINDOSHI | interse dispute between FAMILY MEMBERS in respect of unit in Rehab builidng pending for service |
| CC/165/2020/2020 | NCDRC | COMAPLAINT FILED BY ALLOTTEE BEFORE CONSUMER FORUM IN RESPECT OF ONE OF THE UNIT IN THE PROJECT MATT |
| RPWL 2923 OF 2020/2020 | BOMBAY HIGH COURT | MATTER WILL BE LISTED IN DUE COURSE |
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000068145 | Rishi Chintaman Mali | Keystone Realtors Pvt. Ltd. | 19/02/2019 |
| CC006000000078529 | Chirag Shah and Deepali Shah | Keystone Realtors Pvt Ltd | 25/04/2019 |
| CC006000000110848 | AMIT SANGHAVI | Keystone Realtors Pvt. Ltd. | 13/09/2019 |
| CC006000000193180 | KEYSTONE REALTORS PRIVATE LIMITED | MRS SACHITA PARAB | 28/04/2020 |
| CC006000000196135 | Keystone Realtors Pvt. Ltd | Sonal Tejas Shah | 25/02/2021 |
| CC12501232 | KEYSTONE REALTORS LIMITED | M s Cinema on the Web | 14/04/2025 |
| CC12502389 | sameer sonurlekar | KEYSTONE REALTORS LIMITED | 14/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Sep 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 7 May 2024
Documents filed127
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: PART_OC_PLANS_Part1.pdf | 3 Sep 2026 |
| Building plan approvalFile: PART_OC_PLANS_Part2.pdf | 3 Sep 2026 |
| Withdrawal Update Form 1File: RERA FORM 1 Architect Certificate upto 30062025.pdf | 3 Sep 2026 |
| Withdrawal Update Form 1File: RERA FORM 1 Architect Certificate upto 31122025.pdf | 3 Sep 2026 |
| Withdrawal Update Form 1File: RERA FORM 1 Architect Certificate upto 31122025.pdf | 3 Sep 2026 |
| Withdrawal Update Form 1File: RERA FORM 1 Architect Certificate upto 31032026.pdf | 3 Sep 2026 |
| Withdrawal Update Form 1File: RERA FORM 1 Architect Certificate upto 30062026.pdf | 3 Sep 2026 |
| Withdrawal Update Form 2File: June 2025.pdf | 3 Sep 2026 |
| Withdrawal Update Form 2File: Sep 2025.pdf | 3 Sep 2026 |
| Withdrawal Update Form 2File: Dec 2025.pdf | 3 Sep 2026 |
| Withdrawal Update Form 2File: March 2026.pdf | 3 Sep 2026 |
| Withdrawal Update Form 2File: June 2026.pdf | 3 Sep 2026 |
| Withdrawal Update Form 3File: 2025 07 20 RG KRL PROJECTS FORM 3 JUNE 2025 SUMMIT.pdf | 3 Sep 2026 |
| Withdrawal Update Form 3File: 2025 10 24 RG KRL PROJECTS RERA FORM 3 SUMMIT.pdf | 3 Sep 2026 |
| Withdrawal Update Form 3File: 2026 01 17 RG KRL PROJECTS FORM 3 DEC 2025 SUMMIT.pdf | 3 Sep 2026 |
| Withdrawal Update Form 3File: 2026 04 20 RG KRL PARA SUMMIT FORM 3 MAR 2026 SUMMIT.pdf | 3 Sep 2026 |
| Withdrawal Update Form 3File: 2026 07 18 RG KRL FORM 3 JUNE 2026 SUMMIT.pdf | 3 Sep 2026 |
| Form 2A (FY 2025-2026)File: Form 2A FY25 26 Summit Projec.pdf | 3 Sep 2026 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - SUMMIT.pdf | 19 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Summit June-2024.pdf | 13 Aug 2024 |
| Certificates of CA (Form 3)File: 2024 07 20 RG KRL PROJECTS RERA JUNE 2024- SUMMIT.pdf | 13 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Summit - Form 2 - Engineer Certificate - Dec 2023.pdf | 13 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Summit.pdf | 13 May 2024 |
| Certificates of CA (Form 3)File: 2024 04 20 RG KRL PROJECTS FORM 3 MAR 2024 SUMMUT.pdf | 11 May 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 9978_OCC_Signed.pdf | 7 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Summit December 2023.pdf | 20 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Summit March 2024.pdf | 20 Apr 2024 |
| Certificates of CA (Form 3)File: fORM 3 rera SUMMIT_11zon.pdf | 18 Mar 2024 |
| Declaration about Commencement CertificateFile: RERA Declaration about CC Summit.pdf | 12 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: fORM 2 sEPTEMBER 2023.pdf | 26 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Scan 1.pdf | 26 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Summit Disclosure-1.pdf | 26 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 Summit September 2023_11zon.pdf | 18 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Summit RERA FORM 1 Architect Certificate upto Sept 2023.pdf | 23 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Summit March 2023.pdf | 30 Sep 2023 |
| Certificates of CA (Form 3)File: 2023 08 14 RG KRL PROJECTS RERA JUNE 2023- SUMMIT_11zon.pdf | 21 Sep 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OCCUPATION CERTIFICATE Summit.pdf | 18 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Summit March 2023.pdf | 25 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Summit June 2023.pdf | 25 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3 Summit March 2023.pdf | 25 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Summit Form 2 Dec 2019.pdf | 6 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Summit Form 2 March 2020.pdf | 6 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Summit Form 2 June 2020.pdf | 6 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Summit Form 2 Sept 2020.pdf | 6 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 17 18 19 compressed.pdf | 6 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Summit March 2018.pdf | 5 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Summit March 2019.pdf | 5 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Summit March 2020.pdf | 5 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Summit October 2020.pdf | 5 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Summit March 2018 compressed.pdf | 5 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Summit September 2018 compressed.pdf | 5 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Summit December 2018 compressed.pdf | 5 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Summit March 2019 compressed.pdf | 5 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Summit June 2019 compressed.pdf | 5 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Summit Dec 2022 compressed.pdf | 5 Mar 2023 |
| Certificates of CA (Form 3)File: Summit Form 3 Dec 2019 compressed.pdf | 3 Mar 2023 |
| Certificates of CA (Form 3)File: Summit Form 3 March 2020 compressed.pdf | 3 Mar 2023 |
| Certificates of CA (Form 3)File: Summit Form 3 June 2020 compressed.pdf | 3 Mar 2023 |
| Certificates of CA (Form 3)File: Summit Form 3 September 2020 compressed.pdf | 3 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate Sept 2021.pdf | 21 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 Summit Dec 2022 compressed.pdf | 21 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Summit April 2021.pdf | 31 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SUMMIT June 2022.pdf | 29 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Summit MARCH 2022.pdf | 29 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Summit Form 2 1st Oct 2021.pdf | 29 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUNE 2021 Summit.pdf | 29 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3 Summit SEPT 2022.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: FORM 3 Summit JUNE 2022.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 Summit March 2022.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 Summit Dec 21.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 SUMMIT Sept 2021.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 Summit June 2021.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 SUMMIT March 2021.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 Summit June 2019.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 Summit March 2019.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 SUMMIT December 2018.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 SUMMIT sept 2018.pdf | 28 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 Summit March 2018.pdf | 28 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate March 2021.pdf | 27 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate June 2021.pdf | 27 Jan 2023 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Rustomjee Elita | D N Nagar Muncipal School Road Gharkul Society Indira Nagar Four Bunglows Andheri West Mumbai - 400053 | 169 | Completed | Jan 2016 | Late, Feb 2016 |
| ELITA | DN Nagar Muncipal School Road Gharkul Society Indira Nagar Four Bungalows Andheri West Mumbai-400053 | 169 | Completed | Jan 2016 | Late, Feb 2016 |
| Rustomjee Sangam | Junction of S.V.Road and Sai Baba Road Santacruz West Mumbai 400054 | 67 | Completed | Feb 2014 | Late, Sep 2014 |
| Rustomjee Oriana | Road No 7 Gandhi Nagar Bandra East Mumbai - 400051 | 140 | Completed | Dec 2013 | Late, Nov 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 18 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 127 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Rustomjee Summit on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Rajendra Nagar6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 400 registered projects within 2 km.
Shraddha Park City
Shraddha Prime Projects Limited
GREENAIRY
SAROJ LANDMARK REALTY LLP
Sky City Tower H
Incline Realty Private Limited
Sky City Tower G
Incline Realty Private Limited
SHEETAL REGALIA
D G S TOWNSHIP PRIVATE LIMITED
JANGID ELYSIUM
IMPRINT CONSTRUCTION PRIVATE LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: KEYSTONE REALTORS LIMITED
KEYSTONE REALTORS LIMITED has 19 registrations on MahaRERA, including Rustomjee Seasons - Wing B and Rustomjee Seasons - Wing C. Its filings disclose 11 earlier MahaRERA projects: declares 6 of 11 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Rustomjee Summit is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Rustomjee Summit?
The registered promoter entity is KEYSTONE REALTORS LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Rustomjee Summit?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Rustomjee Summit?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Rustomjee Summit?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Rustomjee Summit?
The professionals named in the filing: Architect: Vivek Bhole Architects Pvt Ltd; Architect: Miti Design and Planners; Architect: Manish D Savant; Engineer: J W Consultant LLP; Engineer: Nitin Bhaskar; Chartered Accountant: V A Shimpi & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Rustomjee Summit?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback