ReraGenieLog inGet a buyer report

Home / Browse projects / Amravati, Maharashtra / RUKHMINI HEIGHTS

Registered No litigation declared Residential / Group Housing project

RUKHMINI HEIGHTS

By SADANI AND PATURDE BUILDERS LLP

RG-MH-13403 · RERA P50300054194 · Last updated on MahaRERA portal: 27 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Amravati registration emailed to you, free during the pilot beta.
May 2027Possession promisedno revision filed
6 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 30%
31 of 32Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

RUKHMINI HEIGHTS is a Residential / Group Housing project by SADANI AND PATURDE BUILDERS LLP in Amravati, Maharashtra, registered with MahaRERA as P50300054194 on 3 Jan 2024. Possession is promised by 31 May 2027. 1 of the 32 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameRUKHMINI HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • PLOT NO 3 AND 4 S.NO 42/1/A
    • MAUJE BENODA
    • Amravati (M Corp.)
    • Amravati
    • 444908
  • Pincode444908
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50300054194
  • ReraGenie IDRG-MH-13403

Builder

  • NameSADANI AND PATURDE BUILDERS LLP
  • Entity typeOthers
  • Named personsSURESHKUMAR GPOIKISAN SADANI, NITIN MOTIRAM PATURDE

Key dates

this monthRegisteredJan 2024PromisedMay 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jan 2024
  • Promised completion31 May 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed63 files

Current status

3%1 of 32 units booked
61.3%Work done, per cost certificate

Figures as on 27 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RUKHMINI HEIGHTSNA8832032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 30%.

RUKHMINI HEIGHTS: 58% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed69

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots69
Closed/Covered55
Open Space14

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area781 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Feb 2026

Approvals and building plan

Sanctioning authorityAmravati Municipal Corporation
Permissible FSI2477.23
Proposed, not sanctioned2,477 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEAR SHYAM TALKIES AMRAVATI
Estimated costRs 11.40 cr
Cost incurredRs 6.99 cr
Work done61.32%
BuildingWingEstimatedIncurred
RUKHMINI HEIGHTSNARs 5.70 crRs 3.50 cr
-NARs 5.70 crRs 3.50 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANJU SAKET Sadani
EngineerSaurabh Ingole
Chartered AccountantMAHESH LADDHA
PartnerRole in project
SADANI AND PATURDE BUILDERS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 May 2027

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect.pdf27 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 2File: Engineer.pdf27 Apr 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 3File: SADANI FORM 3_merged_11zon.pdf27 Apr 2026
Withdrawal Update Form 3File: form 3CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 3File: form 3CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 3File: form 3CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 3File: form 3CERTIFICATE.pdf27 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE.pdf27 Apr 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CHARTERED ACCOUNTANTS CERTIFICATE.pdf21 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect_11zon.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate_11zon (1).pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_11zon.pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf13 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer.pdf19 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Certificate.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SADANI FORM 3_merged_11zon.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certiicate.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountant Certificate_11zon.pdf20 Apr 2024
Other - TechnicalFile: Self Declaration.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fORM 3 SADANI.pdf28 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format A.pdf28 Dec 2023
Other - TechnicalFile: Gmail.pdf28 Dec 2023
Layout approvalFile: LAYOUT APPROVAL.pdf6 Dec 2023
Building plan approvalFile: Sanction plan.pdf6 Dec 2023
PAN CardFile: PAN CARD.pdf6 Dec 2023
Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL.pdf6 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanction plan.pdf6 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_11zon.pdf6 Dec 2023
Proforma of Agreement for saleFile: DRAFT_Agreement RERA.pdf6 Dec 2023
Proforma of Allotment letterFile: DRAFT ALLOTMEMT LETTER .pdf6 Dec 2023
Building plan approvalFile: NA ORDER.pdf5 Dec 2023
Layout approvalFile: Sanction plan.pdf5 Dec 2023
Copy of the legal title reportFile: legal tittle report_11zon.pdf5 Dec 2023
Details of encumbrances concerned to FinanceFile: no legal and finacial encumarance.pdf5 Dec 2023
Details of encumbrances concerned to LegalFile: no legal and finacial encumarance.pdf5 Dec 2023
Copy of Layout Approval (in case of layout)File: Sanction plan.pdf5 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER.pdf5 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf5 Dec 2023
Declaration about Commencement CertificateFile: format D.pdf5 Dec 2023
Declaration in FORM BFile: Form B_11zon.pdf5 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architech certificate.pdf5 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: enginer certificate.pdf5 Dec 2023
CERSAI detailsFile: CERSAI declaration.pdf5 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: annexure A.pdf5 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format a.pdf5 Dec 2023
Deviation Report with respect to Allotment letterFile: decelaration regarding deviation.pdf5 Dec 2023
Deviation Report with respect to model copy of AgreementFile: decelaration regarding deviation.pdf5 Dec 2023
Other - LegalFile: certificate of incorporation.pdf5 Dec 2023
Other - LegalFile: 712.pdf5 Dec 2023

How this compares with Amravati

3%of this project is bookeddistrict median 0%
8%of Amravati projects moved their completion datethis one has not
33%of Amravati registrations have lapsed or been cancelledthis one is on the register

Computed across the 450+ Amravati projects on ReraGenie, from their own filings.

Keep RUKHMINI HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAUJE BENODA450+ in Amravati

2 kmRUKHMINI HEIGHTSCompleted 9Lapsed / revoked 5Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: SADANI AND PATURDE BUILDERS LLP

SADANI AND PATURDE BUILDERS LLP has 1 registration on MahaRERA, including RUKHMINI HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Amravati district page.

Frequently asked questions

What are my rights if RUKHMINI HEIGHTS is delayed beyond 31 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RUKHMINI HEIGHTS?

The registered promoter entity is SADANI AND PATURDE BUILDERS LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RUKHMINI HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RUKHMINI HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RUKHMINI HEIGHTS?

The professionals named in the filing: Architect: MANJU SAKET Sadani; Engineer: Saurabh Ingole; Chartered Accountant: MAHESH LADDHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RUKHMINI HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RUKHMINI HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RUKHMINI HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.